Report to/Rapport au :

 

Transportation Committee

Comité des transports

 

31 May 2004 / le 31 mai 2004

 

Submitted by/Soumis par : Ned Lathrop, General Manager/Directeur général,

Planning and Development/Urbanisme et Aménagement 

 

Contact Person/Personne ressource : Vivi Chi, Manager / Gestionnaire

Transportation Infrastructure / Infrastructure des transports

(613) 580-2424 x21877, vivi.chi@ottawa.ca

 

 

Ref N°: ACS2004-DEV-POL-0007

 

 

SUBJECT:

COUNTRY CLUB VILLAGE AND HIGHWAY 7 SERVICE ROAD ACCESS ENVIRONMENTAL ASSESSMENT STUDY

 

 

OBJET :

ÉTUDE D’ÉVALUATION ENVIRONNEMENTALE SUR L’ACCÈS PAR UN CHEMIN DE DESSERTE AU COUNTRY CLUB VILLAGE ET À L’AUTOROUTE 7

 

REPORT RECOMMENDATIONS

 

That the Transportation Committee recommend Council approve:

 

1.         The study recommendation identifying Crawford Road (Alternative 5) as the second access to the Country Club Village (CCV) and Canadian Golf and Country Club (CG&CC).

 

2.         The study recommendation of providing a year-round static (non-piped) water supply within the Country Club Village subdivision for fire services.

 

3.         The finalization and filing of a Project File detailing the above noted recommendations of the Country Club Village and Highway 7 Service Road Access Environmental Assessment Study.

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité des transports recommande au Conseil municipal d'approuver :

 

1.         la recommandation de l'étude dans laquelle le chemin Crawford (option 5) est déterminé comme le deuxième chemin de desserte au Country Club Village (CCV) et au Canadian Golf and Country Club (CG&CC);

 

2.         la recommandation de l'étude selon laquelle on fournirait une réserve d'eau statique (sans canalisation) dans le lotissement du Country Club Village aux fins de services d'incendie.

 

3.         l'étape finale et le dépôt d'un profil de projet décrivant les recommandations susmentionnées de l'étude d'évaluation environnementale sur l'accès par un chemin de desserte au Country Club Village et à l'autoroute 7.

 

 

BACKGROUND

 

Introduction

The City of Ottawa has undertaken the Country Club Village - Highway 7 Service Road Access - Environmental Assessment (EA) Study to address local service road access issues resulting from the Ontario Ministry of Transportation (MTO) plans to widen Highway 7 from Highway 417 to Carleton Place.

 

The analysis and study findings are described in the subsequent sections of this report, and reflect the challenges that were present in each phase of the study. 

 

From the initial stages of the MTO study, and now continued forward into this EA, there has been tremendous community interest in the resolution of the access issue.  Residents and other members of the public have devoted significant time and energy in working with the study team to formulate a solution.  As such, the decision of the study team to recommend (in essence) a “Do Nothing” option was not an easy one to make.  The issues discussed during the study have ‘boiled down’ to a trade-off between travel time and the costs, both financial and in terms of impact on a Provincially significant wetland. 

 

Ministry of Transportation Highway 7 Widening Project

In 1993 the MTO initiated an EA study to address safety concerns for this heavily travelled section of highway. The study was completed in 1996 with the recommended solution being to convert Highway 7 from a 2-lane highway to a 4-lane divided freeway with interchanges.

 

One of the key study issues for landowners adjacent to the Highway 7 corridor and the Township of Goulbourn was local access and the provision of service roads. The reconstruction of Highway 7 to a freeway configuration would necessitate all entrances and secondary roads to be redirected to interchanges via adjacent service roads. During the Highway 7 EA, the review and evaluation of local access issues considered various ways to locate and direct the service roads to one arterial road or another. Ultimately, service roads leading to the Hazeldean Road, Dwyer Hill Road, and Ashton Station Road interchanges were recommended.

 

Highway 7, within the City of Ottawa, is located predominantly within the former Goulbourn Township. The lands adjacent to Highway 7 in this area are sparsely developed except for the rural estate subdivision known as Country Club Village (CCV) and the adjacent Canadian Golf and Country Club (CG&CC), both of which currently have direct access on to Highway 7.

 

To address access needs for these two properties, the Highway 7 EA identified a service road adjacent to Highway 7 extending from the Dwyer Hill Interchange eastward to the Canadian Golf and Country Club, and ending at that location.   The Highway 7 service road, as planned, will introduce an average 3-minute increase in travel time (also called out of way travel) for trips to the east from the Country Club Village.

