Report to/Rapport au :

 

Environment Committee

Comité de l'environnement

 

and Council / et au Conseil

 

10 May 2011 / le 10 mai 2011

 

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice municipale adjointe, Infrastructure Services and Community Sustainability/Services d 'infrastructure et Viabilité des collectivités

 

Contact Person/Personne ressource : Wayne Newell, General Manager/Directeur général, Infrastructure Services/Services des infrastructures

(613) 580-2424 x16002, Wayne.Newell@ottawa.ca

 

Ward/Quartier 4 – Kanata North/Kanata Nord

Ward/Quartier 5 – West Carleton-March

Ward/Quartier 6 – Stittsville

Ward/Quartier 23 – Kanata South/Kanata Sud

Ref N°: ACS2011-ICS-INF-0006

 

 

SUBJECT:

July 24, 2009 West-end Flooding Investigation ACTION PLAN

 

 

OBJET :

PLAN D’ACTION DE L’ENQUÊTE SUR L’INONDATION DU 24 JUILLET 2009 DANS LE SECTEUR OUEST DE LA VILLE

 

REPORT RECOMMENDATION

 

That the Environment Committee recommend Council approve the Action Plan as outlined in Document 1.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité de l’environnement recommande au Conseil d’approuver le plan d’action tel qu’il est exposé dans le Document 1.

 

 

EXECUTIVE SUMMARY

 

Assumptions and Analysis

 

Following flooding in the City’s west-end on 24 July 2009, Council directed City staff to undertake a comprehensive investigation to confirm the cause of flooding and identify solutions to reduce the risk of future flooding occurrences.  The investigation was carried out in five phases: Phase 1 - Background data collection; Phase 2 - Assessment and problem definition; Phase 3 - Identification and evaluation of alternative solutions; Phase 4 - Development and approval of an action plan; and Phase 5 - Implementation of the approved action plan.

 

This report details the steps taken to date, puts forward an action plan for Council approval (Document 1), and reports on a two-stage peer review on the recommended approach for addressing flooding in the impacted areas.

 

The scope of the investigation included all west end locations that experienced flooding.  The focus was on affected areas where flooding resulted in damage to private properties or to City infrastructure. 

 

The investigation included public input, field assessments, detailed topographical surveys, fog testing of sanitary sewer systems to confirm the presence of cross-connections or undesired infiltration sources, basement elevation surveys and camera inspections of the sewer system at selected locations.  For all areas, the investigation focused on the evaluation of conceptual technical solutions using detailed hydraulic models (adjusted to recreate the 24 July 2009 conditions) that were developed for the affected areas.  These models were used to confirm modes of flooding and assess various alternative solutions to select preferred measures.

 

Given the extent of flooding and complexities involved in the Glen Cairn area, the investigation followed the Class Environmental Assessment (EA) process.  Through this comprehensive process, a number of alternative solutions were evaluated and preferred solutions identified.  This information was presented at 2 public meetings.  In addition, the evaluation was subject to a Value Engineering process, comprised of recognized experts in the field undertaking an independent assessment of the alternative solutions.  A Public Advisory Committee (PAC) was also established and was instrumental in providing information related to the flooding event and ensured information presented to the public was communicated effectively.  Further, the investigation was also subject to a Peer Review by Greenland International Consulting Ltd,  coordinated by the City Manager and Deputy City Manager, Infrastructure Services and Community Sustainability (ISCS).

 

In total, $32M has been identified for improvements to reduce the risk of flooding in the City’s west-end.  As directed by Council, the City has already begun implementing measures that will increase the level of protection and reduce the risk of future occurrences.  The intent is to continue to implement flood protection measures in a timely manner. 

 

Financial Implications

 

To support the implementation of the recommended flooding improvement measures, $4M was approved as part of the 2010 Capital Budget (account 905553), an additional $6.8M as part of the 2011 Capital Budget and the balance will be subject to approval of the 2012 Draft Capital Budget.

 


 

Public Consultation/Input

 

Extensive public consultation has occurred as part of the overall flooding investigation process.  A total of 12 Public Meetings have taken place since the July 24, 2009 flooding event.

