Report to / Rapport au :

Report to/Rapport au:

 

Transportation and Transit Committee /

Comité des transports et des services de transport en commun

and Council/et au Conseil

 

9 July 2003 / le 9 juillet 2003

 

Submitted by/Soumis par:  Ned Lathrop, General Manager/Directeur général

Development Services Department / Services d’aménagement

 

Contact/Personne-ressource:  Vivi Chi, Manager, Transportation Infrastructure/ Gestionnaire, Infrastructure des transports

580-2424, ext. 21877, vivi.chi@city.ottawa.on.ca

 

 

Ref N°:   ACS2003-DEV-POL-0036

 

 

SUBJECT: OTTAWA RAPID TRANSIT EXPANSION PLAN (ORTEP) – IMPLEMENTATION STRATEGY

 

OBJET: PLAN D’EXPANSION DU TRANSPORT EN COMMUN RAPIDE – STRATÉGIE DE MISE EN OEUVRE

 

 

REPORT RECOMMENDATION(S)

 

That the Transportation and Transit Committee recommend that Council receive the Consultant’s report (dated July 2003) and direct staff to:

 

1.                  Proceed immediately with the Environmental Assessment for the priority O-Train Expansion LRT line from Rideau Centre to Limebank (Riverside South), thus allowing the city to proceed with the option deemed most appropriate once funding mechanisms have been confirmed;

 

2.                  Proceed with the Environmental Assessment on the East-West LRT corridor;

 

3.                  Continue to negotiate with the Federal and Provincial Governments to receive at least 1/3 funding from each level of government for the priority O-Train Expansion LRT line;

 

4.                  Explore public-private partnerships for rapid transit in other jurisdictions and bring forward a recommended approach for the City of Ottawa;

 

5.                  Continue negotiations for acquisition of the CP Rail corridor between Leitrim Road and the Prince of Wales Bridge;

 

6.                  Continue negotiations and undertake the necessary due diligence studies to acquire property for a required maintenance and storage yard for the priority O-Train Expansion LRT line;

 

7.                  Prepare a detailed Ottawa Rapid Transit Expansion Program (ORTEP) financial plan for 2004 for inclusion in the 2004 budget deliberations; and

 

8.                  Include ORTEP project costs in the upcoming Development Charges By-law review.;

 

RECOMMANDATION(S) DU RAPPORT

 

Que le Comité des transports et des services de transport en commun recommande au Conseil de prendre connaissance du rapport du consultant (fait en juillet 2003) et de donner pour instruction au personnel :

 

1.                  de débuter immédiatement l’évaluation environnementale sur la ligne prioritaire de train léger sur rail (TLR) du projet d’expansion de l’O-Train, depuis le Centre Rideau jusqu’au chemin Limebank (Riverside Sud), de façon à permettre à la Ville d’appliquer l’option jugée la plus appropriée une fois les mécanismes de financement confirmés;

 

2.                  de débuter immédiatement l’évaluation environnementale relative au couloir est-ouest du TLR;

 

3.                  de poursuivre les négociations avec les gouvernements fédéral et provincial afin d’obtenir au moins un tiers du financement de chaque palier de gouvernement pour la ligne prioritaire de TLR;

 

4.                  d’analyser les partenariats publics-privés du transport en commun rapide dans d’autres administrations et de présenter une approche recommandée à la Ville d’Ottawa

 

5.                  de poursuivre les négociations en vue de l’acquisition du couloir du CP entre le chemin Leitrim et le pont Prince of Wales;

 

6.                  de poursuivre les négociations et d’entreprendre les études nécessaires, dans des délais raisonnables, en vue de l’acquisition de terrains pour l’entretien et le faisceau de garage requis à cette fin;

 

7.                  de préparer un plan financier détaillé concernant le programme d’expansion du transport en commun rapide d’Ottawa pour 2004 aux fins d’inclusion dans les délibérations budgétaires de 2004;

 

8.                  d’inclure les coûts du projet d’expansion dans l’examen du Règlement sur les redevances d’exploitation.

 

 

BACKGROUND

 

In the early 1970’s, the Regional Municipality of Ottawa-Carleton began to plan for the future needs of rapid transit in what is now the City of Ottawa.  The Rapid Transit Appraisal Study identified the future direction and priorities for transit development in the region to accommodate population growth to 750,000 and anticipated an investment of $300M ($1973) – or approximately $1.27B ($2002) - over a period of 20 years.

 

At that time, the City had a population of 472,000, with an employment base of 214,000 jobs. Most jobs were located in the downtown area and government was the primary employer.  A few developments were in the suburban area, mainly in Nepean and Gloucester.  The first development was just beginning in Orleans, with very little happening at that time in Kanata and Barrhaven.

 

The subsequent Rapid Transit Development Programme, completed in 1981, led to the construction of the initial 31km of transitway network (the section from Baseline Road in the southwest to Blair Road in the east and Hunt Club Road in the southeast).  The initial program was completed in 1996 at a cost of $420M (or approximately $600M in $2002) and, since then, has been expanded through new stations, park and ride lots, and freeway and arterial bus-only lanes.  The City operates a fleet of over 900 standard and articulated buses on more than 140 individual bus routes.  The City of Ottawa introduced its first rail transit service, the award-winning O-Train, as a pilot project in the fall of 2001.  Ridership on the entire system has increased almost 25% over the past six years, with a total of 87 million trips in 2002.  Per capita, Ottawa has the largest public transit ridership levels of any city its size in North America.

 

Some of these accomplishments were part of the original vision of the 1970s, others were a response to the changes that took place as the City grew.  They represent an investment of nearly $1 billion for the approximately 50 km transitway system.  This investment took place over 25 years, with 75% of that funding coming from the provincial government until 1996.  As the end of the lifecycle of the previous transit plan came near, plans for the next two decades have been developed.

 

The Rapid Transit Expansion Study, approved in February 2003, sets out the next steps and future direction for rapid transit in Ottawa over the next 20 years.  It identifies 13 separate transit corridors to be studied for the implementation of an integrated 163 km light rail/bus network.  The recommendations approved in the Rapid Transit Expansion Study and its companion document, the Transportation Master Plan (TMP), support Ottawa’s drive to build a more sustainable city.  Becoming more sustainable and maximizing the City’s investment in new infrastructure are critical factors in promoting economic growth.

 

Since the first transit plan was developed, Ottawa’s population has grown to 800,000 and has an employment base of 480,000.  We now have strong economic clusters in government, high tech, agriculture and tourism.  We are the fourth largest city in Canada and a significant player in the Ontario and Canadian economy.  The west end now has a significant high tech employment base, the east end has a solid biotech industry base, and federal government departments have expanded to areas beyond the downtown.  As well, Ottawa’s south end is poised to begin exponential growth which, if not appropriately supported by transit, could lead to significant conflicts between the needs of the new south urban community and those of more established communities in Alta Vista, the Glebe, and Centretown.

 

A large part of Ottawa’s successful economy can be attributed to investments in municipal infrastructure, particularly in transportation infrastructure.  The importance of transportation infrastructure was better understood at the federal and provincial levels of government in Canada during the seventies and eighties – and these levels of government are still reaping the benefits of their previous investments in municipal infrastructure.  Ottawa has enjoyed strong employment creation between 1993 and 2001, averaging 3.5% each year.  For every new tax dollar created in Ottawa, the federal and provincial governments receive 93 cents.  In the two years between 1998 and 2000, the federal and provincial governments collected $753 million in new tax dollars from growth in contrast to the $77 million collected by the City.

 

The politics of the 1990s saw the provincial government abandoning itstheir traditional roles in investing in public transportation in order to meet some shorter-term political goals.  What was once sustained, strategic funding has dwindled to ad hoc, project-based grant programs at considerably lower costs.  This change began to occur at the same time as cities were taking on greater importance in the global economy, and as national governments in Europe and the United States were reinvesting heavily in transportation infrastructure in order to make their cities more competitive – which, in turn, helped their national economies.

 

Canadian federal and provincial government policy has not yet caught up with the increased importance of Canadian cities as drivers of the national economy, with investment in public transit as one of its cornerstones.  In its 2002 Territorial Review of Canada, the Organization for Economic Co-operation and Development noted that,

 

“Canadian metropolitan regions have gone through remarkable expansion.  They are not only vital to the economic health of their provinces but also to that of the whole country.  Yet, they are confronted with several challenges, including the need to be competitive in a context of globalization, to limit urban sprawl, provide adequate public transportation, and avoid the deterioration of their inner neighbourhoods … Cutbacks in federal social and infrastructure investments were accompanied by the decentralization by the provinces of such responsibilities to the municipalities without always granting them the corresponding finances and capacities for revenue management and generation.  The whole approach to urban areas and their economic growth needs rethinking.”

 

Canada is, in fact, the only G8 country without a national urban transit investment fund.  As the City of Ottawa moves forward to implement the vision articulated in the Rapid Transit Expansion Study to support our continued economic growth while maintaining our quality of life, there is evidence that the political priorities of the federal and provincial governments are beginning to change, and the importance of renewed investments in municipal infrastructure recommended by economists, international experts and the international business community are receiving more consideration.

 

Because building a sustainable city is about fiscal sustainability as well, the implementation strategy for the Ottawa Rapid Transit Expansion Program involves a series of options that will allow the City to move forward to meet it’s long-term needs while being able to adapt to current and future circumstances.

 

 

DISCUSSION

 

The Rapid Transit Expansion Study (RTES) used land use, population and employment forecasts to identify travel demand patterns for rapid transit needs over the next two decades.  These travel demand patterns were matched with potential transit corridors and suitable technologies to determine the best fit.  The resulting preferred network, comprising of complementary light rail and bus rapid transit corridors (to be phased in over the next 20 years or more), was approved by City Council in February 2003.  The implementation of the rapid transit network, along with transit-supportive land use policies, will ensure that the City’s overall transit modal split target of 30% will be achieved.

 

Upon approval of RTES, staff was directed to develop an implementation strategy for this long-term plan, including timelines, funding and partnership options, and financial implications.  It was important to ensure that the implementation of Ottawa’s Rapid Transit Expansion Program (ORTEP) reflect both sound development and transit principles along with fiscal sustainability so that Council would have enough information to determine the next steps to be taken.

