Council Member Inquiry/Motion Form Demande de renseignements
d’un membre du Conseil /Formulaire de motion |
||
From/Exp.: Councillor Leadman |
Date: 17 September 2009 |
File/Dossier : |
To/Dest. : Steve Box, Manager,
Policy Coordination & Outreach, CMO
cc: G. Craig, Manager, DCMs Office, ICS C. Curry, Specialist, Strategic Projects, ICS J. Rupert, Specialist, ISCS
Legislative Agenda |
||
Subject/Objet : Inquiry No. TTC-18-09
– Leadman – Rapid Transit Plan –
Supplementary Funding Options Inquiry/Demande
de renseignements : From
the Transit Committee meeting of 16 September: 1. In
the memo sent by the Deputy City Manager on 16 September 2009 in regards to a
2nd phasing scenario, it noted that a “re-grouping” and an
“alternative” funding option were distributed to partner governments. While
the recognition of the rationale for these decisions is understood (if not
supported) the method in which these changes to the Council approved
implementation strategy contained in the Transportation Master Plan (TMP) is
troubling. Please
answer the following questions in regards to the official presentation of a
different TMP phasing option: a. Was
appropriate approval and sign off undertaken before the presentation of this
2nd phasing option? b. Was
the TMP modified to include a 2nd implementation scenario as
presented to partner levels of government? If not, how was the 2nd
implementation scenario presented when it clearly did not represent the
central guiding transportation planning document approved by Council that identified
a strict implementation scenario? c. Did
the presentation of this option go beyond Council direction which sought to
advise partner governments that the City is seeking funding for projects in
Phase 1 (e.g. to fund all phase 1) and to determine which projects may be
funded through the existing funding scenarios? |
d. Does
ascertaining which projects can be funded under the current funding
parameters (approved on November 28th, 2008) pre-authorize
changing of the TMP and associated funding applications to meet those funding
parameters without Council approval? e. Was
there any official indication that the 2nd phasing option was a
preferred implementation scenario for a partner government? f. Why
was this phasing scenario singled out as compared to numerous other phasing
scenarios which could have been presented as permutations of Phase 1 which
also could have been completed within ten years and grow ridership consistent
with the City’s TMP? g. If
City staff were aware that the approved TMP implementation scenario could not
be implemented when recognition of the “very likely limited funding
availability and pressure from other levels of government to begin and
complete project construction” was known, why was this not clearly conveyed
to Council during the approval of the TMP and why did City staff not draft
and support a TMP implementation and project selection that would have suited
those considerations? |
Response/Réponse |