 

During the Highway 7 EA, the former Goulbourn Township identified a concern with this service road, and recommended that it be extended to Jinkinson Side Road to reduce out-of-way travel and the response time of emergency vehicles.  In the Highway 7 EA study, the service road extension was included in the evaluation of alternatives but not supported due to the environmental impact on the provincially significant Huntley Wetland Complex, significant construction costs, and the relatively modest decrease in travel time.  The Goulbourn Fire Service indicated, at the time, that the emergency response times continued to be acceptable without the service road extension.

 

The residents of Country Club Village have continued to express their preference for this eastern extension to Jinkinson Road since this would facilitate the predominate direction of their daily trips.  Goulbourn Township Council strongly supported the views of the residents in the interest of allowing the EA and its safety goals to move forward, requested MTO to include in its ESR highway plans the identification of the service road as a "possible future municipal roadway".  The Township wanted to ensure that the service road issue could continue to be addressed, even after the Highway 7 EA process is completed.  MTO concurred and shortly thereafter the Highway 7 EA was finalized.  See Document 1 for the Study Area Key Plan.

 

Another key factor included in the original MTO review of service road alternatives was the evaluation of impacts on emergency response time. Comments received from the Goulbourn Fire Service in 1996 did not indicate significant concern with the expected change in emergency response time. However, in 1999 following the advertising of the Highway 7 EA Notice of Study Completion, new concerns were expressed by the Goulbourn Fire Service about the increased emergency response time to the Country Club Village.

 

Based on the Goulbourn Fire Service emergency response time concerns, in 1999 the MTO agreed to co-fund this EA study (in partnership with the then Goulbourn Township) to complete a detailed review of emergency response time and local access issues related to the Country Club Village and Canadian Golf and Country Club. Accordingly, in March 2002 the City of Ottawa retained a consultant to conduct the Country Club Village and Canadian Golf and Country Club Access Study.  The MTO contributed 50% or $62,750 of the original study budget of $125,500.  The final study costs are projected to be approx. $160,000 due to additional work added during the study.

 

In the meantime, the MTO has continued to move forward with preparations for the reconstruction of Highway 7 in parallel with this study.  Detailed design is underway and construction will follow depending on the availability of funding and provincial priorities.  See Document 2 for the Local Area Key Plan.

 


 

DISCUSSION

 

Purpose of the Study

The purpose of the access study, in consideration of the eastern extension of the service road, was to:

 

 

Existing Transportation Network

The existing transportation network, as illustrated in Document 3 – Study Area, includes the following transportation facilities:

 

 

Future Transportation Network

 

The Official Plan and the Highway 7 EA Study, both completed and approved either prior to or during this study, define the future transportation network.  The analysis, therefore applied the approved planning as the base case for all evaluation of alternatives.  It should be noted that the CCV participants in this study continue to view the existing conditions as the representative baseline, rather than the previously approved planning.

 

The future approved transportation network, as illustrated in Document 4 - Approved Transportation Network, will include the following changes from existing (2004) conditions:

 

 

A shift in the new highway alignment to the north in the vicinity of the CCV and CG&CC was recommended as part of the planning process to minimize impacts (visual, noise, etc.) on the homes that back onto Highway 7 and to avoid disruption to the golf course.

 

The introduction of freeway features will provide greater safety with the removal of at-grade intersections and opposing lanes.

 

The future transportation network will require vehicles, including emergency services, that may originate from the east to travel to the Dwyer Hill Road interchange and travel back along the local service road.  The higher operating speeds on the freeway (100 km/hr) will partially offset the longer travel distance on the local road network.  In addition, local road access is available via Fernbank Road and Dwyer Hill Road.

 

Alternatives Considered

 

The five alternatives included:

 

 

Following the evaluation exercise with the Public Advisory Committee (PAC) members, variations on Alternatives 2, 3 and 4 were developed and evaluated with the other alternatives.  The variations applied to both the fire response and community access alternatives.  The revised alternatives included:

 

The service road alternatives 1 to 5 are illustrated in Document 5, and service road alternatives 2`, 3`, and 4` are illustrated in Document 6.

 

ISSUES

 

Fire Response

One of the key goals of this study was the examination of fire response to the CCV and CG&CC. 

 

The study review of alternatives found that Alternative 5 provides a better response time to the center of the CCV community (14 minutes and 42 seconds) than existing conditions of today (14:49).  Alternative 5 was considered an acceptable fire response time by City of Ottawa Fire Services and formed the study recommendation based on its low cost to implement and negligible impact to the natural environment.