 

Since the development of the program’s costs and schedules are important components of the overall implementation plan, detailed descriptions of each unique corridor and field reviews were undertaken in order to determine what would be necessary to actually complete each project.  For example, conditions of each structure were examined and any future upgrades or expansions were costed based on the unique characteristics of that individual structure.  Difficulty of construction, potential complexity of design, location, function etc. are all factors that influence the cost of a specific element of the project.  In other words, a detailed project scoping and costing exercise, using the comprehensive  Work Breakdown Structure (WBS) technique was undertaken.  This provides for greater confidence in the resulting project (and ultimately program) cost.  Other work included the identification of all planning, design and construction steps required as well as program-wide tasks that impact all projects.  Funding sources and financing alternatives have been investigated along with the assessment of approaches for project delivery, identification of staffing and project management issues and requirements, and the development of detailed work programs for the overall ORTEP plan and for the priority LRT O-Train expansion project.

 

ORTEP consists of additions and extensions to the existing rapid transit network and is mainly based on exclusive or semi-exclusive rail or bus rights of way.  The LRT corridors (102 km) include double tracking, electrification, frequent (5 minute) service, 105 LRT vehicles, 7 park-and-ride lots and 75 stops and 2 storage and maintenance facilities.  The BRT additions (61 km) include 5 park-and-ride lots and 49 new stops in addition to new vehicles and storage facilities.

 

The ORTEP corridors are listed below and are shown in Document 1.

 

·        (1-LRT)  O-Train Expansion Corridor – Priority Project

·        (2-LRT)  East-West Corridor (including an interim BRT Cumberland Transitway)

·        (3-LRT)  Carling Corridor

·        (1-BRT)  West Transitway Corridor

·        (2-BRT)  Southwest Transitway Corridor

·        (3-BRT)  Baseline Corridor

·        (4-BRT)  Hurdman to Blair Corridor

·        (5-BRT)  East Transitway Corridor

·        (6-BRT)  Albert/Slater Corridor

 

The Priority Project is planned to go forward as the first initiative, with others rolling out over subsequent years to 2021, although this is obviously dependent on the level of funding available from senior levels of government and the City’s own financial situation.   The schedule for ORTEP projects is shown in Document 2.  In 1972, when the Transitway was first envisioned and then planned, funding levels were known and the City was able to move forward with implementation as foreseen.  The fact that this is no longer the case makes the long-term process more difficult.

 

The ORTEP schedules, outlined in Document 2, generally follow the priorities set in the RTES report and are based on the logical rollout of each project and their interdependencies.

 

The 163 km expansion of the rapid transit program will cost $3.4B (in $2003) over 20+ years.  This cost is very much in line with rapid transit expenditures in the past (in the order of $1B in $2002), since the expansion program is 3-times that of the existing system. Document 3 shows the summary table for the cost of ORTEP over the entire 20+ years. 

 

The Priority Project (Rideau Centre to Limebank (Riverside South) as identified in the RTES report, is described in Document 3 and Document 4 (Summary Report), and is estimated at $750 million.

 

The actions undertaken as a result of the motions approved by Transportation and Transit Committee on 19 February 2003 when the RTES findings were deliberated are outlined in Document 5.

 

Priority LRT Project – Staging Options

Given the need to continue to develop the rapid transit network in Ottawa in order to support continued economic growth, staff looked at moving forward with a staged approach for the Priority Project based on current likely levels of partnership funding from the federal and provincial governments and what the City is able to afford to contribute now and in the near future.

The initial conditions for staging development were that the project had to go to at least LeBreton, and south to at least a park-and-ride station.  As well, this staging must allow for subsequent extensions into the downtown and further south.  If the Priority Project were to be implemented in increments, it was important to determine where costs could be reduced as an interim measure while still ending up with a value-added stand-alone project.  Minimal “throwaway” costs and minimal interruption to service as the project is expanded/extended has to be considered.  Staging of the Priority Project will result in a further time extension in the achievement of the goals of the rapaid transit expansion plan.  These issues will all be brought forward during negotiations with senior levels of government on the full priority LRT line.

 

Council has already approved the RTES recommendation for electric LRT.  However, given current fiscal realities, the option of whether to continue with diesel trains in the corridor and convert to electric LRT in subsequent phases or to convert now to electrification was investigated.  From the perspective of network continuity, compatibility and integration with urban design and land use, and environmental considerations, the delay of electrification and the continued use of DMUs (diesel multiple units) presents the following issues:

 

·        Electric vehicles maximize the reduction of greenhouse gas emissions (a very important consideration in applying for Federal funding);

·        Grade-climbing capability is restricted to a maximum of 5% compared to 9% for electric vehicles (this would affect construction costs, performance of vehicles);

·        Wide minimum turning radius of 90m compared to 20-25m for electric vehicles (wide turning radius consumes more land and is inappropriate for extensions into dense, built-up areas such as the downtown);

·        DMUs are approximately 30% more expensive than electric trains;

·        Conversion to an electrified system in the future would be disruptive and more costly in the long term;

·        A mixed fleet (combination of DMUs and electric vehicles) costs more to operate due to lack of commonality.

 

Because of the City’s cash flow requirements, staff investigated the expansion of existing DMU service even though it does not comply with the ultimate network plan.  The existing service would be extended on a single track to LeBreton Station---- and to Leitrim Station---- in the south.  An improvement to 10 minute frequency service is possible, with 1--- additional siding at South Keys, 10--- stations (5 new) and 1--- park-and-ride lot at Leitrim.  At this stage, there would be no requirement to grade-separate the DMU line over the Walkley rail Subdivision and VIA rail service on the Beachburg Subdivision.(mention need or no need to grade separate??)  An improved maintenance/storage yard would be required at Walkley.  The greatest benefit for extending the existing DMU service is the lower initial outlay of capital, estimated at $150 million initially.  The City’s average annual capital contribution would be approximately $10---- million for the next 5 years, with early operation by 2008----.

 

Deferring the move to double tracking presented another staging opportunity.  Although this equates to a lower service frequency at the outset, fewer vehicles would be required.  It would necessitate additional sidings, but would defer the construction of several new structures and reduce initial maintenance and storage requirements.  Eventually, however, double-tracking will be necessary to improve frequency of service and to increase ridership in order to meet the Official Plan’s transit modal split target.

 

There are 3 feasible options for staging the Priority Project as electrified LRT.  With the extension of the rail service to LeBreton, the existing transitway east of Bayview would also have to be relocated at a cost of about $45million.  Each option has a different cost and different service level (and consequential ridership).  These options are being presented within an implementation framework that will be responsive to funding as it becomes available.

 

1.      Full Implementation: Rideau Centre to Limebank $750M

2.      Partial Implementation: LeBreton to Leitrim - double track $530M

3.      Start-Up Implementation: LeBreton to Leitrim - single track $295300M

 

Full implementation would result in frequent 5-minute service on electrified double-track rail for the entire section from Rideau Centre to Limebank.  It would bring LRT service into the downtown and serve the fast-growing community of Riverside South, and link to the Airport.  With a total of 19 stations and 2 park-and-ride lots (at Lester and Leitrim), this entire corridor can be operational by early 2011.  Assuming 2/3 funding from senior levels of government, the City would still be required to contribute $250M (an average annual capital commitment of approximately $31M for the next 8 years).

 

This project can only be begun in full if the federal and provincial governments make in the near future the kinds of significant investments in municipal transportation infrastructure that are being made in by the upper levels of government in Europe and the United States.  While the call for this kind of investment has been growing among economists and international business leaders for some time, political awareness at the federal and provincial levels of government has come at a somewhat slower pace, and it is not likely that the levels of investment needed will be forthcoming in the near future.

 

Partial implementation would focus on the middle section of the Priority Project (LeBreton to Leitrim).  Frequent 5-minute service on electrified double-track rail is still retained.  This project includes the 2 km single-track rail link to the Airport, 12 stations, 2 park-and-ride lots (Lester and Leitrim) for the benefit of the south-end and rural residents, and a new maintenance and storage yard for 25 new LRT vehicles (and later additions to the LRT fleet).  Extension to LeBreton (Booth Street) would serve as a major catalyst for the redevelopment of LeBreton Flats, south of the Aqueduct.  The terminus at LeBreton would provide direct transit connections to the City of Gatineau, as well as to downtown Ottawa.  Service on this section could begin in 2009.  The remainder of the Priority Project (to Rideau Centre, and from Leitrim to Limebank) would be extended later, as more funding becomes available.  There would be no throw-away costs and service disruption would be minimal when the line is extended.  The City’s average annual capital contribution would be approximately $29.5M for the next 6 years.

 

Start-up implementation would further scale back the Priority Project while still operating from LeBreton to Leitrim.  Seven to eightTen- minute service (an improvement over the current 20-minute frequency) would operate on a single track, with 4 additional sidings, 11 stations and 1 park-and-ride lot.  Grade separation would still be required over the two crossing railways.  The extension to the Airport would await a later stage.  The major advantage of the start-up project is the lower initial capital investment required.  However, there will be some future “throwaway” costs and some disruption to service when the line is twinned and expanded in the future.  AnyThis interim staging will also result in a further time extension in the achievement of the goals of the rapid transit expansion plan.  These issues will all have to be considered in continuing negotiations for senior government subsidy for the priority LRT line.  For the start-up project, the City’s contribution would be $100M, or approximately an average of $17M annually for the next 6 years.

 

Major drawbacks of the DMU options include:  (elaborate on points made previously, or addition of new points.  What’s the throw-away cost?, Cost to convert to Option 3? etc.)

Public-Private Partnership Potential

 

The City of Ottawa has begun to investigate the benefits of using public-private partnerships to help meet some of its infrastructure needs.  ORTEP has several potential types of structures for public-private partnerships.  Once the range of acceptable options is narrowed down at a strategic level, either a Design-Build-Operate-Maintain (DBOM) or a Design-Build-Operate-Finance-Maintain (DBOFM) partnership structure may be appropriate.

 

Moving forward with an Expression of Interest could reveal the potential of these partnership options and the degree of risk transfer to a private partner.  These options would need to be carefully investigated and weighed as a project moves toward implementation.

 

 

Funding the Program (First Stage and Beyond)

 

ORTEP continues a significant investment for the City in transit infrastructure and requires major funding commitments by all levels of government for the program to be implemented to meet the needs of now and future citizens.  As has been described earlier, governments’ previous investments in Ottawa’s infrastructure have yielded significant economic benefits for both the federal and provincial governments.  Again, in its 2002 Territorial Review of Canada, the Organization for Economic Co-operation and Development concluded that,

 

“…Whereas Canadian cities have long boasted a better quality of life than American cities, it seems that the United States is currently more involved in solving its urban problems than is Canada… Canadian cities have limited financial capacities to embark on infrastructure spending.  They have benefited from timely infrastructure investments in the past, but these investments were not renewed when appropriate during the 1990s… Canadian cities are therefore at a comparative disadvantage, since infrastructure is critical to enhancing the competitiveness of cities and their export potential.”

