Report
to/Rapport au:
Transportation
and Transit Committee/
Comite des transports et des services de
transport en commun
and Council/et au Conseil
14 February 2002/le 14 février 2002
Submitted by/Soumis par: Rosemarie R.T. Leclair, General Manager/Directrice
généraleTransportation, Utilities and
Public Works/Transport, services et travaux publics
Contact/Personne ressource: Richard Hewitt,
Director of Infrastructure Services/Directeur des services et travaux publics
580-2424
ext. 21268, Richard.Hewitt@city.ottawa.on.ca
|
|
Ref N°: ACS2002-TUP-INF-0006 |
SUBJECT: |
The Realignment
of nixon drive for Approximately 300 metres at the abandoned cpr crossing
located 1.5 km south of main street in The Former Township of osgoode |
OBJET: |
MODIFICATION DU TRACÉ DE LA PROMENADE NIXON SUR
UNE DISTANCE D’ENVIRON 300 MÈTRES À LA HAUTEUR DE LA TRAVERSÉE ABANDONNÉE DU CP, SITUÉE À 1,5 KM AU SUD DE LA
RUE MAIN, DANS L’ANCIEN CANTON D’OSGOODE. |
REPORT RECOMMENDATIONS
That the Transportation and Transit Committee recommend Council approve:
1. the realignment of Nixon Drive for approximately 300 metres at the abandoned CPR Crossing as shown in Annex 3 (Drawing SM-3416-3);
2. that staff proceed with negotiations to acquire the property necessary to accommodate the proposed roadway realignment as shown in Annex 4 (Drawing SM-3416-4).
RECOMMANDATIONS
DU RAPPORT
Que
le Comité des transports et des services de transport en commun recommande au
Conseil
municipal d’approuver :
1. la modification du tracé de la
promenade Nixon sur une distance d’environ 300 mètres
à la hauteur de la traversée abandonnée
du CP, tel qu’il est indiqué dans l’annexe 3
(Plan SM‑3416‑3);
1. la
modification du tracé de la
promenade Nixon sur une distance d’environ 300 mètres à la hauteur de la
traversée abandonnée du CP, tel qu’il est indiqué dans l’annexe 3 (Plan SM‑3416‑3);
2. 2. que
le personnel entreprenne des négociations en vue de l’acquisition de la propriété
nécessaire à la modification du
tracé proposée, tel qu’il est indiqué dans l’annexe 4
Plan SM-3416-4).
The current alignment of the road at the former CPR crossing consists of two back-to-back curves. This alignment is considered to be sub-standard. In the summer of 2001, the City of Ottawa engaged a consultant for the engineering design of the road realignment project. The final design was completed in the fall and presented at a Public Open House, which was held on 06 November 2001, at the Osgoode Community Centre.
In advance of
the meeting, a request was made by a resident, to have a multi-way stop control
installed, at the intersection of Nelson Street and Nixon Drive, which is
located just north of the proposed realignment. This request was made in anticipation of the realignment project
proceeding. The information was
forwarded to the Traffic and Parking Operations Branch for their review and
recommendation.
ANALYSIS
Existing
Conditions
There are no sidewalks along either side of the road. An eight-hour pedestrian/vehicle survey was conducted previously. Throughout the duration of this survey there was no pedestrian traffic identified south of Main Street on Nixon Drive.
There
are currently no special provisions for bicycles on this roadway. Bicycles must share the road with
vehicles. During the above-noted survey
one cyclist was observed on Nixon Drive.
Transit
There
is no transit service in this area.
The traffic count also indicated that 568 vehicles used Nixon Dive during the eight-hour survey timeframe. Between 01 January 1998 and 01 January 2002, one accident was reported within the section of roadway where the curves are located.
DISCUSSION
Design
Proposal
The
design that was selected provides the most appropriate solution, andwhile deliversing an
improved level of service, in a cost-effective manner. In essence, the proposed design allows for
the roadway to be realigned, in order to eliminate the existing curvature. The proposed straightened section of roadway
would will by-pass
the two existing sub-standard curves, as shown in Annex 3.
To accommodate
the realigned section of roadway, property on both sides of Nixon Drive must be
purchased. The property acquisition
requirements are shown in Annex 4.
Design
Features
Removal
of the back-to-back curves along this section of roadway will provide
significant improvements in sight distances and roadway safety.
CONSULTATION
The proposed roadway realignment modifications fall under Schedule “A”
of the Class Environmental Assessment for Municipal Road Projects.
As required by the “ Municipal Act of Ontario”, a notice of the proposed
roadway modifications has been placed in Le Droit and the Ottawa Citizen
newspapers, for four consecutive weeks, starting on 22 February 2002.
This
report has been circulated to the area Ward Councillor
for comments.
In addition, notice of the Open
House, which was held on 06 November 2001 at the Osgoode Community Centre, was
mailed to local residents. Display
boards that showed the proposed realignment details, were on hand for the
public to view and comment on.
Many residents submitted written
comments, which were compiled and sent to the local Councillor, as well as to
the Traffic and Parking Operations Branch.
Many of the residents were concerned that the proposed removal of the
curves in the roadway would be an unnecessary measure and would lead to higher
vehicle speeds along Nixon Drive in this area.
A suggestion was made, by several local residents in attendance, that the installation of a multi-way stop control at Nixon Drive and Nelson Street would help to reduce the anticipated higher speeds that would be expected from the roadway realignment.
The City has recently completed a
traffic survey at the intersection and found that the warrants were not met for
the installation of a multi-way stop control. The warrant criteria for the installation of all-way stop
controls, is based on guidelines recommended in the Ontario Traffic Manual.
In summary,
based on current vehicle and pedestrian volumes, collision experience and
visibility conditions, the installation of an all-way stop control is not being
recommended at this intersection.
The total estimated cost for the
construction of the realignment, including engineering, construction
supervision and property acquisition, is $200,000 (this includes G.S.T.). The 2001 Capital Budget approved $100,000 in
funding for this project. Additional
funds in the amount of $100,000 has been will be requested
in the 2002 Capital Budget.
DISPOSITION
Subject to approval of the
recommendations contained in this report by Council, and barring any
significant delays in acquiring property, construction willcould begin
in the summer of 2002 and be completed by the fall.
ATTACHMENTS
Annex 1 - Key Plan
Annex 2 - Existing Geometry
Annex 3 - Proposed Geometry
Annex 4 - Required Property
ANNEX 1
ANNEX 2
ANNEX 3