Annex 3
Open House
Materials
- Information Bulletin
- Comment Questionnaire
- Exhibits
Draft Terms of
Reference - November/December 2004
Information Bulletin No.
1
Overview
This Information Bulletin has been prepared
to provide a common understanding of the Draft Terms of Reference (ToR) for the
East-West Corridor Light Rail Transit (LRT) Project: Environmental
Assessment. It includes information on
the proposed project and the Draft ToR which sets out a framework that will
guide the preparation of the Environmental Assessment (EA).
Project Background
The proposed East-West Corridor LRT Project
was developed at a strategic level through the Rapid Transit
Expansion Study (RTES), 2003. Following
on from RTES, the Ottawa Rapid Transit Expansion Program (ORTEP) Implementation
Strategy identified the immediate undertaking of the planning work for the
North-South and East-West LRT projects as critical to meet the implementation
timeframe for light rail projects.
In the
spring of 2004, the Statement of Work for the East-West Corridor LRT Project:
Environmental Assessment (EA) Study was approved by the City's Transportation
Committee.
This Study
will examine a range of alternatives, identify both construction and
operational impacts on all aspects of the environment and bring forward a
recommended plan detailing mitigation measures, costs, and all approvals
required to proceed with implementation as opportunities present themselves.
The Study will be conducted in accordance with both Provincial and Federal
Environmental Assessment Act requirements.
The first step in the assessment process is the development of a ToR
which requires Ministry of the Environment (MOE) approval.
Study Area
The
proposed East-West Corridor LRT Project is approximately 47 km long, spanning
from Orléans to Kanata. The rapid transit corridor would provide improved
east-west transit connectivity bypassing the downtown. It also presents a
unique opportunity to influence developments within the growth areas of Kanata
and Orléans as well as inside the Greenbelt.
The study
area is characterized as a corridor encompassing both sides of the existing
rail corridor. In the east end, the band is narrower as the alignment has been
defined by earlier studies. Along most of the corridor, it is wide enough to
consider potential parallel corridors such as arterial roads and hydro
corridors. In Kanata, the study area widens out to consider several route
options, which will be evaluated to determine which best serves the existing
and future growth.
Schedule
The proposed schedule for the EA
Study (including legislated review periods) is as follows:
!
Submit Terms of Reference to MOE in January 2005.
!
Anticipated MOE approval of the ToR by April 2005 (12 weeks
after submission). This includes a 30-day public and agency review and allows
for review and approval by MOE .
!
Submit completed EA Report to MOE by May 2006, including
documentation of all public consultation and all relevant transportation and
environmental planning studies undertaken during the course of the study.
!
MOE approval is anticipated by December 2006. This is based
on legislation providing up to 30 weeks for review and approval.
Terms of Reference
The ToR is a document which sets out a framework to guide
the preparation of an Individual EA.
The City of Ottawa must submit the ToR to the Ministry of the
Environment for approval. The approved
ToR is the first statutory decision by the MOE in the EA planning and approval
process. The ToR describes:
!
The Proposed Project Purpose
!
Environmental
Assessment Work Plan
!
Environmental
Assessment Consultation Plan
!
Additional Approvals
Required
Purpose
of the Undertaking
The
preliminary rationale for the undertaking is twofold:
!
Help to satisfy the study area transportation demand and to
achieve the City wide transit modal split target of 30% (i.e., solving the
problem); and
!
To protect land for the transit facility in advance of major
development (i.e., opportunity to establish and plan for appropriate
development densities and create transit-oriented developments (TODs) around
the facility and stations).
Environmental
Assessment Work Plan
The EA
Work Plan includes the following major activities:
Purpose/Need:
This
activity will be undertaken to document the purpose and rationale for the
undertaking. A Ridership Study will be completed as part of this activity.
Existing
Conditions: Existing biological, physical, economic, social and
technical environmental conditions will be documented as a baseline against
which to assess and evaluate the potential effects of the alternatives on the
environment.
Alternatives:
Alternatives
to the undertaking (do nothing, widen roads, rapid transit, combinations of
road and transit) and alternatives ways to carry out the undertaking
(technologies, corridors, station locations, infrastructure) will be identified
and evaluated.
Assessment
& Evaluation: Various assessment and evaluations methods will be developed
and used to select the preferred alternative.
Environmental
Assessment Consultation Plan
Consultation
will include two invited Consultation Groups and Public Participation at Open
Houses at key points during the study.
