M
E M O / N O T E D E S E R V I C E
|
|
To / Destinataire |
Chair and Members of Transit
Committee/
Président et membres du Comité des services de transport en commun
|
File/N° de
fichier: ACS2009-ICS-DCM-0007 |
From /
Expéditeur |
Nancy Schepers, Deputy City Manager/Directrice municipal adjointe,
Infrastructure Services and Community Sustainability/Services
d’infrastructure et Viabilité des collectivités
Marian Simulik, City Treasurer/ Trésorier
municipal
|
Contact
Person/ Personne ressource : Nancy Schepers, 613-580-2424, 12230 Nancy.schepers@ottawa.ca Marian Simulik, 613-580-2424, 14159 Marian.simulik@ottawa.ca |
Subject / Objet |
Costs and
Affordability - Downtown Ottawa Transit Tunnel (DOTT), Tunney's Pasture to
Blair Station/ Coûts et abordabilité – Tunnel de transport en commun
au centre-ville d’Ottawa (TTCCVO), du pré Tunney à la station Blair |
Date: October 22, 2009 |
This memo is to provide you with the functional design cost estimate for the DOTT project and an update to the Treasurer’s November 2008 memo on affordability to reflect this refined cost estimate.
Key Messages
Ø
The
affordability modelling shows that the City costs for Phase 1 - Increment 1 of
the TMP will not cause any tax increases.
Ø
The City can afford to pay its share of the costs of
Phase 1 of the TMP
Ø
The Fiscal Framework also identifies a revenue-to-cost
ratio target of 55% for transit services.
At the completion of Increment 1 of Phase 1 in 2019 this ratio can be
achieved with changes in local routing as identified in Transit Services 10 –
year tactical plan.
Ø
The
November 2008 Transportation Master Plan (TMP) cost estimates were high-level
estimates developed to support Council’s decision-making between
competing options related to Ottawa’s transit plan for the future.
Ø
TMP
Costs provided to Council in November 2008 did not include costs associated
with land acquisition or a project office.
Ø
Functional
Design estimates are more accurate estimates that allow the project to move
from planning to implementation. This cost estimate includes land
acquisition, DOTT project scope changes, design refinements and phasing
modifications.
Ø The affordability model includes an assumption that the two upper-tier levels of government will each contribute one-third of the total design and construction costs of the Transit portion of the TMP. Any increase in the subsidy, such as that committed to the Region of Waterloo, would provide the City with additional financial flexibility, as the City share of costs would decrease accordingly.
Cost Estimate
Evolution
The project is being developed in consultation
with a team of experts with extensive experience in large capital transportation
projects. In addition staff retained additional expertise to review the cost
estimates. Their credentials are listed in Appendix A of this memo.
The following section explains the cost evolution that normally occurs in the migration from planning to implementation of a capital project of this size:
TMP Estimates
Cost estimates provided as part of the Transportation Master Plan (TMP) in November 2008 were high-level estimates developed to support Council’s decision-making between competing options related to Ottawa’s transit plan for the future. The November 2008 cost estimates were based on industry standards and were understood to be subject to refinement by the functional and detailed design processes and design refinements for each capital project once the overall plan was approved. Council was advised at that time the estimates provided during the TMP decision-making process did not include costs associated with land acquisition or project office costs.
Functional Design Estimates
The cost estimates that are being provided to you as part of this memo were developed to support the Functional Design and Environmental Assessment (EA) of the Downtown Ottawa Transit Tunnel (DOTT). These more advanced cost estimates will provide important context for a Council decision on the Functional Design and will be available for public consultation as part of the October 26, 2009 Open House. The completion of the functional design provides for an increasingly accurate cost estimate for the project and includes elements that are not typically included in a strategic planning exercise such as the TMP.
Additional elements incorporated into the Functional Design cost estimates include land acquisition, DOTT project scope changes, design refinements and phasing modifications.
Description and Cost of Functional Design Elements
Land Acquisition
Now that an alignment has been confirmed we are able to advance functional design of stations and selection of a location for the maintenance facility. This advancement makes an estimate of land acquisition possible. The cost estimate to acquire the required land along the DOTT corridor is $140[1] million. The estimate includes:
· Subterranean rights
· Staging areas to facilitate construction
· Maintenance facility
· Station access
Project
Office Costs
A project office has been
established to continue to move the project forward from a planning phase to
implementation. Costs for staffing and
operation of this office are estimated to be $50
million over the life of the project. This cost represents 3.6% of total
project hard costs. The industry standard is that project office costs
typically fall in the 4% plus range. This estimate will be reviewed and
adjusted once Council selects a procurement process.
Initially, project office costs will be used to:
·
Support
funding negotiations with senior levels of government.
·
Address
identified project risks
·
Secure
land and property rights
·
Identify
development opportunities
·
Coordinate
planning works to support Official Plan (OP) land use goals, TMP goals, and
arts and culture.