 

If the City of Ottawa is to continue to grow and compete in the world economy for the benefit of its residents and the provincial and federal economies, it requires significant additions to its rapid transit infrastructure.  Ottawa, like other large cities in Canada, cannot and should not do this alone.

 

Federal and Provincial Funding

 

Currently, there are two primary shorter-term funding sources for transit infrastructure in Ontario:  the Federal Government’s Canada Strategic Infrastructure Fund (CSIF), and the Ontario Government’s Transit Investment Partnership (TIP).

 

CSIF, established in 2001/2002 with an initial commitment of $2 billion, was doubled in Budget 2003 to a total $4 billion over the next ten years.  Together with a doubling of the CSIF commitment, the Government of Canada also announced a specific commitment to an additional $1 billion in funding for municipal infrastructure in Budget 2003.

 

In September 2001, the Province of Ontario (through MTO and SuperBuild) announced a new ten-year $3.25 billion program of investment in transit in Ontario.  Of this, $1.5 billion was earmarked for inter-regional transit expansion, with $1.25 billion for the Golden Horseshoe and $250 million for the remainder of the province.  The orientation of both funds has now expanded from inter-regional transit to all transit projects (urban or regional).  The $250 million earmarked for the rest of the province over the period from 2001 to 2010 is called the Transit Investment Partnership (TIP).  With over 80% of the transit ridership outside of the Golden Horseshoe, Ottawa should be eligible for a large proportion of the available funds.

 

For 2002/2003, the province announced funding for public transportation in Ottawa from two programs. The Transit Capital Renewal Program earmarked $25.8 million over 2002 and 2003 for bus replacements and refurbishing, and the Transit Investment Partnership will invest $19.7 million for transit expansion.

 

It is essential if Ottawa, like any other Canadian municipality with a major transit system, is to expand its rapid transit system, a minimum of 2/3 funding must be provided by the federal and provincial governments. 

 

Recent discussions with the federal and provincial governments indicate serious interest in rapid transit projects in Ottawa.  Although no actual amount of funding has yet been confirmed, there has been an indication from federal sources that $75-$100 million might be available for an initial investment.

 

City funding

 

The City’s Long Range Financial Plan: First Steps (LRFP), brought forward in October, 2002, notes that funding transportation infrastructure is one of the major challenges of growth, and that transportation solutions may need to involve the expansion of both transit and road networks.  Both the Transportation Master Plan (TMP) and the Rapid Transit Expansion Study (RTES) identify the importance of these initiatives to the long-term health and sustainability of the City of Ottawa.

 

One of the major observations in the LRFP is that investment in sustainable development saves money in the long term, and that,

 

“The City’s capital infrastructure deficit can be reduced by changing the way the City develops. One alternative is investing in high quality transit, which in turn reduces the need to build more arterial roads and expressways. This alternative also provides significant side benefits, such as less air and water pollution, and the creation of high quality community living. Any increase in the share of trips taken by transit reduces infrastructure costs.”

 

At the same time, the City of Ottawa, which has frozen property taxes for eleven consecutive years, is currently facing a capital funding gap of about $148 million over the next four years for all of its transit, roads, lifecycle and infrastructure requirements.  It is estimated the Priority Project will average $17-31 million per year over the 6-year implementation period.

 

At this point, $29 million has been identified for rapid transit initiatives over the next four years.

 

The City cannot afford to do all of the projects that currently make up its total 2004 capital envelope.  Fundamentally, City Council will need to set priorities for which projects it will fund within the available resources and determine how they will be funded.

 

As both ORTEP and the Transportation Master Plan move forward, the policies and principles for funding priority projects as set out by the LRFP should be considered as funding is allocated.  One major consideration is whether or not the Priority Project should be funded through pay-as-you-go or through debt financing.  Although the City’s goal is to move to a maximized pay-as-you-go funding model overall, it was noted that there were some projects that could be best funded through debt financing. These involved those large, long-term projects related to capacity expansion or growth and those that leverage funding from others, and specifically include those to be financed from development charges, future new non-traditional infrastructure projects such as new transit programs, or projects that are tied to third party matching funding.

 

Development Charges

 

Municipal development charges must provide some level of support to offset the municipal share of major transit investments as they have in the past for major municipal road infrastructure, as was indicated in the LRFP.  The City’s Development Charges Bylaw is being reviewed this year and required transit investments will be included in the revised development charges calculations.

 

Other Potential Funding Mechanisms

 

Currently, a number of municipalities in Canada receive a share of their province’s fuel tax. Calgary and Edmonton receive 5 cents per litre, Vancouver collects 2.5 cents per litre and Montreal receives 1.5 cents per litre.  This revenue-sharing arrangement has been widely recommended by economists and is presently being pursued by large municipalities, including Ottawa, through their federal and provincial municipal associations.  Even a 2.5 cents per litre share from each level of government would provide the City with $60 million annually.

 

Required Near-Term Action

 

Present O-Train Status

 

The current O-Train operation has been extended until 30 April 2005.  The service operates with three Bombardier Talent trains, which have been purchased by the City with a sellback option that can be exercised by the City until 30 April 2005.  The return of the trains to Bombardier at this point would realize approximately $9 million.  In addition, import duties on the trains of $1.6 million have been deferred until January 2005.  These may be payable if the trains are kept much beyond the beginning of 2005.

 

The use of the rail corridor from Bayview to Leitrim and the maintenance facility at Walkley Yards is governed by a lease agreement between the City and Canadian Pacific Rail.  This lease continues until 2005.  During the term of the lease, the City can purchase the corridor and/or Walkley Yards at a pre-agreed price.

 

It is clear from the time-lines developed for this report that the current O-Train service can be continued until at least the Spring of 2007, perhaps longer depending on the next steps taken for the Priority One project.  Continued running of the Talent vehicles will require the continued use of the current maintenance facility at Walkley Yards whether or not this site is ultimately selected for the LRT maintenance facility.

 

The arrangements with both Bombardier and CP Rail will need to be adjusted to take account of the current circumstances as the detailed project plan is developed.  The purchase of the rail corridor should take place as soon as possible since it is clear that this property will be needed for any new LRT system.  In the short term, an agreement to extend the lease on the Walkley Yards property should be pursued, while a thorough investigation of the suitability of that site and other possible locations for a long-term maintenance facility is undertaken.

 

East-West Corridor - Opportunity

 

Although initial travel demand levels indicate that this LRT line is not required immediately, the implementation of the LRT would also present a unique opportunity to influence development within growth areas of Kanata and Orleans as well as inside the Greenbelt.  As such, it would be prudent to undertake the environmental assessment for this corridor now.  If the planning work were completed ahead of time, the City would then be in a position to discuss public-private partnerships with interested parties as they come forward.  This creates the opportunity to advance the implementation of the East-West corridor earlier than planned.

 

Initiating the environmental assessment also signals to senior levels of government that the City is serious about its entire comprehensive rapid transit network - not just one priority component.  The entire network has to be realized in order to fully attain the vision, goals and targets of the Official Plan.

 

Required Actions

 

The following activities should be initiated now and in 2004 in order to advance the priority O-Train expansion LRT project:

·        Undertake the environmental assessment for the Priority Project;

·        Undertake the environmental assessment for the East-West LRT Corridor;

·        Continue negotiations with the senior levels of government for Priority Project funding

·        Extend the existing O-Train agreements to at least 2007;

·        Complete acquisition of the CP Rail line;

·        Investigate suitable locations for the maintenance yard (Walkley or elsewhere); and

·        Establish a program management team.

 

An early estimate of approximately $24 million may be required in the 2004 budget (this will be discussed as part of the 2004 budget deliberations) to:

·        Initiate the environmental assessment for the East-West LRT corridor;

·        Purchase the CP Rail line;

·        Purchase an appropriate LRT yard site; and

·        Development of the 30% design and standards for the LRT project.

 

 

COMPLIANCE WITH OFFICIAL PLAN AND TRANSPORTATION MASTER PLAN

 

The ORTEP program complies with both the Official Plan and the TMP.  This implementation strategy is a detailed examination of the cost and priorities of the rapid transit projects identified in the TMP to support the projected growth of the City.

 

 

ENVIRONMENTAL IMPLICATIONS

 

Implementation of any elements in the rapid transit expansion program will result in reduced levels of transportation-generated greenhouse gasses and contribute to Canada’s achievement of Kyoto Protocol targets.  For the electrified Priority Project alone, this means an annual reduction of up to 50 million kg (or higher) of greenhouse gas emissions.

 

 

CONSULTATION

 

Public consultation was not undertaken as this implementation strategy is a follow-up action to the RTES.

 

 

FINANCIAL IMPLICATIONS

 

Funds for the required environmental assessment of the priority O-Train Expansion LRT project are already included in the 2003 budget allocations.  Most of the costs related to this program were not included in the 2003 capital budget and four year forecast. Additional required funds will be submitted and discussed as part of the 2004 budget deliberations. Annual impacts of the various options outlined in the report will need to be prioritized against other initiatives to fit into existing funding envelopes.

 

 

ATTACHMENTS

 

Document 1 ORTEP Corridors

Document 2 ORTEP Project Schedules

Document 3 ORTEP Cost Summary

Document 4 ORTEP – Summary Report

Document 5 Actions Arising from Transportation & Transit Committee’s Motions (19 Feb 03)

 

 

DISPOSITION

 

Following Committee and Council approval of these recommendations, Development Services Department will initiate the required environmental assessment studies for the priority O-Train Expansion LRT line and the East-West Corridor.

 

Staff will continue to negotiate for funding from the Canada Strategic Infrastructure Fund and the Transit Investment Partnership program and will continue to supplement supporting documentation if and when required by the funding partners.  As well, negotiations will continue towards establishing fairer and more appropriate revenue-generating arrangements, such as sharing revenues collected from fuel taxes.

 

Funding for required rapid transit expansion will be included as part of the review and update of the City’s Development Charges Bylaw.

 

Staff will prepare a detailed funding plan for the initial City funding for the Rapid Transit Expansion Program for inclusion in the 2004 budget deliberations.

 

Staff will continue to negotiate a property agreement for the CP Rail corridor and for an appropriate site for a storage and maintenance yard along the priority LRT corridor.

 

The Strategic Delivery Unit will work with Development Services and Transportation, Utilities and Public Works staff to explore public-private partnerships for rapid transit in other jurisdictions and prepare recommendations for the Committee and Council.