 

A Public Advisory Committee was established for the Kanata South area.  This committee was engaged throughout the investigation process and was instrumental in providing information related to the flooding event and ensure information presented to the public was communicated in a meaningful way.

 

Further public consultation also took place when the Glen Cairn Environmental Assessment report was filed for the 30-day public review.  This process was completed on 4 April 2011.

 

RÉSUMÉ

 

Hypothèses et analyse

 

En raison des inondations survenues dans l’ouest de la Ville le 24 juillet 2009, le Conseil avait demandé au personnel de la Ville d’entreprendre une enquête approfondie pour confirmer la cause de ces inondations et trouver des solutions permettant de réduire le risque d’inondations futures. Cette enquête a ensuite été menée en cinq phases : phase 1 – collecte des données relatives au contexte; phase 2 – évaluation et détermination du problème; phase 3 – définition et évaluation de solutions de rechange; phase 4 – élaboration et adoption d’un plan d’action; phase 5 – mise en œuvre du plan d’action adopté.

 

Ce rapport décrit en détail les mesures prises à ce jour, propose un plan d’action à faire approuver par le Conseil (document 1) et présente un compte rendu de l’examen professionnel en deux étapes portant sur l’approche recommandée pour régler le problème des inondations dans les zones touchées.

 

L’enquête de la Ville concernait tous les secteurs de l’ouest de la ville qui ont été inondés, l’accent ayant été mis sur les zones où l’inondation avait occasionné des dégâts matériels aux propriétés privées ou aux infrastructures de la Ville.

 

Cette enquête comprenait la consultation du public, des évaluations sur le terrain, des levés topographiques détaillés, de tests de fumée permettant de détecter dans les systèmes d’égout séparatif la présence de raccordements croisés et les sources d’infiltration indésirables, des levés sur la hauteur des sous­sols et des inspections par caméra du réseau d’égouts à des endroits précis. L’enquête était axée sur l’évaluation de solutions techniques et conceptuelles au moyen de modèles hydrauliques détaillés, adaptés pour recréer les conditions présentes le 24 juillet 2009 et élaborés pour les secteurs touchés par les inondations. Ces modèles ont été utilisés pour établir le mécanisme des inondations et évaluer les diverses solutions afin de choisir les mesures à privilégier.

 

Vu l’importance et la complexité des inondations dans le secteur Glen Cairn, l’enquête a été réalisée selon la méthode du processus d’évaluation environnementale de portée générale. Au cours de ce vaste processus, un certain nombre de solutions ont été évaluées, et certaines ont été retenues. Ces informations ont fait l’objet de deux réunions publiques. De plus, ce même processus d’évaluation a fait l’objet d’un processus d’analyse de coûts, dans le cadre duquel des experts reconnus dans leur domaine ont entrepris une évaluation indépendante des solutions. On a également mis sur pied un comité de consultation publique, qui a grandement contribué à fournir des renseignements sur les inondations et à voir à ce que les renseignements présentés au public soient communiqués de manière efficace. L’étude a également fait l’objet d’une évaluation par les pairs réalisée par la société Greenland International Consulting Ltd. et coordonnée par le directeur municipal et la directrice municipale adjointe, Services d’infrastructure et Viabilité des collectivités (SIVC).

 

En tout, le coût des travaux prévus pour réduire les risques d’inondation dans la partie ouest de la ville s’élèvent à 32 millions de dollars. À la demande du Conseil, la Ville a déjà mis en œuvre des mesures dans le but d’améliorer le niveau de protection contre les inondations et de réduire le risque que la situation se répète. L’objectif est de mettre en œuvre les mesures de protection contre les inondations le plus tôt possible.

 

Incidences financières

 

Pour soutenir la mise en œuvre des mesures de protection recommandées pour contrer les inondations, une somme de 4 M$ a été approuvée dans le budget d’immobilisations de 2010 (compte 905553) et 6,8 M$ de plus dans le budget d’immobilisations de 2011. Les montants restants devront être approuvés dans le budget d’immobilisations provisoire de 2012.