 

Alternative 3 and Alternative 2 both provide better fire response times to the CCV community than Alternative 5.  However the cost and environmental impacts required to improve on the acceptable response time of Alternative 5 is considered too great to warrant recommendation.

 

Each of the Alternatives were evaluated with the assumption that the Highway 7 widening will be in place.  A complete table of Fire Response Comparisons for each alternative is shown in Document 7.

 

Access to Country Club Village

One of the community’s primary concerns during the study was the increased travel time for residents of the Country Club Village and patrons of the Canadian Golf and Country Club.  The recommended Alternative 5 maintains the same out-of-way travel for CCV residents (3:16) as was identified in the approved Highway 7 EA planning.  If compared to existing (today's) conditions, Alternative 5 represents a 30% increase (from 10:56 to 14:12) in travel time to Stittsville and a 23% increase (from 13:49 to 16:10) in travel time to Kanata.  The  impact on trips will decrease proportionally for destinations further east such as downtown Ottawa.

 

Alternative 2 does provide improved travel time to Stittsville (10:48) and to Kanata (14:38), but there is a cost (financial and significant environmental) to implement this alternative.

 

A complete table of Community Travel Time Comparisons for each alternative is shown in Document 7.

 

Access to Canadian Golf and Country Club

The out-of-way travel to the golf course is the largest travel time impact that is not reduced by the recommended Alternative 5.  The serviced road identified and approved in the Highway 7 EA will require guests arriving from the east to travel approximately 2 km further than provided today.  As an example, this results in a 33% increase in travel time from Kanata.  Golfers arriving from the east are the majority of the course’s patrons. 

 

The TAC considered this issue and included it in the evaluation exercise.  However, the review of travel time impacts was weighed against two important factors.  Firstly, the golf course has an agreement (1972) with the MTO that pre-contemplates and accepts the loss of direct access to Highway 7 as a condition of the initial approval for the golf course entrance.  Secondly golf course patrons are generally making destination trips and are aware of the location of the course before booking a "tee-off" time, and therefore can effectively plan for the additional travel time.

 

The possible air quality impacts of the additional travel time to the golf course were also considered and determined to be an inappropriate measure to gauge the need for modifications to low volume local roads.  When compared to air quality issues related to major high volume roads elsewhere in the City, the marginal benefits available from similar levels of investment on major roads far exceed the potential for any real air quality benefits in the relatively low volume local road context.

 

A complete table of Canadian Golf and Country Club Travel Time Comparisons for each alternative are shown in Document 7.

 

Provincially Significant Wetland

Wetlands are essential components of ecosystems that contribute to the high quality of the environment in Ottawa.  Wetlands control and store surface water to assist in flood control, act as sediment traps to improve water quality, and provide habitat for a wide variety of plant and animal species and may serve as recharge areas for groundwater resources. 

 

The Ministry of Natural Resources has developed a system that evaluates the biological, social, hydrological and special features of wetlands to determine their relative significance in Ontario.  The Huntley Wetland Complex has been evaluated and identified as a Provincially Significant Wetland.  Impacts on Provincially Significant Wetlands are avoided whenever possible and only considered where other reasonable alternatives do not meet essential needs.  The Huntley Wetland Complex is identified in the OP as a Significant Wetland.

 

The PAC’s overall preferred solution, Alternative 2, crosses the Huntley Wetland Complex.  However, some members of the PAC have defended the ecological values of this area and support the study's technical recommendation (Alternative 5).

 

Funding

The MTO has indicated (October 2003) that it is willing to fund 75% of the total construction cost for the final MOE approved solution arising from this EA.  Depending on which alternative is endorsed, potential funding from the MTO would result in the following approximate costs to the City:

 

At the final Public Open House on 14 October 2003 the Country Club Village Community Association indicated that they had been in contact with Thomas Cavanagh Construction Ltd. and arranged for the donation of road building materials for Alternative 2. 

 

Thomas Cavanagh Construction Ltd. has provided a letter offering the donation of rock for the construction of an Alternative 2 road base.  The approximate value of this contribution is $50,000 ($37,500 of this would be the MTO share of this alternative).  A review of the evaluation of alternatives by the TAC has indicated, based on the weighting of the various factors including cost, that Alternative 5 remains the recommended alternative of the study.


 

EVALUATION CRITERIA AND PROCESS

 

Both the TAC and PAC completed the technical review and evaluation exercise.

 

The PAC requested and completed a separate weighting exercise from the TAC and recommended Alternative 2 (Service Road along Highway 7 from Dwyer Hill Road to Jinkinson Road).  The TAC's recommendation is Alternative 5 (Crawford Road).

