Report to/Rapport au :

 

Planning Committee

Comité de l'urbanisme

 

and Council / et au Conseil

 

May 9, 2012

9 mai 2012

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager, Directrice municipale adjointe, Planning and Infrastructure/Urbanisme et Infrastructure

 

 

Contact Person / Personne ressource:  Contact Person/Personne-ressource John L Moser - Management/Urbanisme et Gestion de la croissance

(613) 580-2424 x28869, John.Moser@ottawa.ca

 

 

Cumberland (19)

Ref N°: ACS2012-PAI-PGM-0129

 

 

SUBJECT:

 

area-specific development charge – connection of two existing portions of provence avenue

                                     

OBJET :

 

Redevances d’aménagement de secteurs distincts – Raccordement de deux parties actuelles de l’avenue Provence

 

 

REPORT RECOMMENDATIONS

That Planning Committee recommend that Council approve:

 

1.      Debt financing and expenditure of $1,100,000 in 2012 for the construction of the Provence Avenue connection as described in this report; and

 

2.      The Area-specific Development Charge Levy described in this report to repay the expenditure including all carrying costs.

 

 

RecommandationS du rapport

Que le Comité de l’urbanisme recommande au Conseil d’approuver :

 

1.        Un financement par emprunt et une dépense de 1 100 000 $ en 2012 pour la construction du raccordement de l’avenue Provence décrit dans le présent rapport; et

 

2.      Les redevances d’aménagement spécifiques décrites dans le présent rapport, afin d’assurer le remboursement de la dépense, y compris les coûts de portage.

 

 

Background

Provence Avenue was constructed in two sections west of Trim Road and south of Innes Road.  These two sections are not connected for a distance of approximately 450 metres.  A 26-metre corridor was reserved through vacant lands zoned Development Reserve, which are not expected to be developed for five to 10 years.  Local works are generally described as costs that are directly attributable to the subdivision itself.  The road is categorized as a collector and is considered the developer’s responsibility.

 

The City currently owns the lands where the connection will be constructed.  In addition, sanitary, storm and water services have been installed in the right-of-way to service new development to the south.  An Area-specific By-law amendment is proposed, in order to provide a viable mechanism for funding the road-related capital costs and to improve future local development circumstances.  Residents living in the community will benefit from direct access to the entire transportation network.  The City will borrow funds in order to finance the capital expenditure and fully recover the costs using an Area‑specific development charge within the defined geographic boundaries.

 

 

DISCUSSION

Development-related costs are paid for in part from development charges and by the benefiting landowners.  It is inevitable, over the life of the by-law, that some project timing requirements and cost estimates will be modified in order to respond to changing circumstances.  The installation of local servicing typically occurs at the time of development and would be the financial responsibility of the affected landowner(s).  In this case, the vacant land is not expected to be developed for some time and delaying construction only serves to hinder proper north-south traffic flows.  In addition, construction of the road will provide a direct cycling and pedestrian route from the Notting Hill community to the south to the French Catholic High School located at Provence Avenue and Innes Road.  It is of fundamental importance to the local community that the City puts in place an interim financing plan to pay for the installation of this portion of the servicing costs.

 

The proposed capital funding approach is to front-end the road connection costs.  This is the best method to ensure the local infrastructure is built in a timely fashion without eroding service levels and will also benefit the landowner by making the lands building permit ready.  Funds will be collected in the future from residential properties in the narrowly defined benefiting area to offset the costs of servicing this site (see Document 1).  Carrying costs associated with issuing debt to finance construction would form part of the levy requirement in order to recoup the entire upfront investment. 

Issuing debt will also allow the landowner to access the City’s high credit rating and benefit from the resulting lower borrowing costs.

 

The site specific development charges collected within the benefiting area will be used as the mechanism to fully recover the debenture payments.  The cost of providing local servicing for this site was estimated by staff to be $1,100,000 in 2012, which includes engineering and contingency components but excludes annual carrying costs estimated to be 4.069%.  Should the actual cost exceed the estimated amount, the additional portion shall be recovered from the benefiting area.

 

No benefit to existing development deduction has been made in this case for existing residents and no contributions from other sources are anticipated.  The 2012 forecasted cost is then calculated on a per capita basis, by dividing the total by the anticipated residential population of 1,950.  The estimated cost allocation, expressed as a charge per capita, is $835.23, which is then levied on a per unit basis for each residential dwelling type (i.e. singles, townhouses, apartments).  For example, in Table 1, the estimated allocation for single detached unit is $2,823 ($835.23 X 3.38 persons per unit occupancy rate specifically attributable to this area).

 

                       

 

Anticipated repayment of the long-term debt will be dependent upon the local development circumstances; however, marketability of the residential land should increase with this servicing arrangement.  The per dwelling unit charges will be indexed starting on August 1, 2013, in accordance with the annual development charge index rate, and will continue to be indexed until the infrastructure costs are fully funded.  Increases in ongoing operating costs arising as a result of the completion of the road segment are considered to be negligible.  A cash flow analysis has not been undertaken as the timing of the development of the vacant land is extremely difficult to predict.

 

 

RURAL IMPLICATIONS

There are no rural implications associated with this report.

 

 

CONSULTATION

Councillor Blais was contacted by a number of residents regarding the extension of Provence.  He also met the landowner to discuss the potential charge.  The landowner is to be contacted early in the process to discuss issues relating to road construction including evaluation of tile drainage and timing of construction for impact on the ongoing farm operation.

 

Comments by the Ward Councillor

Councillor Blais supports the report as this link will provide pedestrian, cycling, and vehicular connections for the surrounding community to better access schools, parks, pathways, amenities, and other services.

 

 

LEGAL IMPLICATIONS

While there are no direct legal implications associated with this report, it should be noted that any person or organization may appeal a development charge by-law to the Ontario Municipal Board. The appeal period for a development charge by-law is forty days after the day that the by-law is passed.

 

 

RISK MANAGEMENT IMPLICATIONS

There are no risk management implications association with the recommendation in this report.

 

 

FINANCIAL IMPLICATIONS

Should Council approve, expenditure authority in the amount of $1,100,000, funded through debt, will be established in a new Provence Avenue connection account. The Area-specific Development Charge Levy will repay the debt and all carrying costs.

 

Public Works will review and determine the ongoing operating costs, and include the additional funding requirements within the 2013 budget pressures.

 

 

ACCESSIBILITY IMPACTS

There are no accessibility implications associated with this report.

 

 

Environmental Implications

There are no environment implications associated with this report.

 

 

Technology Implications

There are no technology implications to this report.

 

 

TERm of council priorities

This extension will provide infrastructure to support mobility choices and improve operational performance.

 

 

SUPPORTING DOCUMENTATION

Benefiting Area        Document 1

 

 

DISPOSITION

Upon Council approval, staff will implement the recommendations contained in this report.

 

Benefiting Area                                                                                             DOCUMENT 1