ORTEP CORRIDOR Document 1

 


ORTEP PROJECT SCHEDULES Document 2

 



ORTEP COST SUMMARY Document 3

 

Project Corridors and Program Costs

 

Corridor

Cost ( $M 2003)*

 

Item

Totals

1-LRT  – O-Train Expansion Priority Project (Rideau Centre-Limebank)

$600

 

Priority LRT Vehicles

$150

 

Priority LRT Subtotal

 

$750

1-LRT  – Future Extensions (Rideau-Montreal; Barrhaven)

$330

 

2-LRT  - East West Corridor

$976

 

3-LRT  - Carling Corridor

$254

 

             Other LRT Vehicles

$480

 

Other LRT Corridors Subtotal 

 

$2,040

LRT Total

 

$2,790

 

 

 

1-BRT  - West Transitway

$230

 

2-BRT  - Southwest Transitway

$101

 

3-BRT  - Baseline Corridor

$46

 

4-BRT  - Hurdman to Blair Corridor

$119

 

5-BRT  - East Transitway

$30

 

6-BRT  - Albert/Slater Corridor

$20

 

BRT Corridors Subtotal

 

$546

BRT Vehicles

$53

 

BRT Total

 

$598

 

 

 

ORTEP Total Estimated Cost

 

$3,388

 

*  Costs include property, engineering, project management and contingency

 

Priority Project Cost  ($M 2003)

WBS

Cost Element

Full Implementation

Rideau Centre to Limebank

Double Track

Partial Implementation

LeBreton to Leitrim

Double Track

Start-up Implementation

LeBreton to Leitrim

Single Track

10

Property

25

21.9

20

20

Grading, Track & Structures

137.5

103

32.5

30

Stations & Park and Rides

61

47

16.5

 

Yard

37.5

37.5

19.5

 

LeBreton Transitway

45

45

45

 

Associated Works

23

0

0

40

Vehicles

150

84

60

45

Traction Power

70

48.5

30.5

50

Signals / Train Control

31.5

23

12

60

Utility Relocation

6.5

0

0

70

Engineering

50.5

37

18

80

Project Management

33.5

24.7

12

90

Contingency

79

58.4

29

Total

 

$750

$530

$295


ORTEP SUMMARY REPORT Document 4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CITY of OTTAWA

RAPID TRANSIT

EXPANSION PROGRAM

(ORTEP)

 

SUMMARY REPORT

 

July 2003

 

 


TABLE OF CONTENTS

 

1. Introduction

2. Background

2.1 Public Transit in Ottawa

2.2 The Growth of Ottawa

2.3 The Rapid Transit Expansion Study (RTES)

3. Ottawa Rapid Transit expansion Program (ORTEP)

3.1 ORTEP Corridors Summary Descriptions Introduction

3.2 Corridor Descriptions

3.3 Program Wide Tasks

4. Funding the Program

4.1 Estimated Program Capital Costs

4.2 Available Federal and Provincial Funding programs

4.3 Other Funding Sources

4.4 Public or Private Financing

4.5 Impacts of Government Funding Support Levels

4.6 Recommended Financing Approach For The Priority LRT Project

5. Delivery approaches

5.1 Traditional

5.2 Public-Private Partnerships

5.2.1 Public- Private Contract Options

5.2.2 Contract Term

5.3 Recommended Delivery Approach

6. ORTEP Work Program

6.1 ORTEP Schedules

7. Priority project work plan

7.1 The Priority Project (1-LRT:  Rideau Centre to Limebank)

7.2 Extension of the LRT Service

7.2.1 Background

7.2.2 Rationale for the Route

7.2.3 Rationale for the Technology / Vehicle

7.2.4 Use of existing DMU fleet

7.3 Proposed Priority Project Schedule

Tasks

7.4 Preferred Construction Staging Plan

7.5 Minimum Feasible Start-up Project

8. Program staffing resources

8.1 Introduction

8.1.1 Implementation

8.1.2 Defining the Scope of Work

8.2 Program Management

9. Summary conclusions


 

 


 

Introduction

In April 2003, the City of Ottawa initiated the development of an implementation strategy for the Ottawa Rapid Transit Expansion Program (ORTEP).  The need for this implementation strategy follows the completion of the Rapid Transit Expansion Study (RTES).  The RTES project identified a rapid transit network for Ottawa comprising both light rail and bus transit technologies.  RTES also included some conceptual level costs and implementation timings.  The purpose of this study is to define the costs of the ORTEP more closely, develop an implementation schedule that considers all of the required planning, approval, design and construction stages necessary for each of the individual projects that make up the rapid transit network, and lay out a detailed implementation plan for the LRT O-Train expansion project (Priority Project).

 

Background

Public Transit in Ottawa

Higher-order public transit, in the form of Bus Rapid Transit (the Transitway), has been part of Ottawa since the 1980’s.  The initial 31 km Transitway network was completed in 1996 and has been expanded through new stations, park and ride lots, and freeway and arterial bus-only lanes.  The City of Ottawa introduced its first rail transit service as a pilot project in the fall of 2001.  Known as the O-Train, this diesel rail transit service operates on a leased Canadian Pacific Railway branch using Bombardier Talent rail vehicles.  The City’s Transit Services Branch, OC Transpo, also operates over 900 standard and articulated buses on more than 240 individual bus routes.  Ridership has increased almost 25% over the past six years, with a total of 87 million trips in 2002.

The Growth of Ottawa

Ottawa is one of the most desirable cities in Canada in which to live and do business, and it is also one of the fastest growing.  Over the past 20 years, the City’s population has increased by 41.6%.  In the next 20 years, the population is forecast to increase by a further 50% from approximately 800,000 to 1,200,000 people.

In order to maintain Ottawa’s attractiveness as an innovative and competitive city with an exceptional quality of life, while managing this tremendous level of growth, the City of Ottawa’s new Official Plan describes a transportation system that emphasizes transit, walking and cycling in a compact city.  The plan assumes that the proportion of peak‑hour travel on transit will increase from 17% to 30%.  Given the forecast increase in population, this means that transit usage would grow from 87 million to almost 260 million trips annually over the next 20 years.

The Rapid Transit Expansion Study (RTES)

The purpose of the Rapid Transit Expansion Study (RTES) was to develop a long-range strategic plan for rapid transit in Ottawa.  The study used land use, population and employment forecasts to identify travel demand patterns for future rapid transit.  The strongest travel demand patterns were matched with potential transit corridors in a screening process to determine the best fit. Potential rapid transit corridors were identified from previous transportation plans, stakeholder/public consultation, and field observations; then the most promising corridors were combined into rapid transit  networks and matched with suitable technology.

Five network options were developed and assessed.  The networks were evaluated using factors reflective of the 2020 Charting A Course principles to formulate a ‘preferred’ network concept. Based on public and stakeholder input, the preferred network was then refined and resulted in the recommended Rapid Transit Network.  It includes the following elements:

§Electrified light rail (LRT) to replace the existing O-Train service, extended south to the Airport and Riverside South, then west to the South Nepean town centre; 

§LRT service through downtown Ottawa connecting the O-Train corridor to Rideau Street, Montreal Road, and the Blair Transitway Station;

§LRT service on the east-west CN corridor connecting Kanata North, Bells Corners, Colonnade, Greenboro and Cumberland;

§LRT service on Carling Avenue between the O-Train corridor and Bayshore and connecting Bayshore to the new east-west LRT service on the CN corridor;

§A new BRT corridor between the Innes/Blair intersection and the Southeast Transitway serving the Smyth Road Hospital complex;

§Substantial improvements to the Albert/Slater downtown Transitway;

§Transitway improvements and extensions along:

oThe West Transitway between Bayshore Station and Pinecrest Road, west from Eagleson past Terry Fox and the Corel Centre, to Hazeldean Road;

oThe Southwest Transitway between Hunt Club and Nepean Town Centre;

oThe East Transitway beyond Place d’Orleans to Trim Road;

§BRT service in the Baseline/Heron corridor between the West Transitway and the Southeast Transitway.

 

 

The recommended Rapid Transit Plan was approved by the City of Ottawa’s Transportation and Transit Committee oin 19 February 2003 (subsequently approved by council on 26 February 2003) and included a recommendation to develop an implementation strategy for the plan. City staff and the Consulting team have proceeded to develop an Implementation Strategy including timelines, funding and partnership options, and financial implications.  TThis report summarizes that implementation strategy.

 

 

 

Developing the implementation strategy involved detailed assessments of potential corridors, costing of each project based on the selected corridors, identification of all planning, design and construction steps required for each project, and project scheduling. The strategy also involved identification of funding sources and financing alternatives, assessment of approaches for project delivery, identification of staffing and project management issues and requirements, and the development of detailed work programs for the overall ORTEP plan and for the priority LRT O-Train expansion project.

 

 

Ottawa Rapid Transit expansion Program (ORTEP)

ORTEP Corridors Summary Descriptions Introduction

ORTEP Project Summary Description

 

The 2003 RTES report identified 13 separate transit corridors to be studied for the implementation of an integrated Light Rail Rapid Transit (LRT) and Bus Rapid Transit (BRT) network.  These have been regrouped into 3 LRT and 6 BRT corridors in the ORTEP study.  Exhibit 3.1, on the next page, displays this corridor grouping.  Table 3.1 , below, describes outlines key specifications of the corridors and their costs excluding vehicles.   Exhibit 3.1, on the following page, displays the corridor grouping.

At this time, individual ORTEP corridors have been shown as an alignment that is representative of what could be considered for further refinement as detailed planning and design tasks are undertaken.  The alignments have been developed based on the RTES report, information available from previous environmental assessment reports and field reviews.  It is important to note that all corridors have or will be subject to some level of environmental assessment (EA), which will include public input.  That work will result in a definitive alignment with a functional design level of detail.  Current assumptions will be re-evaluated during that EA work.

 

 

Some of the current assumptions are:

LRT is on twin tracks unless identified otherwise;

LRT will not be run on existing freight track;

Existing freight tracks to be relocated within ROW to accommodate LRT;

LRT will be located on new continuous welded rail (CWR);

Existing subway structures will be retained for current rail usage;

New subway structures will be constructed for the LRT;

Overhead road structures will be modified to accommodate LRT;

Exclusive transit right-of-ways will be grade separated from other means of transportation;

Semi-exclusive right-of-ways will have controlled access and may be co-located with other means of transportation;

Transit priority measures will be employed on all facilities that share roadway right-of-ways; and

A reduction in road capacity for non-transit vehicles is acceptable.