 

Consultation publique

 

Une vaste consultation publique s’est déroulée dans le cadre de l’enquête sur l’inondation. En tout, il y a eu douze réunions publiques depuis l’inondation du 24 juillet 2009.

 

Un comité de consultation formé du public a été mis sur pied dans le secteur de Kanata Sud. Ce comité a été impliqué tout au long du processus d’enquête. Il a permis de recueillir de l’information sur l’inondation du 24 juillet et il a vu à ce que les renseignements soient communiqués de façon pertinente à la population.

 

D’autres consultations publiques se sont déroulées lors du dépôt du rapport d’évaluation environnementale de Glen Cairn aux fins d’examen public de 30 jours. Cette démarche a pris fin le 4 avril 2011.

 

 

BACKGROUND

 

On 24 July 2009, parts of the City of Ottawa experienced a significant rainstorm (over 100 mm of rain in a 24-hour period in some areas) resulting in nearly 1,500 flooded basements and sewer backups, overflows at two sewage pumping stations, and seven culvert failures.  These occurred primarily in the City’s west end, mainly in Ward 4 - Kanata North (Beaverbrook), Ward 5 - West Carleton-March (Carp Village), Ward 6 - Stittsville, and Ward 23 - Kanata South (Katimavik and Glen Cairn).  At the direction of Council, an investigation, led by the Infrastructure Services Department (ISD) and supported by several City departments, was initiated to understand why flooding occurred, what can be done to reduce the risk of future occurrences and to implement solutions.

 

The investigation was carried out in five phases: Phase 1 - Background data collection; Phase 2 - Assessment and problem definition; Phase 3 - Identification and evaluation of alternative solutions; Phase 4 - Development and approval of an action plan; and Phase 5 - Implementation of the approved action plan.  The scope of the investigation included all west end locations that experienced flooding.  The focus was on affected areas where flooding resulted in damage to private properties or to City infrastructure.  While heavy rainfall and flooding also occurred in other parts of the City, impacts in other areas was isolated and dispersed.  These isolated cases are subject to separate investigations on an individual basis.

 

On 2 September 2009, staff provided Council with a verbal update on the flood investigation. In recognition that it was only about five weeks after the flooding, the update was limited to staff’s preliminary determination of the causes of the floods, flooding statistics including historical occurrences and follow up mitigation measures, design standards, statistics of the 24 July 2009 rainfall event, the work plan for the flood investigation and the peer review process being led by the City Manager’s Office.

 

On 22 January 2010, staff provided a memo to the Mayor and Members of Council with a copy of the Phases 1 and 2 Summary Report.  This report provided a summary of the background information collected and reviewed for the affected areas, including the evolution of design standards, the main causes of basement flooding and sewer backups, and the focus for Phase 3 – identification of solutions to reduce the risk of future flooding occurrences.  The memo also included preliminary cost estimates for consideration as part of the 2010 capital budget with the understanding that final estimates would be refined as part of Phase 3.

 

On 18 November 2010, the Planning and Environment Committee received as status update on the Action Plan related to the July 24, 2009 West-End Flooding (ACS2010-ICS-INF-0011) and approved the following recommendations:

 

1.         That Environmental Services staff be instructed to:

a) Prepare a policy on debris in creeks, drainage ditches and other drainage courses to balance water quality and water flow concerns;

b) Co-ordinate efforts of staff in other departments and branches, as well as external agencies, to keep creeks, drainage ditches and other drainage courses free of unnecessary debris; and

c) Report back to Planning and Environment Committee on what has been put in place.

 

2.         That Environmental Services launch a public awareness campaign on drainage issues including the role that surface accumulation of water during heavy rainfall events, the need to not remove manhole covers when water accumulates on the surface and what level of debris is acceptable or even helpful.

 

Work is ongoing related to the approved recommendations and Environmental Services will be reporting on the status of those initiatives under a separate report.

 

The purpose of this report is to present the final Action Plan (Document 1).