·
Manage
senior government regulatory requirements
·
Investigate
procurement options including Infrastructure Ontario (IO) as a procurement
agent
·
Communication
and Outreach
·
Support
preliminary engineering and detailed design
·
Support
the development of output specifications
·
Secure
contract and construction management support
·
Coordinate
urban design and business development
DOTT Scope Change
On May 27, 2009 Council approved a scope change to the tunnel component of the DOTT project by adding approximately 750 metres (30 percent) to its length, thereby moving the Campus station underground. The cost of this scope change is estimated at $150 million.
Design Refinements
Design refinements are the result of examining
the approved project alignment, stations, staging areas and requirements, and
identifying the requirements and adjustments necessary for implementation. The total estimated cost of these design
refinements is $100 million. This figure includes:
· Enhanced accessibility at the underground stations
· Elevator renewal at existing stations
· Canopy coverings for all above-ground stations to improve customer comfort and reduce winter maintenance costs
· Station refinements to improve access and connectivity
Phasing Modifications
Phasing modifications are those costs related
to strategically advancing elements of subsequent increments of the TMP. Some of these modifications will result in
future cost savings over the duration of the TMP’s implementation. Total estimated cost for this modification
is $160 million and includes:
· Adding tail tracks at Tunney’s Pasture
· Making Tunney’s Pasture an interim terminal transfer station
· Building Bayview as a transfer station
·
Pre-building the maintenance facility to accommodate
the complete Phase 1 requirements
Peer Review
The MMM Group’s third party review identified three key issues with the potential to increase the DOTT Functional Design cost estimate. MMM also identified areas where the Delcan estimate was higher than industry standards, which indicates a potential for an adjustment downward. Also included in their review was an acknowledgment that their approach was a top down (high level) review and not a more detailed bottom up analysis, as used by Delcan.
Staff reviewed both the Delcan functional
design estimate and the observations made by MMM Group and are confident that
Delcan’s estimates are appropriate considering the advanced nature of the
functional design. Staff did, however,
acknowledge MMM’s assessment and agree that it is reasonable to add additional
contingency to the project cost estimate given where we are currently.
Therefore, staff has added a Project Director’s
contingency of $100 million to the overall project cost (see Figure 1).
DOTT
Functional Design Cost Estimate Break Down
Figure 1
Figure 1 summarizes
the progression outlined above.
Figure
2
Figure 2 presents the overall project costs
by cost element
Total project elements and cost estimates are as follows:
Project Element |
Refined Cost
Estimate |
Transit Tunnel and Underground Stations |
$735M |
Transitway to LRT Conversion Tunney’s to Blair |
$540M |
Maintenance Facility and vehicles |
$515M |
Property, public art, insurance |
$160M |
Project Office |
$50M |
TOTAL |
$2B |
Project Directors Contingency |
$100M |
TOTAL |
$2.1B |
Subject to Council approval of the Functional Design in early 2010, the DOTT project will continue moving towards implementation by finalizing the EA process, securing property rights, developing output specifications and completing preliminary engineering and detailed design. These project activities are outlined in more detail in the Council approved Transit Critical Path (an updated version was sent as a memo on October 13, 2009). Project cost estimates will be subject to further refinement as we advance to detailed design.
Though the costing element of this memo speaks to the functional design cost estimate of the DOTT project, the affordability piece, in order to accurately reflect the future pressures, will encapsulate all of Increment 1 in the modeling up to 2019, and speak to the two other elements in the modeling post 2019.
In order to determine whether the refined costs of Phase 1 - Increment 1 of the Transit portion of the TMP affect the overall affordability, the Finance Department developed a high-level funding model, which includes all Transit capital needs over a 20-year time frame. The model also includes the impacts that Increment 1 implementation will have on the operating budget during the construction period, as identified in the 10-year transit tactical plan. As with any forecast, the further it extends into the future the less reliable it becomes, but in order to determine whether future increments of the Transit portion of the TMP are still affordable, the model was extended to 20 years so that it could include increments 2 and 3.
Costs Included in the Model
In addition to the Transit costs identified in the TMP, the model also includes all of the other Transit capital works that are required over the time period. These include the yearly lifecycle renewal program, as well as the strategic capital initiatives planned for transit and any residual growth that was not part of the TMP. The full costs identified for Increment 1 of Phase 1 of the TMP are within the first ten years, and the costs for Increments 2 and 3, as identified in the TMP in late 2008, have been included in the last ten years of the model. The costs for Increments 2 and 3 are very high-level estimates and are subject to the same caveats as applied to the initial high-level estimates for Increment 1.
All capital costs identified have been inflated at the rate of 2.5% per year as they were developed using 2009 dollars.
The ten-year
tactical plan points out that, during the construction period, Transit Services
can expect to experience increased operating costs and decreased revenues. To smooth the impact this will have on
taxation, the model includes one-time contributions that will be made from the
capital reserves to the operating budget during those years. The model does not include the operating
savings that should be realized starting in 2019 as identified in the tactical
plan.