 

TABLE 3.1 - ORTEP CORRIDORS

Corridor

Project

Distance (km)

Stations

Cost

 

 

Semi.

Excl.

Stops

P&R

2003 $M

1-LRT corridor

O-Train Expansion Corridor 

19.7

22.4

33

3

$930

2-LRT corridor

East - West Corridor

3.2

43.6

25

4

$976

3-LRT corridor

Carling Corridor

10.5

2

26

-

$254

1-BRT corridor

West Transitway Corridor

2

9.5

12

1

$230

2-BRT corridor

Southwest Transitway Corridor

-

8.0

5

1

$101

3-BRT corridor

Baseline Corridor

6.5

-

13

-

$46

4-BRT corridor

Hurdman to Blair Corridor

2.2

6.8

11

-

$119

5-BRT corridor

East Transitway Corridor

5.6

1.0

2

1

$30

6-BRT corridor

Albert/Slater Corridor

-

-

6

-

$20

Notes:  P & R = park and ride.  Preliminary property cost, engineering and contingency included in estimate, vehicle costs not included in estimate


 



Corridor Descriptions

The following pages provide brief descriptions of each of the ORTEP corridors as illustrated in the previous Exhibit 3.1.  Table 3.1 below provides summary detail with respect to type of right of way, number of stations, number of park and ride lots, and corridor costs exclusive of vehicles.

 

TABLE 3.1 - ORTEP CORRIDORS

 

 

Corridor

Project

Distance (km)

Stations

Cost

 

 

Semi.

Excl.

Stops

P&R

2003 $M

1-LRT corridor

O-Train Expansion Corridor 

19.7

22.4

33

3

$930

2-LRT corridor

East - West Corridor

3.2

43.6

25

4

$976

3-LRT corridor

Carling Corridor

10.5

2

26

-

$254

1-BRT corridor

West Transitway Corridor

2

9.5

12

1

$230

2-BRT corridor

Southwest Transitway Corridor

-

8.0

5

1

$101

3-BRT corridor

Baseline Corridor

6.5

-

13

-

$46

4-BRT corridor

Hurdman to Blair Corridor

2.2

6.8

11

-

$119

5-BRT corridor

East Transitway Corridor

5.6

1.0

2

1

$30

6-BRT corridor

Albert/Slater Corridor

-

-

6

-

$20

 

Notes: P & R = park and ride.

Semi = semi-exclusive right of way

Excl. = exclusive right of way

Preliminary property cost, engineering and contingency included in estimate.

Vehicle costs not included in estimate

 

O-Train Expansion Corridor (1-LRT)

This $930M light rail corridor extends consists of twin tracks from Barrhaven near Jockvale Road in the South Nepean Town Centre (tying in with the Southwest Transitway Corridor 2-BRT), easterly through the Riverside South Community, northerly along the current O-Train Pilot Corridor (crossing over the East-West Corridor (2-LRT), then through LeBreton Flats and Downtown Ottawa on Sparks and Rideau Streets. The corridor continues easterly on Montreal Road to the NRC campus at Blair Road, then south through the campus and existing hydro corridor to its termination with a connection to the East-West Corridor (2-LRT) south of Innes Road.

East-West Corridor (2-LRT)

This $976M Light Rail corridor extends consists of 46.8 km of twin light tracks from the intersection of Klondike and March Roads in Kanata, through the Kanata North Business Park, along the Ottawa Central Railway and Beachburg Rail Subdivision to the Queensway-Carleton Hospital Campus (tying in with the Carling Corridor (3-LRT)). Service will continue easterly to the O-Train Expansion corridor (1-LRT) at Greenboro, through Walkley Rail Yard, the Alexandria Rail Subdivision, along a corridor south of Innes Road, connecting again to the O-Train Expansion Corridor (1-LRT) at Blair Road, then traveling south of the Blackburn Hamlet Bypass along the Cumberland Transitway alignment to Trim Road. 

Carling Avenue Corridor (3-LRT)

This $254M Light Rail corridor extends consists of twin tracks from the Queensway-Carleton Hospital, along Holly Acres Road, to Bayshore Shopping Centre, along Woodridge and Bayshore Drive to Carling Avenue, then easterly along the median of Carling Avenue, past Lincoln Fields Shopping Centre, to connect with the O-Train Expansion Corridor (1-LRT). 

West Transitway Corridor (1-BRT)

This $230M corridor of Bus Rapid Transit corridor includes an extension of BRT from Hazeldean Road in Kanata near the Corel Centre easterly, north of Highway 417 to Eagleson Road and a section of BRT north of Highway 417 between Bayshore Shopping Centre and the existing Southwest Transitway at Woodroffe Avenue.  This 11.5 km corridor includes nine stations and one park and ride lot between Hazeldean and Eagleson Road and three stations between Bayshore and Woodroffe Avenue.

Southwest Corridor (2-BRT)

This $101M corridor extends from the Nepean Sports Plex at Hunt Club Road west of Woodroffe Avenue to the Fallowfield Road Park and Ride Lot, then southerly along the Smiths Falls Railway Subdivision to Greenbank Road, then southerly east of Greenbank Road to the Nepean South Town Centre (tying to the O-Train Expansion Corridor (1-LRT)).  The 5 km corridor includes five stations and a park and ride lot at the Town Centre.

Baseline Road Corridor (3-BRT)

This $46M Bus Rapid Transit corridor extends along the median of Baseline Road between Navaho Drive and Data Centre Road, then along Data Centre Road to Billings Bridge Transit Station.  Thirteen stops are proposed along this 6.5 km long corridor.

Hurdman Station to Blair Station Corridor (4-BRT)

This $119M section of Bus Rapid Transit Corridor extends from the Southeast Transitway at Lycée Claudel Station easterly through the hospital complex on Smyth Road, to Innes Road at Blair Road (connecting to both 1-LRT and 2-LRT corridors), then northely along Blair Road to the Blair Transit Station at Gloucester Centre.  Eleven stations are proposed along this 9 km BRT corridor.

East Transitway Corridor (5-BRT)

This $30M corridor extends to the east from the existing BRT station/ Park and Ride at Place d’Orleans Shopping Centre, using shoulder Bus Only Lanes on City Highway 174, to Trim Road and the Park and Ride Lot at that location.  This 6.6km corridor includes two stations and an expansion of the current Park and Ride lot at Trim Road.

Albert/Slater Corridor (6-BRT)

This $20M corridor extends along the existing Albert and Slater bus mall between Bronson and Elgin. The work includes improvements to bus operations, enforcement through design,  and improved access and amenities for transit customers.

 

Estimated RTES Ridership

NEED TEXT ABOUT RIDERSHIP – 1 PP.

 

 

Program Wide Tasks

In order to implement, monitor and control an infrastructure program of this size ($3.4 billion), a dedicated program management team needs to be established by the City.  In addition to the responsibility for the planning, design and development of the individual rapid transit projects in the City of Ottawa’s long range transit expansion plan (ORTEP), there are a large number of program wide tasks, such as specifications and standards for  vehicles, operations, and the system itself.  These are outlined later in this report.

 

 

Funding the Program

Estimated Program Capital Costs

Table 4.1 summarizes the total estimated ORTEP costs by project and includes required vehicles and maintenance facilities.  This program is a very large long-range undertaking requiring a $3.4 billion investment by the City and its funding partners.  PThe potential sources of funding are discussed in the following section.

ORTEP COST SUMMARY - TABLE  4.1TABLE 4.1

Corridor

Cost ($M 2003)

 

Item

Totals

1-LRT  – O-Train Expansion Priority Project

$600

 

1-LRT  – Future Extensions

$330

 

2-LRT  - East West Corridor

$976

 

3-LRT  - Carling Corridor

$254

 

 LRT Corridors Subtotal

 

$2,160

LRT Vehicles

$630

 

LRT Total

 

$2,790

 

 

 

1-BRT  - West Transitway

$230

 

2-BRT  - Southwest Transitway

$101

 

3-BRT  - Baseline Corridor

 $46

 

4-BRT  - Hurdman to Blair Corridor

$119

 

5-BRT  - East Transitway

 $30

 

6-BRT  - Albert/Slater Corridor

 $20

 

BRT Corridors Subtotal

 

$546

BRT Vehicles

 $53

 

BRT Total

 

$598

 

 

 

ORTEP Total Estimated Cost

 

$3,388

 

·         Costs include property, engineering, project management and contingency

 

 

Exhibit 4.2 below provides a graphical illustration of the required total annual cash flow and the accumulated total over the next 18 years if the program is to proceed as scheduled.

 

 

 

 

Available Federal and Provincial Funding programs

There are two funding sources that are the primary vehicles for funding transit infrastructure in Ontario: the Federal Government’s Canada Strategic Infrastructure Fund (CSIF), and the Ontario Government’s Transit Investment Partnership (TIP).

Administered by Infrastructure Canada, the CSIF was established specifically to deal with strategic, large-scale infrastructure projects.  Established in 2001/2002 with an initial commitment of $2 billion, CSIF was doubled in Budget 2003 to a total $4 billion over the next ten years.  ORTEP is an ideal candidate for CSIF under the “Local Transportation Infrastructure” priority of the CSIF fund. 

In September 2001, the Province of Ontario (through MTO and SuperBuild) announced a new ten-year $3.25 billion program of investment in transit in Ontario, of which $250 million was dedicated for urban centres outside the Golden Horseshoe.  The $250 million earmarked for the rest of the province over the period from 2001 to 2010 is called the Transit Investment Partnership (TIP).  As the largest urban area in Ontario outside of the Golden Horseshoe, and the only city with higher-order transit, the City of Ottawa should be eligible for a significant portion of the $250 million Transit Investment Partnership (TIP) funding.  It is not unreasonable to anticipate receiving close to 80% (based on ridership) of the committed $250 million over the next ten years, with the potential for a higher portion.

Other Funding Sources

Development Charges – Capital investment in public transportation infrastructure is commonly supported by levying infrastructure support charges through development charges (either city-wide or area-specific) and/or other considerations sought from developers in exchange for increased density, especially near transit stations. 

Land Value Uplift - Public investment in major transportation infrastructure can result in windfall increases in property value for the owners of private property adjacent to and served by the new facility.  This increase, or uplift, in property value is an untapped potential source of funding for governments.  It is possible that some of this land value uplift (or windfall) can be shared with the public and mechanisms will be investigated to determine whether additional funds can be acquired for some ORTEP projects.