Public Consultation Group
(PCG): formed to
enable the community and interest groups to provide direct input into the
study. It includes representatives from
City Wards adjacent to the corridor, interest groups, and representatives from
several City advisory committees.
Agency Consultation Group
(ACG): formed to address the full range of technical issues
and to comment on special studies as well as applicable procedures and
legislation and policies. The ACG
includes representatives from all levels of government.
Three Open
Houses are planned for the Study:
!
EA Open House #1
(Spring 2005)
!
EA Open House #2
(Fall 2005)
!
EA Open House #3
(Spring 2006)
City’s
Website: Information on the EA will be available on the City’s
website www.ottawa.ca/lrt
Additional Approvals
Additional approvals may be required beyond the Federal and
Provincial Environmental Assessment Acts. The City of Ottawa is committed to
obtaining the necessary approvals at the appropriate time in the implementation
phase. The agencies responsible for issuing approvals will be consulted during
the EA to address their interests and approval requirements.
Next Steps
Following
this Open House, the Study Team will:
!
Incorporate your comments into the draft ToR.
!
Present the revised ToR to Transportation Committee and
Council.
!
Incorporate Committee and Council comments into the Final
ToR.
!
Submit the Final ToR to MOE for approval.
The MOE
approved ToR will provide the framework for completing the Individual
Environmental Assessment. When
reviewing the EA, the MOE will ensure that the EA followed the process as set
out in the ToR.
Before you
leave tonight, please complete the Comment-Questionnaire and place it in the
designated box, or mail or fax it to us by December 17, 2004.
Questions
or Comments |
If you have any questions or comments about the study, please contact: Mona Abouhenidy, Ph.D., P.Eng. Planning
and Growth Management Department City of
Ottawa 110
Laurier Avenue West, 4th Floor Telephone: 580‑2424, ext. 26936 Fax:
580-2578 E-mail: mona.abouhenidy@ottawa.ca |
Prepared by Delcan
Corporation
Terms of Reference Public Open House
November/December
2004
COMMENT-QUESTIONNAIRE
The City of Ottawa would appreciate your responses to the following questions as well as any comments you wish to make about the information presented at this Open House. Please take a few moments to complete our Comment-Questionnaire. You may leave it in the designated box when you leave tonight’s Open House, or send it to the address listed below by 17 December 2004. All information gathered in the Comment-Questionnaire will become part of the public record and used for the purpose of conducting this study.
About You
Where do you live? (Street name) |
|
What specific interest do you have in this study? |
|
|
Study Process
Do you have comments on the Study Process (Federal, Provincial or Harmonized) for conducting the Environmental Assessment?
|
|
|
What in your view, are the primary issues to be addressed in the Environmental Assessment?
|
|
|
Terms of Reference
Do you have specific comments on the Draft Terms of Reference as they relate to the following subject headings?
Existing Conditions
|
|
|
Alternative Solutions
|
|
|
Alternative Designs
|
|
|
Assessment and
Evaluation
|
|
|
Public Consultation
|
|
|
If you wish, please provide:
Name: Representing
(if applicable):______________________
Address: |
|
Postal Code:
_________________________________________
email: _________________________________________
Thank you for your participation
If you wish to provide us with more detailed comments, send written submissions, by 17 December 2004 to:
Mona Abouhenidy, Ph.D., P.Eng.
Planning and Growth Management Department
City of Ottawa
110 Laurier Avenue West, 4th Floor
Tel: 613-580-2424 ext. 26936
Fax: 613-580-2578
E-mail:
mona.abouhenidy@ottawa.ca
East West LRT Environmental Assessment
Terms of Reference Public Open
House – November/December 2004
Exhibit List
Welcome
Sign-In Table
Directional Signage
Welcome
Background
Environmental Assessment Process
Terms of Reference
Study Schedule
Environmental Assessment Work Plan
Purpose/Need
Study Area
Existing Biological Environmental Conditions
Existing Physical Environmental Conditions
Existing Socio-Economic Environmental Conditions
Existing Transportation Conditions
Alternative
Solutions
Alternative Methods
of Carrying Out the Undertaking
Evaluation
Methodology
Impact Assessment and
Mitigation
Consultation
Next Steps
Appendix C
Excerpts from Statement of Work
Excerpts from
East-West Corridor LRT Project Environmental Assessment Report
to/Rapport au:
Transportation Committee
Comité des transports
26 March 2004 / le 26 mars
2004
Statement of Work
4.0 MAJOR
ISSUES TO BE ADDRESSED
The ToR shall identify the issues to be examined during the course of this study. Some of the major issues to be addressed include, but not limited to:
Staging
and Technology
Implementing a project of this magnitude would likely necessitate a staged implementation approach. Accordingly, the EA study shall examine a range of options, and recommend a preferred staging strategy based upon a range of criteria including ridership generation potential, likely development potential along the corridor, compatibility and integration with land use, environmental considerations, logical sequence and ease of implementation, costs, and funding availability.