 

The difference in perspective of the two groups of evaluators (TAC and PAC) is illustrated in a Comparison of PAC and TAC Weights table found in Document 7.  Documents 8 and 9 provide further comparisons of TAC  and PAC opinions as well as comparisons of alternatives.

 

Alternative 2 is the preferred solution for the adjacent community in that it improves access for the existing approximately 90 homes and the golf course.  The TAC and study team have not endorsed this solution due to the higher costs ($1.4 million), and impacts to a provincially significant wetland.

 

Community representatives have noted that they will be asking the Committee to change the recommendation of the study, and utilize funding from the MTO and any private business contribution to reduce the cost of the project to the City.

 

Sensitivity Testing

A sensitivity testing exercise was completed to test the range of perspectives of the TAC and PAC.  This allowed the study team to assess how robust the preferred solution was between the two groups as well as whether there were differences among individual members on each committee.

 

The results of the sensitivity testing showed the TAC was generally in agreement with selecting Alternative 5.  It was selected as the preferred Fire alternative by the committee, rated first in 8 of 12 sensitivity tests for Fire; rated first for Community Access and rated first in 8 of 12 sensitivity tests for Community Access.  When rated as a "Balanced Need" the TAC selected Alternative 5 and it was the individual choice of 11 of the 14 TAC members.

 

The results of the sensitivity testing showed the PAC was generally in agreement with selecting Alternative 2.  It was selected as the preferred Fire alternative by the committee, rated first in 7 of the 12 sensitivity tests for Fire; rated first for Community Access and rated first in 9 of 12 sensitivity tests for Community Access.  When rated as a "Balanced Need" the PAC selected Alternative 2 and it was the individual choice of 8 of the 11 PAC members.

 

The conclusion of the sensitivity testing exercise was that there was polarity of perspectives between the two groups.  Those that live in the community have a preference for attributes of reduced travel time.

 


 

RECOMMENDED SOLUTION

 

The study recommendation is Alternative 5 (Crawford Side Road), as shown in Document 10.  Alternative 5 provides a road link from Dwyer Hill Road to the south portion of the CCV via Crawford Side Road.  This recommendation also incorporates the previously approved service road from Dwyer Hill Road along Highway 7 to the eastern limits of the CG&CC as proposed in the MTO highway widening project.

 

This recommendation was developed based on the following issues:

·        The acceptance from senior fire officials that this alternative met acceptable fire response standards for rural response times;

·        It does not introduce any new impact to the natural environment since the construction of Crawford Road is already underway within the road allowance; and

·        It does not impose additional road construction costs on the City since the developer of the CCV is required to construct the road in accordance with a development agreement. Current schedules indicate that the construction of the service road, begun in the fall of 2003, will be completed in 2004.

 

 

CONSULTATION

 

During the course of the study regular update meetings were held with the Technical Advisory Committee (TAC) and Public Advisory Committee (PAC).

 

The TAC was composed of representatives from the City of Ottawa (including emergency services), Ministry of Transportation, Ministry of Natural Resources, Mississippi Valley Conservation Authority and consultant staff.

 

The PAC was comprised of representatives from community associations (Country Club Village Community Association and Northwest Goulbourn Community Association), Canadian Golf and Country Club, Friends of the Jock River, Goulbourn Wetlands Advisory Committee, Ottawa Cycling Advisory Committee and a local farming operation.  The PAC participants have invested significant time and effort on the study.

 

A Value Planning Workshop was held as part of the public consultation program.  The workshop included participation from all stakeholders including the TAC, PAC and external agencies with interest in the study.  The Value Planning workshop defined all issues and participants brainstormed ideas for improving transportation service to this part of the City.

 

In addition to the TAC and PAC meetings and Value Planning Workshop, two Public Open Houses were conducted to present the study and its findings to the general public.  The first Open House was held on 12 September 2002 at which the study process, existing conditions, alignments options, issues and next steps were presented for public review and comment.  The second Open House, held on 14 October 2003, presented the technically preferred alternative for the study.  Summaries of these Open Houses were provided to the Ward Councillor, and members of the PAC and TAC.

 

The Public Open Houses were advertised in local and community papers.  Flyers were distributed to homes in the community and within the study area boundaries.  The meetings drew an attendance of 45 and 61 visitors at the first and second Open Houses respectively.

 

Although there is general agreement that protection of wetlands is important, a large proportion of the residents strongly support Alternative 2.

 

 

FINANCIAL IMPLICATIONS

 

The study recommendations include the construction of a new static (non-piped) fire water supply point in the CCV with an estimated cost of $50,000. 