Local Payroll, Sales, Excise, Parking, and Congestion Taxes - While, for the most part, the levying of these taxes is not available to municipal governments in Ontario, Canadian Provinces do have the ability to allow municipalities to impose these taxes.  Some support has been expressed at the Federal level for the Government of Canada to vacate tax room on the fuel excise tax, to be filled by municipalities.

Public or Private Financing

City of Ottawa Financing - There are several conventional forms of debt finance available to municipalities, as well as unconventional ones under new initiatives being undertaken by the Province.  The Ontario Municipal Economic Infrastructure Financing Authority (OMEIFA) was established in 2002 to provide subsidized financing for municipalities through the use of Opportunity Bonds.  Public transportation is an eligible category of public infrastructure to receive OMEIFA financing.

Private Financing - While private finance tends to attract a higher cost of capital than does public finance, this higher cost of capital is typically largely accounted for by increased risk that has been passed to the private sector that would have otherwise been borne by the public sector.  It is likely that, given that fare revenues are unlikely to cover operating costs and entail some revenue risk, the City will need to provide a payment structure to support this type of financing structure.  Further, it is possible that regardless of the specific structure of a public-private partnership, the transaction is likely to be regarded as a capital lease and may therefore be reported as a capital lease on its balance sheet - “off-book” accounting treatment is therefore not a certain outcome. 

Impacts of Government Funding Support Levels

Impacts of Government Funding Support Levels

The following Exhibits 4.1 and 4.2 show the annual cash flow requirements for each project and for the entire $3.4 billion ORTEP program over the estimated implementation program period.  Exhibit 4.1 provides a graphical illustration of the cash flow.

The impacts of differing levels of senior government support on the project’s annual cash flow requirements were examined.  Two senior-level government subsidy scenarios were considered. One scenario has each level of government sharing 1/3 of the programme and providing a 67% total subsidy to the City.  The other scenario considered only a total 33.3% subsidy provided by senior levels of government.

If the City of Ottawa had to finance the entire program it would require an average of $132 million annually over the life of the program, including $83 million per year over 8 years for the priority LRT O-Train expansion project.  Projects of this magnitude cannot be (and never have been) funded by the municipal taxpayer in Ottawa or any other city in North America. This is not reasonably achievable out of the municipal tax base.

On a cost shared basis of 1/3 each or 67% total subsidy to the City, it will still cost the City of Ottawa an average of $63 million per year over the life of the program including $31 million per year over 88 years for the priority LRT O-Train expansion project.

Recommended Financing Approach For The Priority LRT Project

There is no clear advantage to having the private sector provide financing for an LRT project and the terms required can complicate the terms of the subsidy funding agreement, especially when the project may be subsidized by 3 levels of government.  As such it is recommended that the City of Ottawa self finance its share of the first priority project.  It is also clear that a minimum 2/3 funding must be provided by senior levels of government if the projects are to proceed in a timely fashion.

 

Delivery approaches

(insert cash flow table spread over two rows  - may need to cut and paste to fit table in two pieces on this 8.5 x 11 page - File=ORTEP cash flow formatted Jun 1.xls)

 


Delivery approaches

Traditional

Traditional delivery of large-scale public transit infrastructure projects has followed the process of plan, design, bid and construct a number of contracts (50-100 or more) to make up a completed transit facility.  The owner (or agent for the owner) completes the design for each of the component civil or system contracts and awards them to a large number of individual contractors.  The owner takes responsibility for issuing the contracts in the proper sequence, for insuring that each component contract is coordinated with the others and for testing the completed system.  Operation and maintenance of the system is generally an owner responsibility.

This process gives the owner the maximum control over quality and scope for the completed project but also leaves the owner with the full risk for cost overruns and schedule delays.  Because the construction contracts cannot be initiated prior to the full completion of the tender design packages, the schedule for the project tends to be longer.

Public-Private Partnerships

There are several potential types of structures for public-private partnerships.  Once the range of acceptable options in a particular case is narrowed down at a strategic level, further, much more specific, structuring options need to be considered.  A key distinguishing feature of each option is the degree of risk transfer to the private partner.  The strategic and more specific options that are chosen depend on the transportation, urban development, and financial objectives of the public partner and its private partners, and on a range of other considerations.  These options need to be carefully investigated and weighed as a project moves toward implementation.  Subject to the foregoing, either a Design-Build-Operate-Maintain (DBOM) or a Design-Build-Operate-Finance-Maintain (DBOFM) structure is likely to be appropriate.  These structures and others are described below.

Public- Private Contract Options

Three potential contract options for LRT rapid transit under public private partnerships are:

Design-Build Contracts (DB):  Under this structure, the private partner both designs and builds the rail and associated infrastructure for an LRT rapid transit system.  Design and construction are awarded to a single contractor, who is responsible for ensuring that both design and construction satisfy performance specifications and are provided at a fixed price within a specified deadline.  Because design/builders are bidding on the contract and trying to minimize costs, the drawback of this approach is the potential for short-cutting by the contractor on life-cycle, operating, and maintenance costs.

Design-Build-Operate-Maintain Contracts (DBOM):  Under this structure, the private partner designs, builds, operates, and maintains the LRT rapid transit system, but is not responsible for securing finance.  By integrating responsibility for operations and maintenance with responsibility for design and construction, this approach (and all approaches that do the same) helps optimize the life-cycle cost of transit system development and operation by internalizing the capital-operating trade-offs to a single party.  The project will usually get constructed to a higher standard because of the inherent operating and, more importantly, maintenance responsibilities.

Design-Build-Finance-Operate-Maintain Contracts (DBFOM):  Under this structure, the private partner designs, builds, finances, operates and maintains transit infrastructure.  The main difference in the DBFOM option is that the design builder also finances the line.  Added discipline may be imposed on the private partner through the introduction of creditors that seek to preserve their interest in the project by ensuring its successful operation.  However, in financing the project the private partner usually cannot borrow money at as favourable a rate as the City unless the City provides financial guarantees.

Contract Term

The appropriate term of a public-private partnership contract depends on a variety of factors, and whatever term is set, it is invariably qualified by the right of either party to terminate for cause, and the right of the public partner to terminate for convenience.  For the City of Ottawa, a contract term in the order of twenty-five to thirty years is likely to be appropriate as it reflects the expected useful life of the major assets, avoids unnecessarily high contingencies related to long-term uncertaintieuncertainty, and allows the City to finance the project with debt matching the term of the agreement.

 

Recommended Delivery Approach

For the Priority Project it is recommended that an experienced consortium be hired through a competitive process to Design-Build-Operate and Maintain the LRT line.  While a DBOM consortium will not necessarily complete the project at a lower cost than following the traditional design-bid-build process, it will most certainly result in the project being completed on a more accelerated schedule.  In addition, if the project is bid at a guaranteed maximum price with appropriate schedule penalties/rewards, it will reduce the risk of project  cost overruns and schedule delays.

 

 

ORTEP Work Program

In addition to the individual rapid transit projects within the ORTEP program there are a number of program wide tasks that need to be completed.  Due to the complexity of the project and the length of the project schedule, a series of standards need to be developed to provide performance guidelines, mitigate risk, and ensure safe operations.  These tasks areinclude:  (refer to the full Technical Report for more information).

§                  Program Procedures Manual

§                  Risk Assessment Plan

§                  LRT standards/operating procedures

§                  Updated BRT Standards

§                  LRT Vehicle Specifications

§                  System Specifications

§                  Property Acquisition Plan

§                  Yards and Maintenance Facilities

§                  Program Procurement Plan

 

ORTEP Schedules

Exhibits 6.1, starting on page 14 and continuing on page 15shows, shows the proposed schedule for all of the ORTEP project program components.  The associated cash flow tables and chart have been included in Section 4.  It is proposed that the City set up its ORTEP program management team, thenand then proceed with the implementation of the first priority north-south LRT and the required planning for most of the other projects.  Construction of other major projects would follow as financing allows.

Based on this schedule, the LRT Priority Project Stage 1 between LeBreton and Leitrim would be operational by Spring 2009.  The bulk of the expenditures for construction and vehicle purchase will be in 2007 and 2008. 

 

Following the priority project, there are a number of BRT projects which could be implemented and which would complete the BRT network and have the required planning approvals. The BRT projects are:

 

Other BRT projects that should be considered as the network is implemented are:

 


 

Exhibit 6.1 – Proposed Schedule, Full ORTEP Program



 

 


Priority project work plan

The Priority Project (1-LRT:  Rideau Centre to Limebank)

In February 2003, the recommendations of the Rapid Transit Expansion Study were approved by Council. The recommended network includes as a priority the expansion of the O-Train corridor to downtown and to the growth areas in the south. The downtown service would be at-grade on an east-west street (possibly on Queen Street or Sparks Street depending on the outcome of an environmental assessment study). The existing O-Train corridor would extend southwards to the Riverside South community and eventually across the Rideau River to the South Nepean area.

Extension of the LRT Service

Background

After 18 months in operation and an investment of $30 million, the O-Train has been judged a success.  Ridership has met expectations with more than 6000 riders per weekday and it operates on time, 99% of the time. The public feedback has been positive.  Based on the success of the Light Rail Pilot Project and the results of analysis of future travel demand, the RTES has recommended that as a priority the service be extended to the east into downtown and to the south to the new growth area of Riverside South, the Ottawa MacDonald Cartier International Airport and eventually across the Rideau River to the Barrhaven area.

Rationale for the Route

The O-Train service in the existing north - south railway corridor has been successful.  However, on its present alignment running between Greenboro and Bayview, it will never be able to realize its full potential unless the line is extended into the Central Business District (CBD) and into the new development areas of Riverside South and the Ottawa International Airport.

Based on a recent travel analysis for the South East sector of the City, the number of riders per day on the LRT system between the Rideau Centre and Limebank has been conservatively estimated to be in the order of 60,000 to 80,000 persons per day by 2021. The LRT system would also be an attractive option for travel within the Central Business District.  As a result the LRT is likely to attract more than 100,000 riders per day. 

 

There are a number of Light Rail corridors that have been identified (see Section 3).  With the north south corridor having proven its potential, it is expected that no other corridor would produce these ridership results within this time frame.

 

Rationale for the Technology / Vehicle

A ‘lighter’, more flexible LRT vehicle (compared to the current O-Train technology) will be needed to operate in the downtown setting of mixed-use and pedestrian-friendly environment. The extension of the service through LeBreton Flats and into the CBD will mean that the Light Rail vehicle will be running along and crossing existing roadways within the downtown area.  Consequently the vehicle must be able to negotiate tight turning radii typically found at many downtown intersecting roads.  In addition, to ensure that the platforms are the least intrusive within the downtown environment, low floor (at least 70%) vehicles would be required. The resulting platform height would be approximately 350 mm.