 

 

DISCUSSION

 

Flood Investigation Process

 

A comprehensive investigation was undertaken to confirm the cause of flooding and identify solutions to reduce the risk of future flooding occurrences.  This was undertaken using a combination of staff and engineering consultant resources.  The investigation included public input, field assessments, detailed topographical surveys, fog testing of sanitary sewer systems to confirm the presence of cross-connections or undesired infiltration sources, basement elevation surveys and camera inspections of the sewer system at selected locations.  For all areas, the investigation focused on the evaluation of conceptual technical solutions using detailed hydraulic models (adjusted to recreate the 24 July 2009 conditions) that were developed for the affected areas.  These models where used to confirm modes of flooding and assess various alternative solutions to select a preferred approach.  As outlined later in this report, public consultation with affected residents was undertaken throughout the investigation process to seek input, and to keep residents abreast of the process and the anticipated solutions.

 

Given the extent of flooding and complexities involved in the Glen Cairn area, the investigation followed the Class Environmental Assessment (EA) process.  Through this comprehensive process, a number of alternative solutions were evaluated and preferred solutions identified.  This information was presented at 2 public meetings.  In addition, the evaluation was subject to a Value Engineering process, comprised of recognized experts in the field undertaking an independent assessment of the alternative solutions.  This process has helped to reinforce the selection of the preferred technical solutions.  A Public Advisory Committee (PAC) was also established at the outset by the Ward Councillor for Kanata South.  This PAC was engaged throughout the process and was instrumental in providing information related to the flooding event and ensured information presented to the public was communicated in a meaningful way.  The EA report was filed on 3 March 2011 for a 30-day public comment period which ended on April 4, 2011 and no Part II Orders were issued to the Ontario Minister of Environment allowing the implementation of the recommended measures to proceed.

 

The investigation was also subject to a Peer Review, coordinated by the City Manager and Deputy City Manager, Infrastructure Services and Community Sustainability (ISCS).  That review commenced in September 2009 by Greenland International Consulting Ltd. Greenland’s original scope and schedule was adjusted to accommodate the introduction of the Class EA process in the fall of 2009. Greenland’s team spent time with City staff reviewing investigation protocols and cross referencing data prior to completing an interim draft report of the “Phase 1 and 2 Report – West End Flooding Investigations – July 24, 2009 Storm Event Jan 2010”that was delivered in the fall of 2010.  Greenland also reviewed the basement flooding reports and provided recommendations for minor adjustments to the information to be collected in the future.  Based on their experience in similar assignments in other jurisdictions throughout Canada, Greenland determined that the City’s data collection and field investigations were comprehensive providing sufficient information to be used in Phase 3 and 4.  Greenland recommended that a node by node model be prepared to be used as a tool to evaluate the problem that occurred and the potential options to be considered.  This approach, which has been the most successful approach used in other jurisdictions in the province (Peterborough, Barrie, Hamilton, Toronto), was followed by City staff.

 

In late August 2010, Greenland was invited to attend and observe the initial session and the final presentation in a three day Value Engineering Session for the flooding investigation of the Glen Cairn community.  There were over 100 alternatives that were screened in this three day session that Greenland has reported demonstrate the City’s commitment to resolving the flooding in this neighbourhood.

 

Greenland has recently completed an independent review of the EA report.  In its technical memorandum, Greenland summarizes how the EA addresses recommendations they made on the Phase 1 and 2 investigations as well as the public concerns raised in the early meetings.  They identified 11 recommendations from their report on the Phase 1 and 2 investigations and 23 public concerns that had been documented to be dealt with during Phase 3.  Their review has also included key features to remain focused on when preparing the drawings to implement the main flood improvement measures.  It is Greenland’s opinion that the City of Ottawa has been thorough in its investigation of the July 2009 flooding in the Glen Cairn community in the first three phases of its program and recommended proceeding with the Phase 4 work as described in the Consolidated Report and Action Plan.  Greenland will finalize their review of the solutions proposed for Glen Cairn along with the Stittsville, Katimavik, Leacock, and Vanstone clusters during the detailed designs that are being prepared as part of moving forward with the Implementation Plan.