 

The MTO cost sharing agreement calls for funding up to 75% of the MOE approved recommended option (capital costs only).  The MTO have been asked to confirm that this funding scenario can include the recommendation to provide an improved fire water supply point.  The City's share (from $12,500 to $50,000 depending on funding) for the construction of this water supply point will have to be identified in a future budget. 

 

The previous subdivision approval anticipated the maintenance cost for Crawford Road, now estimated to be in the order of $ 6,000 per year.

 

 

SUPPORTING DOCUMENTATION

 

Document 1 - Study Area Key Plan

Document 2 - Local Area Key Plan

Document 3 - Existing Transportation Network

Document 4 - Approved Transportation Network

Document 5 - Service Road Alternatives 1, 2, 3, 4, 5

Document 6 - Service Road Alternatives 2`, 3`, 4`

Document 7 - Tables

Document 8 - Comparison of PAC and TAC Opinions

Document 9 - Comparison of Alternatives 5, 3 and 2

Document 10 - Recommended Alternative 5

 

 

DISPOSITION

 

Following Committee and Council approval, the Project File documenting the entire environmental assessment process and study recommendations will be prepared and filed for the 30-day public review period, in accordance with the provincial Environmental Assessment Act.

 

Once the formal review period is over and if there is no Part II Order request to the Minister of the Environment (previously known as a request for a ‘bump-up’ to a higher level of study), the project study will be considered approved. 

 

The recommended extension of Crawford Side Road to Dwyer Hill Road as a collector road with the appropriate right-of-way protection will be included in the appropriate schedule(s) of the City's Official Plan.  The extension of Crawford Side Road to Dwyer Hill Road is under construction by the developer for completion in 2004, and no additional road construction will be required by the City.

 


STUDY AREA KEY PLAN                                                                                           Document 1

                                                                                                                                                          

 


LOCAL AREA KEY PLAN                                                                                          Document 2

 

 


STUDY AREA                                                                                                               Document 3

 


APPROVED TRANSPORTATION NETWORK                                                       Document 4

 


SERVICE ROAD ALTERNATIVES 1, 2, 3, 4, 5                                                        Document 5

 


SERVICE ROAD ALTERNATIVES 2`, 3`, 4`                                                            Document 6

 


TABLES                                                                                                                         Document 7

 

 

Table 1

Fire Response Comparisons

Alternative

CCV (Existing Homes)

CCV (Future Homes

CCV (Homes Average)

CGCC

Existing (2003)

14:43

14:55

14:49

11:47

Alt. 1 (1997 MTO Baseline)

15:55

16:07

16:01

14:00

Alternative 5

15:11

14:13

14:42

14:00

Alternative 3

12:04

12:51

12:28

12:21

Alternative 2

13:53

14:04

13:58

11:03

 

 

 

Table 2

CCV Travel Time Comparisons

Alternative

CCV to Stittsville

CCV to Kanata and East

Existing (2003)

10:56

13:49

Alt. 1 (1997 MTO Baseline)

14:12

16:10

Alternative 5

14:12

16:10

Alternative 3

12:11

16:10

Alternative 2

10:48

14:38

 

 

Table 3

Canadian Golf and Country Club Travel Time Comparisons

Alternative

CG&CC to Stittsville

CG&CC to Kanata and East

Existing (2003)

7:57

10:49

Alt. 1 (1997 MTO Baseline)

12:28

14:26

Alternative 5

12:28

14:26

Alternative 3

12:28

14:26

Alternative 2

7:48

11:38

 

 

Table 4

Comparison of PAC and TAC Weights

Issue

PAC

TAC

Fire Response

18

36

Natural Habitat

17

21

Access

46

9

Land Use & Property

11

7

Cost

1

20

Other Factors

7

7


COMPARISON OF PAC AND TAC OPINIONS                                                      Document 8

 

 

The evaluation of the two groups (TAC and PAC), have resulted in two different preferred solutions.  The PAC, speaking for the community, have a preference for Alternative 2.  Alternative 2 provides the best performance for community travel issues.  The TAC preference is for a solution that provides some improvement in performance with no cost or environmental impact. 

 

The level of performance and associated costs are graphically shown below.  The detailed comparison of the trade-offs of all competing criteria are presented on the Resource Table.

Text Box: Acceptable PerformanceText Box: Increased PerformanceText Box: Performance 

 

 

 



COMPARISON OF ALTERNATIVES 5, 3 AND 2                                                   Document 9

 



RECOMMENDED ALTERNATIVE 5                                                                     Document 10