M E M O   /   N O T E   D E   S E R V I C E

 

 


 

To / Destinataire

Chair and Members of Transit Committee/Président et membres du Comité des services de transport en commun

File/N° de fichier: 

 

ACS2009-ICS-TRA-0016

From / Expéditeur

Alain Mercier,

General Manager/Directeur général,

Transit Services/Services de transport en commun

Contact / Personne-ressource :

Alain Mercier, General Manager/ Directeur général, Transit Services/ Services de transport en commun

Alain.Mercier@ottawa.ca 

613-842-3636, 2271

Subject / Objet

Elevators at Transit Stations / Ascenseurs aux Stations de Transport en Commun

Date:    

November 5, 2009

Le 5 novembre 2009

 


 

BACKGROUND

 

At the special meeting of Transit Committee on 9 February 2009, direction was given to staff to “provide an update on the capital upgrading process of elevators at transit stations as well as a review of operating procedures”.  The following responds to that direction.

 

DISCUSSION

 

Update on the Capital Upgrading of Elevators at Transit Stations

 

An independent engineering firm conducted a comprehensive review of all elevators at OC Transpo stations in 2007.  The resulting report, produced in May 2007, outlined a number of recommendations including a prioritized list of elevators requiring rehabilitation.  Elevator rehabilitation is continuing as recommended in that report.

 

The following major work was completed recently.  Complete rehabilitation refers to the replacement of the control unit and car/cab, as well as bringing the elevators up to the current design code.

 

 

The mechanical reliability of these elevators has increased following completion of the rehabilitation work.  For example, the percent of days when all elevators at Tunney’s Pasture Station were operational increased from 83 per cent to 99 per cent following rehabilitation, with a similar increase at Westboro Station, from 69 per cent to 88 per cent.  The increase at Westboro Station would have been higher if not for water damage that occurred, which resulted in the need for additional downtime to restore the elevators to working condition.

 

Rehabilitation of the following elevators is already underway or scheduled to begin later this year or in early 2010:

 

 

In 2010, all elevators at Blair Station are slated for complete rehabilitation.  Funds in the amount of $500,000 for this work are included in the draft budget estimates for 2010.

 

All remaining transit station elevators are scheduled to undergo complete rehabilitation in future years (see table below).  The amount of funding required will be determined at a later date.

 

Transit Station

Year (tentative)

Queensway

2011

Campus

2011

Billings Bridge

2012

Greenboro

2013

South Keys

2013

Lycée Claudel

2014

Smyth

2014

 

Current Operating Procedures

 

Elevators must be temporarily removed from service in the case of vandalism, mechanical problems, or health and safety concerns, such as the presence of bodily substances.  The status of all elevators is checked by Transit Facility Maintenance staff every day and any deficiencies are reported immediately to the Transit Facility Maintenance Supervisor and Transit Law Enforcement. In the case of mechanical problems, Transit Law Enforcement places a call with the elevator maintenance contractor and sends a report by e-mail to Transit Facility Maintenance confirming the call-in.  In the case of janitorial services being required, Transit Facility Maintenance takes appropriate action.  Transit Facility Maintenance, Transit Operations, or Transit Law Enforcement staff places out of order signage on all elevator levels to inform customers about the elevator status.

 

If an elevator deficiency is reported by a customer, for example through use of an emergency call box, Integrated Control Centre staff liaise with and dispatch mobile staff (Transit Supervisor and/or Special Constable) to verify the elevator status on-site.  In the case of mechanical problems, once the elevator deficiency has been confirmed, Integrated Control Centre staff immediately report the failure to the elevator maintenance contractor and notify Transit Facility Maintenance by phone and by e-mail.  In the case of janitorial services being required, Transit Facility Maintenance takes appropriate action.  The responding Transit Supervisor or Special Constable places out of order signage on all elevator levels to inform customers about the elevator status.

 

Transit Supervisors manage customer impacts resulting from the elevator failure until the elevator is restored to normal service.  This includes:

 

 

Once the elevator is repaired and operational:

 

 

Review of Operating Procedures

 

As part of the recent integration of former Real Property Asset Management staff (now Transit Projects and Facilities Management staff) into Transit Services, new integrated operating procedures will be put into place by the end of March 2010.

 

For more information on these procedures and rehabilitation plans, please contact Stéphane Carbonneau, Manager, Transit Projects and Facilities Management.  Customers with inquiries about specific elevators should contact Customer Service (613-842-3600 or ocserve@octranspo.com) or Transit Information (613-741-4390).  To report a defective elevator, customers at transit stations should use the nearest emergency call box which provides a direct line to the Integrated Control Centre.

 

 

Original signed by

 

Alain Mercier

 

AM:ps