 

The Deputy City Manager’s office also engaged R.V. Anderson Associates Limited for additional oversight of the peer review process, and confirmed that a sound process had been undertaken.

 

Level of Service Objective

 

The west-end communities that experienced flooding and sewer backups are largely serviced by separated storm and sanitary sewer systems with a few locations serviced by roadside ditches.  The City's stormwater and sanitary sewer systems convey flows generated from wastewater discharges and wet weather influences and were designed and built in accordance with recognized standards that evolved over time.  "Stormwater" means wet weather runoff that is collected from roads, parks, rooftops, private property and building footing drains.  "Sanitary sewage" means wastewater that comes from toilets, showers, floor drains, sinks and other plumbing fixtures.

 

Since the mid to late 1980’s, there have been significant changes in the way communities are designed to handle stormwater by introducing the concept of minor and major storm drainage systems.  Minor systems refer to the storm sewers that are sized and controlled to convey frequent storm events (i.e. rainfall events with a return frequency less than 5 years).  Major systems refer to the grading of roads and the provision of stormwater retention facilities that are sized to handle larger less frequent storm events (i.e. rainfall events with a return frequency up to 100 years, including the ability to handle historical major storm events).  Communities built prior to the mid to late 1980’s include provisions for the minor system (i.e. storm sewers) only.  Provisions for the major system only gradually occurred after this date.

 

The provision of major system considerations in the design of new communities has resulted in a significant increase in the level of protection against property flooding from large and infrequent rainfall events.  It has made these communities more resilient to these events and impacts associated with climate change.  For example, this resiliency has been demonstrated by the limited property flooding that was experienced in new neighbourhoods of Orléans during significant rainfall events in 1998 and 2006 and in newer areas of Kanata in 2009.  The key is that even though rainfall levels were significant, flows in these newer communities were controlled and channelled away from private properties.  The challenge is to emulate this level of resiliency in existing communities given the constraints associated with the existing conditions (i.e. topography, depressed driveways, road and lot layouts, etc).

 

For existing west-end communities, the current levels of service are based on the standards of when they were built.  When evaluating these existing communities as part of the investigation process, the objective is to achieve the same level of protection that is provided in new developments built to current standards wherever possible.

 

Action Plan

 

As directed by Council, the City has already begun implementing measures that will increase the level of protection and reduce the risk of future occurrences.  The intent is to continue to implement flood protection measures in a timely manner.

 

In total, $32M has been identified for improvements to reduce the risk of flooding in the City’s west-end, as follows: 

 

Table 1 – Recommended Action Plan (Preliminary Cost Estimates and Schedule)

 

Recommended Measure

2010

2011

2012

Total

Status

Replace MH covers and install ICDs (Kanata, Stittsville and Carp)

$1,300,000

 

 

$1,300,000

Started late fall 2010, to be completed summer 2011

Correct fog testing deficiencies (Kanata and Stittsville)

$650,000

 

 

$650,000

Started late fall 2010, to be completed summer 2011

Glen Cairn Storm Pumping Station, incl pond cleaning and expansion as required

 

$500,000

$3,100,000

$3,600,000

Subject to EA approval, design 2011 and construction 2012

Glen Cairn B/W valves and Sump pumps in zones of influence

 

$1,000,000

$1,675,000

$2,675,000

Implementation to take place in 2011

Glen Cairn Storm drainage system improvements

 

$400,000

$8,400,000

$8,800,000

Design in 2011/2012 with some construction starting in 2011 to be completed in 2012 and 2013

Hazeldean Sanitary Pumping Station improvements (surcharge control only)

 

$400,000

$4,200,000

$4,600,000

Design 2011 and construction 2012 for the surcharge control components only.  Provisions to increase capacity for growth not included and subject to discussion with PGM.

Leacock sanitary sewer

$300,000

$4,200,000

 

$4,500,000

Design and construction in 2011, possibly extending into 2012

Cattail creek drainage improvements

 

$25,000

 

$25,000

Scope of project is being finalized.