The total costs that need to be financed in the model are summarized as follows:
Costs Included Costs IncludedCosts
Included
|
Forecasted
Expenses from 2010 to 2019 ($M) |
Forecasted
Expenses from 2010 to 2029 ($M) |
Transit portion of
TMP (incl. DOTT) |
3,109 |
4,953 |
Lifecycle Renewal |
559 |
1,334 |
Residual Growth |
62 |
145 |
Strategic
Initiatives |
24 |
52 |
Total Capital |
3,754 |
6,484 |
|
|
|
Operating Impacts
during Construction |
149 |
149 |
TOTAL FUNDS
REQUIRED |
3,903 |
6,633 |
Sources of Funding
The model includes assumptions around the funding sources
the City has available for the Transit capital program. These sources and the assumptions around
them are as follows:
The funding plan has
been developed using the sources of revenue and the costs identified
above. The model includes an assumption
that the two upper-tier levels of government will each contribute one-third of
the total design and construction costs of the Transit portion of the TMP. Any increase in the subsidy, such as that
committed to the Region of Waterloo, would provide the City with additional
financial flexibility, as the City share of costs would decrease accordingly.
The Sources of Funding chart identifies the amount of cash that is expected to be received in the ten- and twenty-year time periods. In funding the expenses as much cash as possible was used, but for timing reasons, in some cases debt needed to be applied. The difference between the amounts identified in the sources of funding chart and the amount of cash applied to fund expenses in the model is being used to either service the debt or remain within the reserve balance. For example, by 2019 $723 M of tax contributions towards transit capital will have been received, $709 M will be used to fund capital, and of the $14 M difference $5 M will have been used for debt financing and the $9M balance will be in the reserve.
It should be noted that the funding model prepared for this exercise will not align precisely with the 10-year capital plan identified as part of the 2010 budget. The model assumes inflation on future capital costs, which have not been incorporated into the 10-year capital plan as that plan is updated each year as part of the budget exercise and can therefore be adjusted for actual inflation.
The fiscal framework has two funding principles that must be met with respect to the use of debt. These principles are:
The only tax-supported debt included in the model is the $38 million identified above as Transit - Debt. The funds within each category of revenue are sufficient to both contribute the cash identified and to service the debt, therefore the debt servicing for the $38 million in debt will not result in a tax increase, and thus the plan identified is in compliance with the fiscal framework.
The Province also establishes a debt limit for the City and the 2009 limit was set at yearly debt servicing of $341 million. The province has indicated that if the City were to borrow for a 20-year term at a rate of 7% this would allow an additional $3.6 billion in borrowing. The total debt authorized under the 20-year plan of $1.053 billion is well below that threshold.
The Fiscal Framework also identifies a revenue-to-cost ratio target of 55% for transit services and at the completion of Increment 1 of Phase 1 in 2019 this ratio is achieved.
The City has the financial capacity to afford its share of Phase 1 of the TMP including its share of the construction of the DOTT project. The sources of funding and the level of debt required for the City’s share is in accordance with the City’s Fiscal Framework.
Next Steps for Project Funding
Costs and affordability are important inputs to decisions on functionality. Council must be satisfied that the value proposition supports the level of investment.
Council, as part of the TMP deliberations in November 2008, directed staff to seek funding from our senior government partners in support of Phase 1 of the TMP.
As a result, staff has had ongoing discussions with counterparts federally and provincially throughout the TMP and now the DOTT project though to date formal endorsement has not been received.
Staff will be setting up follow-up meetings with the current estimates and funding models to explore approaches that provide the appropriate support levels.
If you have any questions please do not hesitate to contact Nancy at ext. 12230 or Marian at ext. 14159.
Original signed by
Nancy Schepers, Deputy City Manager
Marian Simulik, City Treasurer
Attach: Appendix A – List of Expert Consultants and Credentials.
Expert Consultants
Below is a list of the City’s expert
consultants who have been commissioned by the City to aid in the development
and review the functional design estimates:
Delcan Corporation
Delcan, commissioned to develop the functional design and cost estimates, is an industry leader in transportation and transit projects with over 50 years of experience in the field. Delcan’s past projects include work with the Sheppard Subway, Spadina Subway Extension, Transit City and the Union Station Rail Corridor Infrastructure Program in the City of Toronto, Evergreen Line in Vancouver, Peer Review of the Laval Extension in Montreal and the first phase of the C-Train in Calgary.
Halcrow Group
To ensure the highest level of accuracy on tunnel planning and cost estimation, Delcan partnered with Halcrow to focus on the tunneling requirements of the City’s TMP. Halcrow has over 75 years in the tunneling industry with experience tunneling in a variety of different environments. Past tunneling projects have included: the Edinburgh Airport rail link, the Tai Wai station subways in China, and the Cigar Lake Mine tunnel in Saskatchewan, among many others.
MMM Group
As part of the due diligence required to
provide as accurate a cost estimate as possible, staff requested that MMM Group
complete a third party review of the cost estimates provided by Delcan. MMM Group,
established in 1952, has extensive experience in consulting, engineering,
planning and project management in Canada and around the world.