The electric vehicle will be particularly environmentally friendly, with little or no harmful emissions.  Overhead electrical wires will be supported by poles placed either on the sides of the road or in the centre between the tracks.

Use of existing DMU fleet

The three Talent DMUs, currently used for the O-Train, will no longer be required for the North – South LRT line once the service is expanded and extended. The question has been raised as to whether the existing DMUs could be used to provide a low-cost service on the East – West rail line in the short term.  The consulting team has examined the feasibility of this service in detail. However, due to the unsuitability of existing track and signalling and associated costs, and the difficulty of gaining Transport Canada approval to run the Talent service on active freight lines, extending the service using the Talent vehicles is not recommended.  The full ORTEP technical report contains more information regarding this feasibility study.

Proposed Priority Project Schedule

Exhibit 7.1 following shows a detailed schedule of the key elements of the Priority O-Train expansion LRT project. The project is scheduled to start operation in early 2009 and in order to achieve that fast track schedule there are a number of tasks that must be initiated. These tasks are briefly described in the following sub-sections.


 

Exhibit 7.1 – Proposed Schedule, Full ORTEP Program

INSERT PRIORITY SCHEDULE

 


Tasks

The proposed schedule shows the opening of the Priority Project between LeBreton and Leitrim stations by early 2009 with the extensions to the Rideau Centre and Limebank to follow immediately. In effect this means that there are approximately five and half years to get the first phase of the line in operation.  This is an ambitious but achievable schedule.

  However, it is highly unlikely that the conventional approach of planning, design, tender, award and construction will result in project completion in this time frame. The Sheppard Subway in Toronto, for instance, while on time and on budget, took approximately 12 years from EA to service start.  Consequently, a fast tracking approach is required for the Priority Project.  This means that a number of the major tasks will have to be carried out either at the same time or with considerable overlap.  While there are risks that have to be assumed in the process, the purpose of a well-defined implementation plan is to understand and minimize these risks.

The following tasks will be required to implement the Priority project:

Environmental Assessment - Provincial legislation will require an individual Environmental Assessment be carried out for the complete project, and the study must also meet the requirements of the Canadian Environmental Assessment Act.  To avoid any duplication in the level of effort, a harmonized assessment should be undertaken.

Preliminary Design (Project Scope Definition) - As part of, or in parallel with, the EA study, Preliminary Design Studies will be carried out.  Typically, a minimum 30% design level by the City would be required to meet the risk requirements of the suggested PPP.  This task will establish project scope, Baseline Schedule and a Baseline budget.

DBOM Consortium Procurement – If a DBOM approach to procurement is pursued, it is extremely critical that the process for procuring one or more design/build/operate/ maintain contractors be carefully developed and contract requirements clearly assessed before a competitive procurement process.

Development of Various Standards and Plans - In conjunction with Environmental Assessment Studies and the subsequent Preliminary Design work, plans must be developed to assist in ensuring that the project proceeds smoothly, on time and within budget.  A number of the additional activities will have to be carried out in parallel with the EA and preliminary design activities, specifically:

 

§                  LRT Planning and Design Standards

§                  Vehicle and Systems Procurement Plan

§                  Maintenance Operations Specifications

§                  Communications and Public Consultation Plan

§                  Operational and Service Plan / Integration with Bus and Transitway Services

 

 

Property Acquisition - There are a number of properties to be acquired for the LRT priority project.  These include:

§                  CP Right of Way - the City is currently leasing the track system it operates from CP Rail. The agreement with CP contains a clause to purchase the leased line with or without the portion of the Walkley yard also currently being used for the O-Train.

§                  Maintenance and Storage Yards - Acquisition of the lands to accommodate the initial LRT yard is a priority.  The existing maintenance facility at Walkley may not be adequate for use with the new system. Other yard sites are being identified along the line and will be acquired in the event that Walkley is not appropriate.

§                  Riverside South - The required property south of Leitrim is in the hands of a number of developers:  A new right-of-way will be required from the developers.

§                  LeBreton Flats - Property requirements for the relocation of the Transitway have already been negotiated with the NCC, including protection for the co-location of the LRT line.

§                  LeBreton to Rideau Centre - While as much as possible, the chosen alignment will be within City rights-of-way, there may be some property requirements through the downtown area.

§                  Park and Ride Lots - Property will be required for park and ride lots at Lester and Leitrim stations.

§                  Airport Lands - A separate right-of-way will be set aside for the airport LRT connection through Airport lands.

 

Preferred Construction Staging Plan

The first priority LRT project from Rideau Centre to Limebank Station is estimated to cost $750 million ($2003). Three major stages have been identified. The first stage is the upgrading, double tracking, and extension of the existing O-Train corridor between LeBreton and Leitrim including Park and Ride lots at both Lester and Leitrim stations. The second stage will likely be the section from LeBreton to Rideau Centre.  The third stage (Leitrim to Limebank) would either be constructed at the same time as stage 2 or follow shortly thereafter.  The airport extension could also be included as a second stage but is presently included as part of the first stage. The proposed preferred staging plan is shown in the following Exhibit 7.2

 

 

 

 

 

 


 

Exhibit 7.2

Proposed Staging of priority LRT

 

 

(insert staging map)

 

 

 

Table 7.1 provides the costs of the preferred staged approach to the construction and  implementation of LRT in this priority corridor.

 

 

Staging Plan Table 7.1

 

Stage

 

Section

Estimate

2003 $M

1

LeBreton flats to Leitrim, including the spurs to OMCIA and Maintenance Yard

$530

2A

LeBreton to Rideau Centre, including relocation of the Transitway and Booth Street

$120

2B

Leitrim to Limebank

$100

 

TOTAL

$750

 

STAGE 1:  LEBRETON TO LEITRIM

Provincial and federal EAs will have to be completed prior to construction of LRT in this corridor.  The existing O-Train operation will continue in service until at least 2007 and continued as long as possible while early construction is in progress.  The relocated Transitway and grade-separation of Booth Street will be completed at the same time as the LRT construction through this area.  A crossing of the Rideau River and a tunnel under the canal will have to be completed as soon as possible. Existing bridges at Heron Road will have to be replaced, the existing track will be twinned, and a relocated freight track between the Walkley yards and the NRC testing labs will need to be built as soon as possible.  Park-and-Ride lots will be constructed at Leitrim and Lester, along with new and upgraded stations at South Keys, Greenboro, Walkley, Heron, Carleton University, Carling, Gladstone and Bayview.  Storage and maintenance yards will also have to be built in this first stage.  Finally, a connection into the airport is presently planned as part of the first phase construction, but could be deferred to stage 2 if required.

STAGE 2A:  LEBRETON TO RIDEAU CENTRE

The specific alignment of the LRT within the downtown will only be selected after a number of options are investigated as part of an Environmental Assessment study.  This section will inherently be more complicated (and may take more time) than the LeBreton south section because of a number of alignment constraints within the CBD.  The first priority for construction will be the relocation of all underground services along the selected route as well as around the war memorial, Rideau Street and George Street. Track should be laid as the utility relocation is completed, and retaining wall and structural elements of the LRT from the LeBreton Flats to Sparks street constructed.

STAGE 2B:  LEITRIM TO RIVERSIDE SOUTH

This section could be constructed at the same time as Stage 2A or after it. This routing is currently through an open space area planned for development. The LRT alignment and stations will be integrated with development and probably constructed at the same time.  The only major structure will be a bridge over Mosquito Creek.

 

Minimum Feasible Start-up StageProject

Based on the real possibility that initial funding allocations from senior levels of government may be less than required to complete the recommended first stage of the Priority Project a “minimum feasible start-up project” has been developed to address this possible scenario. In order to come up with a minimum cost start-up project, a preliminary review was conducted on the proposed LRT to determine what options were possible and where costs could be reduced, while still ending up with a feasible stand alone project.

The initial conditions for the review were that the project had to go north to at least LeBreton Station, south to at least a park-and-ride station, as well as being subsequently extendable into the downtown and further south as an LRT line. Using the existing 3 DMUs plus additional DMUs was briefly considered. This option was set aside because it would not be as environmentally friendly as electric propulsion, would result in similar civil costs to that of the proposed electric LRT, would result in more throw away costs for the eventual electrification and could not be extended into the downtown.

A minimum feasible interim LRT project has been developed. This interim stage would run from LeBreton Station south to Lester station on single track with 4 sections of passing track. An extension to the airport would await a later stage. Service would be run at approximately 10 minute intervals with fewer (8 rather than 25) initial LRT vehicles required. In addition to vehicles, initial savings would include no new tunnel at Dows Lake, no new structure over the Rideau River, less track, signal and initial maintenance and storage requirements. 

After a preliminary review of this option, it is estimated that the minimum feasible start up priority LRT project would cost approximately $295 million (in 2003 dollars). It is doubtful that any further substantial savings can be made without seriously affecting the viability and feasibility of the minimum start up LRT project. This start up project would require approximately $100 million in subsidy from each level of government. This minimum feasible start up project has to be developed in more detail and attention should be placed on minimizing throw away cost, minimizing service disruptions when the service and line is expanded and minimizing additional operating costs.

While this start up project is not as desirable as the LRT staging proposed in the main report, it is a feasible start up to the proposed priority LRT. The service frequency and the start up ridership potential will be less than the proposed project but it will still be a considerable improvement on the existing O-Train service. It will be extended to LeBreton Transitway Station with connections to the City of Gatineau as well as to Ottawa downtown, and it will terminate in the south at a major park-and-ride lot. The major advantage is that it will cost less as a start up project.

However, with this interim staging there will be some future throw away costs and some disruptions to service when the line is twinned and expanded in the future. This interim staging will also result in a further time extension in the achievement of the goals of the rapid transit expansion plan. These issues will all have to be considered in continuing negotiations for senior government subsidy for the priority LRT line.Based on the real possibility that initial funding allocations from senior levels of government may be less than required to complete the recommended first stage of the Priority Project, as described in the previous section, a “minimum feasible start-up project” has been developed to address this possible scenario.

Using the existing DMUs (diesel multiple units) plus new DMUs was briefly considered as a minimal service option. This option was set aside for the reasons given above.