Vanstone ditch and sewer upgrades

 

$200,000

$2,000,000

$2,200,000

Design 2011 and construction in 2012 and 2013

Stittsville overland flow deficiencies

 

$75,000

$400,000

$475,000

Design and construction in 2011 and 2012

Contingency

 

 

$3,300,000

$3,300,000

 

 

$2,250,000

$6,800,000

$23,075,000

$32,125,000

 The total amount does not include the approximately $6M provisions to increase capacity for growth.  This is beyond the scope of flood improvements and implementation is subject to discussions with PGM.

 

Note: Further details of the Action Plan are contained in Annex 1.

 

The following provides a status update related to the implementation of the recommended system improvements:

 

Initiatives completed to date:

 

·         Since July 2009, more than 600 Protective Plumbing Grant Applications have been approved for and installations completed at residences in the impacted areas at a cost of $2.4 million.

 

Proposed Actions (2011):

 

 

Proposed Actions (2012/2013):

 

 

Homeowner Information

 

Homeowners can assist in reducing the risk of basement flooding due to sewer backups in a number of ways.  One of the most effective means is the removal of uncontrolled stormwater from piped systems.  Although, in isolation, one individual property's contribution might appear insignificant, downspouts from eaves troughs may be one of the causes of flooding in their basement, their neighbour's properties or the properties downstream in the sewer system.  Another way homeowners can reduce the risk of flooding is to ensure storm backflow valves are functioning properly and cleanout caps located in their basement are properly sealed.  A qualified plumber can assist with these works, if required.  A checklist has been developed to assist homeowners with ways of reducing the risk of basement flooding.  Residents continue to be encouraged to participate in the City’s Residential Protective Plumbing Program.  Information on these topics is available at Ottawa.ca or at Client Service Centres.

 

 

RURAL IMPLICATIONS

 

This investigation extended to affected areas in the rural areas, such as those impacted by the culvert failures and the flooded basements in the Carp Village area.

 

 

CONSULTATION

 

Extensive public consultation has taken place as part of the overall investigation process.  The following is a summary of the Public Meetings that took place since the July 24, 2009 flooding event:

-          July 30, 2009 – Stittsville

-          September 12, 2009 – Glen Cairn (South of Carp River)

-          September 12, 2009 – Glen Cairn (North of Carp River)

-          September 12, 2009 – Katimavik

-          October 1, 2009 – Kanata North

-          February 17, 2010 – Stittsville

-          April 14, 2010 – Glen Cairn Community Association meeting

-          May 19, 2009 – Glen Cairn

-          September 7, 2010 – Kanata North

-          September 13, 2010 – Katimavik

-          September 15, 2010 – Glen Cairn

-          November 1, 2010 - Stittsville

 

A Public Advisory Committee was established for the Kanata South area.  This committee was engaged throughout the investigation process and was instrumental in providing information related to the flooding event, and ensures information presented to the public was communicated in a meaningful way.

 

Further public consultation also took place when the Glen Cairn Environmental Assessment report was filed for the 30-day public review.  This process was completed on 4 April 2011.

 

 

WARD COUNCILLOR COMMENTS

 

The affected Ward Councillors are aware of this report.

 

 

LEGAL/RISK MANAGEMENT IMPLICATIONS

 

The implementation of the recommendations contained in the Action Plan should help to prevent future claims for compensation for damage due to flooding in the event of another significant rainstorm in the affected area.  However, it should be noted that neither a decision by City Council to not implement these recommendations nor an approval of only a portion of the Action Plan would constitute a basis for liability for future claims.  This is in keeping with the legal analysis set out below.

 

At the City Council meeting of September 2, 2009, the City Clerk and Solicitor outlined the basic principles underlying the City’s possible liability for damage due to flooding and explained that these principles would form the bases on which any claims for compensation would be evaluated.  Historically speaking, flooding claims against municipalities have been founded either in the law of nuisance or in the law of negligence.  A brief summary of these follows.

 

Nuisance

 

A property owner may claim compensation where another person has unreasonably interfered with the owner’s quiet use and enjoyment of his or her property.  Nuisance claims can be made when a person has allowed a dangerous thing or substance to escape from his or her control and has caused damage to, or otherwise interfered with, someone else’s property.  In the case of flooding, water would be the substance released from one property that causes damage to, or otherwise interferes with the quiet enjoyment of, another property.