Although Council has already approved the RTES long range recommendation for twin-track electric LRT, this EA study will examine the feasibility and cost-effectiveness of single-track alternatives. The EA will also examine the option of using the DMU vehicles currently in use on the North-South corridor, with additional vehicles.
Grade Separation Requirements
The ultimate East-West Corridor, as envisaged in RTES, crosses the VIA rail line, the North-South LRT Corridor, Rideau River, Southeast Transitway, Southwest Transitway, West Transitway, twice Highway 417, and numerous arterial roads. Requirements for grade separation with these facilities will be addressed. Existing structures will be examined to determine whether there are any impacts (keep as is, modify, or replace).
Coordination
with existing freight/passenger rail Traffic
Transcontinental freights were re-routed away from the Beachburg Subdivision to Toronto in 1995 and as such freight traffic is minimal. Also, this route passes over 1.1 kilometers of track between Wass and Federal Junction that is also used by heavy VIA trains.
The option of co-locating the LRT operation on existing freight tracks versus operating in the same right-of-way but on separate tracks will be examined. For the “same track” option, the issue of coordinating the schedules of the LRT and VIA Rail (on the Smith Falls Subdivision) and freight (on the Beachburg Subdivision) will be investigated and verified with Transport Canada regulations on the shared use.
Integration
with other modes
The provision of strategically located and appropriately sized Park and Ride facilities is key to providing high quality rapid transit service, and achieving the expected ridership within this corridor. This study will examine and recommend the preferred location and size of Park and Ride lots, as well as access requirements. The recommended plan will incorporate functional designs and cost estimates for these facilities.
The Study will also examine the integration with other transit services. Of particular importance are the integration with the North-South LRT, Southwest Transitway, the Southeast Transitway and West Transitway at Hwy 417. The recommended plan will incorporate functional design and cost estimate for stations and transfer facilities.
The TMP identified a future multi-use pathway following the proposed LRT Corridor from Woodroffe Avenue to Rideau River to Highway 417 East. The Study will examine how these two facilities are interfaced.
Urban
Environment Integration
The possible introduction of surface running LRT through Kanata North and possibly in other areas will have a significant impact on the surrounding environment. This study will determine a preferred alignment, and address a host of issues including, but not limited to urban design, access to adjacent land uses, station locations, integration with the pedestrian environment, including safety and access considerations, effect on cycling, noise and vibration.
Operation
and Maintenance Requirements
A considerable amount of supporting infrastructure is required to provide for the operation of the proposed LRT system. Amongst the major components required, this study will:
· identify LRT vehicle maintenance and storage facility requirements, and address the environmental impacts of its connection to the system;
· identify and cost electrical supply requirements and facilities, as necessary, including all substations and property requirements;
· identify and cost all communications, control and signalling requirements, including central control facility location and requirements.
Serving
Extensive Employment Market
A chain of extensive employment areas currently exists along this LRT corridor. It extends from Orleans Industrial Park, Sheffield Industrial Park, Hawthorne-Stevenage Business Park, Ottawa South Business Park, South Walkley - Albion Industrial Park, across the Rideau River through the Colonnade business park and on to both the Bells Corners and Kanata North Business Parks. It is anticipated that employment in this area will roughly double from today’s level of about 40,000 jobs to about 70,000 by 2021. Given the importance of serving this market, the Study will examine corridors alignment that best serve these areas including stations, integration with surrounding buildings, and pedestrian accesses.