A reduced version of the LRT project would run from LeBreton Station to Lester Station, which includes a large park-and-ride lot. The LRT extension to the airport would be postponed to a later stage. Because of the reduced service frequency, the City will be able to run the service on a single track with the addition of four passing tracks.  After a preliminary review of the project, it is estimated that the minimum feasible start up priority LRT project would cost approximately $295 million (in 2003 dollars).  It is doubtful that any further substantial savings can be made without seriously affecting the viability and feasibility of the minimum start up LRT project. This start up project would require approximately $100 million in subsidy from each level of government.

While this start up project is not as desirable as the LRT staging proposed in the previous section, it is a feasible start up to the proposed priority LRT.  However, with this interim staging there will be some future throw away costs and some disruptions to service when the line is twinned and expanded in the future, and will result in a further time extension in the achievement of the goals of the rapid transit expansion plan.

 

Program staffing resources

Introduction

 

ORTEP has a preliminary cost, in 2003 dollars, of $3.4 billion. The Priority Project LRT is in the range of $750 million, with initial stage operation by 2009.  This program will be the largest financial undertaking in the history of the City of Ottawa, greatly surpassing the $450 million Transitway Program of the 1980/90’s  As such, ORTEP will be an extremely high profile and complex undertaking involving communities across the City, all levels of government and experts from all disciplines. The Program is not a single project but is a number of projects with priority sections, taking approximately 20 years to complete the implementation.

 

All this makes it imperative that the Program is managed carefully and competently. City Council and all funding partners must have confidence in the management of the Program.  Expenditures must be transparent, justifiable and accountable.

 

Implementation

As discussed and recommended in Section 5.3, implementation of the Priority LRT Project should proceed under a “Design/Build/Operate/Maintain” model. This model would see the City bringing a project up to the detailed functional design level where the scope of the project is clearly defined. At this stage, a formal proposal process would procure a private sector consortium that would be responsible for detail design, supply, construction and maintenance of the infrastructure and vehicles.  Other ORTEP projects could also proceed under a Design/Build model, or could be implemented in a more traditional way whereby the City, or its consultants, would design the infrastructure and tender for its construction. 

 

Defining the Scope of Work

Prior to proceeding with a design/build/operate/maintain project, the City must clearly define the scope of work to be tendered. For the City to minimize their risk and have some control and assurance that the final project will be to their satisfaction, it is essential that the City complete the preliminary design of the priority LRT project to at least the 30% design level.  The 30% design level is generally considered to be the level of design necessary for the owner to minimize risk and exercise control of the final product while still leaving the design/build/operate/maintain consortia enough flexibility to exercise private sector innovations and efficiencies and schedule improvements.  In order to plan, manage and control a program of this size it is essential that the City institute a strong and experienced program and project management team.

 

Program Management

The Program Management Structure should be set up as a dedicated stand alone core team specific to this program while at the same time calling on all of the required support resources from existing City departments. In order to minimize the requirement for hiring new City staff and to provide specialized expertise, outside resources will be required to support the City staff in areas of program management, LRT technology, transit design/build, and procurement of large private sector consortia unique to this Program.

It will not be possible for the project to proceed on a fast track basis with only the existing City resources.  The project will also proceed on a slower basis if funding is inadequate or slow in being provided.  Based on experience else where, the City will not receive final funding commitments until the environmental assessment is complete. If the other preparatory elements such as preliminary design and setting up the design/build/operate/maintain procurement process are not completed concurrently with the EA process, then the City will not be able to fast track the Priority Project implementation when the funds are approved.  These tasks must therefore occur concurrently and as  expeditiously as possible.

 


Summary Conclusions

 

 

Summary conclusions

Ottawa has endorsed the Rapid Transit Expansion Program (ORTEP) as a key approach to meeting the goals of the new City of Ottawa Official Plan.  This Program calls for the implementation of approximately 101 km of rail (LRT) and 61 km of busway (BRT)  forming a comprehensive network with the existing O-Train service and the Transitway. 

 

The first priority - O-Train expansion - is a critical building block in development of this plan and has been given the highest priority by Ottawa City Council.  In order to implement the priority project on a fast tracked basis and to commence with the other elements of the plan, it is recommended that the City of Ottawa:

 

§                  Continue to endorse the $750 million O-Train Expansion LRT as its first priority transit project;

§                  Continue negotiations with both the Provincial and Federal governments to secure at least a 1/3 subsidy from each level of government for the priority LRT project;

§                  Further define the potential minimum first stage start up project for consideration in funding discussions with the senior levels of government.

§                  Proceed immediately with the required Environmental Assessment studies for the priority LRT project;

§                  Complete negotiations for the purchase of the CPR railway corridor for the north-south priority line and commence railway abandonment procedures;

§                  Identify and acquire the most appropriate maintenance and storage yard site along the priority LRT line;

§                  Construct the priority LRT project, in stages if necessary.

 

 

If the City chooses to expedite this project and pass some of the schedule and budget risk on to the private sector, Ottawa should pursue a single competitive contract for the design, construction, operation and maintenance of the priority LRT project. In this regard it is recommended that the City:

§                  Complete the preliminary design of the priority LRT to a 30% level;

§                  Based on this design, issue a single competitive DBOM contract to a private sector contractor for development and operation of the project, including the supply of LRT vehicles.

§                   

 

The entire rapid transit expansion program includes a number of LRT and BRT projects.,  The plan is highly dependant on shared funding from both Federal and Provincial levels of government and from the City itself.  To be prudent, it is recommended that the City:

§                  Carry out required planning studies on all other transit corridors;

§                  Proceed with design and construction of some of the critical BRT links, including the Cumberland Transitway, as a precursor to the East-west LRT;

§                  Proceed with other LRT projects/extensions as funds become available.

 

 

In order to manage a program and projects of this size and complexity and to negotiate for appropriate funding, it is important that a core team be assigned to manage the program. In that regard it is recommended that the City:

§                   assignAssign appropriate staff representatives to an ORTEP management team, consisting of both City staff and outside assistance to manage both the priority project, and the overall program.

 

 


Document 5

 

 

Actions Arising from Transportation & Transit Committee’s Motions (19 Feb 03)

 

 

The results of the Rapid Transit Expansion Study (RTES) were presented to Transportation and Transit Committee for approval on 19 February 2003 with the following recommendations:

 

1.      That the recommended Rapid Transit Network form the basis for the transit component of the Transportation Master Plan;

2.      That the Rapid Transit Priority Plan be approved, pending clarification of funding sources;

3.      That staff be directed to develop an Implementation Strategy that would include timelines, funding and partnership options, and financial implications.

 

The Committee approved recommendations 1 and 3 and amended recommendation 2 to read “That the Rapid Transit Priority Plan form part of the City’s Long Range Financial Plan, pending clarification of funding sources.”

 

The Committee also approved the following additional recommendations (which were subsequently approved by Council on 26 February 2003) and these have been addressed as noted in italics following each recommendation:

 

·        “That the Rapid Transit Expansion Study, as part of the implementation strategy, cost out and incorporate an interim bus rapid transit option for the section of the Cumberland Transitway which has already undergone an Environmental Assessment, in order to serve the proposed intensified development in the East Urban Community.”

 

This has been included as an interim BRT – as a precursor to the full East-West LRT line.

 

·        “That the City of Ottawa convey to the Ministry of Transportation Ontario Queensway Widening Study, its position that current transit lanes on the Queensway be protected in developing design alternatives.”

 

This request has been forwarded to the Minister Of Transportation from the City Clerk in a letter dated 7 March 2003.

 

·        “Whereas the City of Ottawa has developed considerable expertise in maintaining and operating the Bombardier Talent trains and they have given a reliable service; and whereas the Talent trains may be used to service Cumberland and Orleans in the east and Kanata North in the west for a number of years prior to the first choice electric light rail option being available, be it resolved that staff look at the possibility of retaining the Talent trains for this or other extended non-electric service as precursor to the electric light rail service.”

 

The report discusses the feasibility of using the existing diesel Talent trains in the East-West Corridor as an interim measure but concludes that it would be costly and of negligible benefit.  Using the existing trains on a line between Kanata and Orleans would only provide service every 90 minutes or so.  The line is currently in active use by freight trains and it is unlikely that Transport Canada would approve joint use of the track, thus construction of new tracks for transit operation would be necessary.  There area also a number of grade-separations to address along this corridor.  However, there is still some time yet before the diesel Talent trains are no longer required on the priority north-south corridor.  Therefore the possible use of these trains in other corridors can continue to be investigated over time and as conditions change.

 

·        “That the short spur to the Airport be included as part of the South Keys – Riverside South element of the plan and that its priority be adjusted accordingly.”

 

An Ottawa Airport spur and station has been included in the priority O-Train Expansion LRT line.

 

·        “That given the concerns of the Riverview Park Community Association and area residents, that staff review corridor options other than the Browning Avenue corridor.”

 

This will be done and it is more appropriately addressed as part of the environmental assessment study for this corridor.

 

·        “Whereas the Federal Budget allocated $3 billion in infrastructure support over the next ten years which included $1 billion for municipal infrastructure, and whereas the Federal Budget allocated $2 billion over five years to help implement the Climate Change Plan for Canada through such measures as sustainable transportation, and whereas the Provincial Government is investigating new ways of financing infrastructure that better reflect the life span of the asset involved, and whereas the Rapid Transit Expansion Study is our plan for the future of the rapid transit network in Ottawa, and whereas the plan recommends a priority plan for implementation of the Rapid Transit Expansion Study plan, and whereas the top priorities for implementation are extending the O-Train from South Keys to the Rideau Centre and from South Keys to Riverside South, therefore be it resolved that Transportation Committee recommend that Council approve the above-mentioned priorities as City Council’s top priority for any Federal or Provincial Infrastructure type funding.  Further be it resolved that staff consider the above-mentioned priorities as candidates for any new financing arrangements proposed by the Province of Ontario, and that Council’s number one transportation priority, the Rapid Transit Network (in accordance with the Rapid Transit Priority Plan) be communicated by the Mayor to the Prime Minister and the Minister of Finance, the Premier of Ontario and to all area MPs and MPPs and that their support of our priorities be solicited.”

 

Application has been made for funding of the priority O-Train Expansion LRT Line and negotiations with the appropriate officials at both the Federal and Provincial level is ongoing and will continue.

 

·        “Whereas the southwest corridor to Centretown is under tremendous stress, be it resolved that Riverside South to Centretown be fast-tracked and if approvals, financing and equipment permit, to bring it into service earlier than 2008.”

 

Schedules for the priority project have been reviewed in detail and advancing the schedule to earlier than 2008 would not be possible, even if full funding were in place.  Availability of funding is a critical component of the implementation schedule.