 

 In the context of flooding claims against municipalities, these were historically based on the escape of water or sewage from water, wastewater and stormwater systems.  However, in recognition of the increasing cost of these types of claims, the Ontario Government amended the Municipal Act in 1997 to protect municipalities from claims based in nuisance.  These changes have been carried over into the Municipal Act, 2001, which states:

 

  449.  (1)  No proceeding based on nuisance, in connection with the escape of water or sewage from sewage works or water works, shall be commenced against,

(a) a municipality or local board;

(b) a member of a municipal council or of a local board; or

(c) an officer, employee or agent of a municipality or local board.

 

In light of this statutory protection, a flooding claim against a municipality can be successful only if it is based in negligence.  The manner in which the law of negligence is applied to flooding claims is explained below.

 

Negligence

 

Negligence is generally defined as “conduct that falls below the standard of what a reasonable person would do in like circumstances.”  As explained during the September 2, 2009, briefing to Council, the City may be found liable for flooding damage if it was negligent in the design, construction, operation, or maintenance of the drainage system.  Examples of negligence would be:

      If the drainage system was not designed and/or constructed according to the recognized engineering standards in effect at the time.

      If the City failed to maintain the drainage system according to accepted industry practices.

      If the City failed to repair a broken portion of the drainage system within a reasonable period of time after the problem came to its attention.

 

In regard to the first of these examples, it is important to note that the operative period against which the design of the system is measured is the standard in effect at the time when the design and construction took place.  This legal approach acknowledges that while standards may evolve and improve over time, a municipality does not have a positive obligation to update and rebuild its existing infrastructure to keep up with those changes.  In this way, the courts have recognized that the cost of redesigning or replacing infrastructure may be prohibitive and that municipalities should not be placed in the position of being insurers of all the misfortunes that may befall property owners.

 

With respect to the second example, the maintenance obligations would be restricted to taking the required reasonable steps to keep the drainage system operating within the parameters of its design and would not include an obligation to upgrade the system.  The third example requires the City to delay repairs to damaged drainage infrastructure for an unreasonable period before liability would apply.

 

Summary

 

In keeping with the City Clerk and Solicitor’s comments during the September 2, 2009, Council briefing, all claims against the City arising out of the July 24, 2009, rain event will be assessed in accordance with the legal principles that govern the law of nuisance and negligence as they apply to municipalities.  To date, the City has received in excess of 875 claims and approximately 500 of those claims are from property owners in the Glen Cairn area.  All but 70 of the claims were received from insurers on behalf of property owners.

 

With the release of this report, the City’s Claims Unit will be proceeding expeditiously to apply the findings related to the causes for flooding in the identified “cluster” areas against the legal standard for negligence and responding to claimants’ within the next few weeks.

 

While each claim will be assessed based on its specific facts, it should also be noted that a similar rain event that hit the eastern areas of the City on September 9, 2004 generated 802 flooding claims based on overtaxed drainage systems and all of them were ultimately denied.  No lawsuits were initiated against the City as a result of those denied claims.  Similarly, a rain event that effected Orleans and other eastern areas of the City on July 3, 2006 resulted in 373 claims that were subsequently denied and no lawsuits followed.

 

 

CITY STRATEGIC PLAN

 

This report is consistent with the Service Delivery priority of the City Strategic Plan.

 

 

TECHNICAL IMPLICATIONS

 

N/A

FINANCIAL IMPLICATIONS

 

To support the implementation of the recommended flooding improvement measures, $4M was approved as part of the 2010 Capital Budget (account 905553), an additional $6.8M as part of the 2011 Capital Budget and the balance will be subject to approval of the 2012 Draft Capital Budget.

 

 

SUPPORTING DOCUMENTATION

 

Document 1 – West-End Flooding Investigation, 24 July 2009 Rainstorm Event, Consolidated Report and Action Plan, March 2011

 

 

DISPOSITION

 

Infrastructure Services will implement the recommendations of the Action Plan.