Appendix D
Public and Agency Consultation Groups
Membership, Role and Responsibility
Public Consultation Group
East-West Corridor Light Rail Transit (LRT) Environmental Assessment
Proponent
· City of Ottawa
City Ward Representatives (maximum of two per ward as recommended by Ward Councilors)
· Cumberland, Ward 19
· Innes, Ward 2
· Beacon Hill – Cyrville, Ward 11
· Gloucester – Southgate, Ward 10
· Alta Vista, Ward 18
· River, Ward 16
· Capital, Ward 17
· Bell-South Nepean, Ward 3
· Knoxdale – Merivale, Ward 9
· Baseline, Ward 8
· Bay, Ward 7
· Kanata, Ward 4
City Advisory
Committee Representatives
· Environmental Advisory Committee
· Pedestrian and Transit Advisory Committee
· Roads and Cycling Advisory Committee
· Accessibility Advisory Committee
· Ottawa Forests and Greenspace Advisory Committee
· Local Architectural Conservation Authority Committee
· Arts, Heritage and Culture Advisory Committee
· Ottawa Youth Cabinet
Other Interest Groups
· Federation of Citizens Association
· Transport 2000
· Disabled and Proud
Role and Responsibility of the PCG Working Members
The PCG members will:
·
Represent
the interests and values of residents, land owners/users and interest groups in
their individual wards and City as a whole;
·
Attend
all PCG meetings to ensure consistent two-way communication throughout the
study;
·
Review
information provided by the Study Team in advance of each PCG meeting;
·
Provide
feedback on information provided and comment on ideas and issues raised at
meetings;
·
Work
towards a consensus to allow the City to achieve project milestones.
The input from the PCG, other consultation groups and the general public will be reviewed after each Public Open House and, where appropriate, adjustments will be made to the study findings.
All comments received will become part of the
public record for the Study.
Administration
The City of
Ottawa’s Project Manager will chair the PCG meetings and be responsible for the
following administrative duties:
·
Ensure
adequate notification to members of upcoming meetings
·
Prepare
meeting agendas and circulate materials for review;
·
Distribute
(by e-mail) all meeting notes following each meeting.
The Study Team recognizes that tight study timelines limit the time for review and comment on study materials and as such endeavors to provide as much review time as practical. Accordingly, study materials and progress reports will be provided to the PCG members throughout the study as they become available, and best efforts will be made to provide all relevant study materials within two weeks prior to each PCG meeting.
Agency
Consultation Group
East-West Corridor Light Rail Transit (LRT) Environmental Assessment
Proponent
· City of Ottawa
Federal
· National Capital Commission
· Transport Canada
· Health Canada
· Indian and Northern Affairs Canada
· Infrastructure Canada
· Parks Canada
· Public Works and Government Services Canada (Investment Management Directorate)
· Canadian Environmental Assessment Agency
· Environment Canada
· Fisheries and Oceans
Provincial
· Ministry of Culture
· Ministry of the Environment
· Ministry of Natural Resources
· Ministry of Public Infrastructure Renewal
· Ministry of Transportation
Regional
· Rideau Valley Conservation Authority
· Mississippi Valley Conservation Authority
· South Nation Conservation Authority
Other
· Greater Ottawa Chamber of Commerce
· Canadian National Railway
· Ottawa Central Railway
· VIA Rail
City of Ottawa
· Public Works and Services (including OC Transpo)
· Planning and Growth Management
· Corporate Services
· Community and Protective Services
· Ottawa Police
Role and Responsibility of the ACG Working Members
The ACG
members will:
·
Represent
the interests of their department and agencies;
·
Attend
all ACG meetings to ensure consistent two-way communication throughout the
study;
·
Identify
planning and design issues early in the study so that they may be addressed in
a timely manner;
·
Review
information provided by the Study Team in advance of each ACG meeting;
·
Disseminate
this information within their departments and agencies;
·
Provide
feedback on information provided and comment on ideas and issues raised at
meetings;
·
Work
towards a consensus to allow the City to achieve project milestones.
The input from the ACG, other consultation groups and the general public will be reviewed after each Public Open House and, where appropriate, adjustments will be made to the study findings.
All
comments received will become part of the public record for the Study.
Administration
The City
of Ottawa’s Project Manager will chair the ACG meetings and be responsible for
the following administrative duties:
Ensure
adequate notification to members of upcoming meetings
Prepare
meeting agendas and circulate materials for review;
Distribute
(by e-mail) all meeting notes following each meeting.
The Study Team recognizes that tight study timelines limit the time for review and comment on study materials and as such endeavors to provide as much review time as practical. Accordingly, study materials and progress reports will be provided to the ACG members throughout the study as they become available, and best efforts will be made to provide all relevant study materials within two weeks prior to each ACG meeting.