Report to/Rapport au:
Planning Committee
Comité de l’urbanisme
and Council / et au Conseil
08 March 2012 / le 08 mars 2012
Submitted by/Soumis par:
Submitted
by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice
municipale adjointe, Planning and Infrastructure /
Urbanisme et Infrastructure
Contact Person/Personne-ressource: Arlene Grégoire, Director of Building Code
Services and Chief Building Official/Directrice des services du code du
bâtiment et chef du service du code de bâtiment, Planning and Growth
Management/Urbanisme et Gestion de la croissance (613) 580‑2424 x41425,
Arlene.Gregoire@ottawa.ca
SUBJECT: |
|
OBJET : |
RAPPORT ANNUEL DE 2011 PRESCRIT PAR LA LOI SUr LE CODE DU BÂTIMENT |
That the Planning Committee recommend that
Council approve the 2011 Annual Report pursuant to the Building Code Act.
Que le Comité de l’urbanisme recommande au
Conseil d’approuver le Rapport annuel de 2011 prescrit par la Loi sur le code du bâtiment.
Background
Pursuant
to Section 7 (4) of the Building Code Act,
the City is required to prepare a report every 12 months containing information
on building permit fees collected as well as the cost of servicing building
permits and enforcing the Building Code
Act and Building Code. Regulation
Division C Part 1 (1.9.1.1) further directs the municipality to distinguish between
direct and indirect costs as well as to include in the report the balance of
the reserve(s) at year end where such have been established. Accordingly, the 2011 Annual Report pursuant
to the Building Code Act is provided
for the approval of Planning Committee and Council as follows.
The Cost of Servicing Building
Permits and Enforcing the Building Code
Act and Building Code |
Actual
2011 $000 |
||
|
|
||
Building Permit Revenues |
23,996 |
||
|
|
|
|
Expenditures – |
Direct Costs |
(14,564) |
|
|
Indirect Costs |
(4,374) |
|
|
|
||
Transfer to Building Code Enforcement Reserves |
5,058 |
||
|
|
||
Building Code Enforcement Reserve Funds |
||||
|
|
|
|
|
|
Revenue Stabilization $000 |
Insurance $000 |
Capital Contribution $000 |
|
Closing Balances |
|
|
|
|
December 31, 2011 |
27,929 |
6,388 |
8,071 |
|
DISCUSSION
Costs
The Building Code Act directs municipalities to set building permits fees to fully recover the costs of servicing building permits and of enforcing the Act and Building Code. These include both direct and indirect costs. Direct costs include such costs as the compensation costs for the Building Officials, staff involved in the processing of applications, training and development costs, computers and peripherals and vehicles and mileage costs to name a few. The approach for allocating indirect costs within the City is closely aligned with the Ontario Municipal Benchmarking Initiative (OMBI) recommended methodology. Indirect costs consist of expenditures by other departments incurred in support of Building Code Services’ Code-related activities, including legal assistance and representation from Legal Services, budget preparation and tracking by the Finance Department and accommodation expenses based on the actual square footage space that is occupied by the branch.
Of total costs in 2011, 77 per cent were direct costs while 23 per cent were indirect. The direct and indirect costs, excluding the contribution to the reserve funds, were:
Direct Costs |
$14,563,877 |
Indirect Costs |
$ 4,373,766 |
|
|
2011 Totals |
$18,937,643 |
Permit Fees and Activity
The Building Code Act stipulates that revenues must not exceed the anticipated reasonable costs required to administer and enforce the Act and Code. Accordingly, the building permit fee rate and other fees for services are set to generate sufficient revenues to ensure full cost recovery and ensure the program is revenue neutral. The 2011 budget year anticipated a 2.5 per cent increase in costs and in view of the previous year’s surplus results, the branch did not raise the building permit fee rate and preserved the rates of $12.00 per $1000 construction and $8.40 per $1000 construction for farm buildings.
Since 2007, Ottawa has experienced consistently higher numbers of building permit applications than in previous years. In fact, the number of applications received yearly from 2007 through 2011 has been on average 15.7 per cent higher than in 2006. In 2011, 8827 building permit applications were submitted, roughly the same number as were submitted in 2010. This is not an indication of a trend of decreased construction activity or reduction in workloads because the number of permit applications received for more complex projects, residential and institutional, has increased in proportion to other types of projects. For example, a shift from constructing single dwelling units to multi-residential projects has resulted in a drop in total residential permits as one permit application for a multi-residential project will bundle many units per permit.
Ottawa is also experiencing a heightened demand for inspections. The number of inspections performed by Building Officials in 2011 (over 103,000) represents a 17-per-cent increase in the number of inspections completed five years ago in 2006. With the additional mandatory inspections related to the new energy conservation standards, it is anticipated that the number of inspections for similar construction activity will rise. New resources, including technologies, will be necessary to offset the increase in workloads, meet the legislated timeframes and mandate while providing excellent service to the permit holders.
Reserve Funds
The Building Code Act provides for the establishment of reserve
funds to ensure municipalities are able to fulfill their legislative mandate
despite downturns in construction activity and to cover capital investments
(growth vehicles, computers and software development, etc.) and special
costs/liabilities. In 2006, the branch
established the following reserve accounts to which any surplus building permit
revenues are allocated at year-end: 1) a revenue stabilization fund, which
safeguards the City’s ability to enforce the Building Code despite a
significant drops in construction activity and a declines in revenues; 2) a
capital contribution fund, which covers capital expenditures in support of the
activities related to servicing and enforcing building permits and enforcing
the Act and Code; and, 3) an
insurance fund, which covers costs associated with appeals and lawsuits.
As of December 31, 2011, the following fund balances were as follows.
Building Code
Enforcement Reserve Funds |
||||
|
||||
|
Revenue Stabilization |
Insurance |
Capital Contribution |
Total |
Opening Balance
January 1, 2011 |
25,229,358 |
6,388,089 |
6,445,573 |
38,063,020 |
2011 Transfers to Operating |
|
(733,713) |
|
(733,713) |
2011 Year-end Contributions |
2,700,000 |
733,713 |
1,625,000 |
5,058,713 |
Opening Balance
January 1, 2012 |
27,929,358 |
6,388,089 |
8,070,573 |
42,388,020 |
2011 Highlights
Cowan was provided a 10 year claims history
specific to the Building Code Services branch as well as an overview of its
policies and procedures. The outcome of
the risk review was positive with no significant concerns or recommendations
for action.
The percentage of applications determined within legislative timeframes for 2011 by building type is as follows:
On the 2012 Workplan
There are no rural implications associated with this report.
The City is required to report annually on the status of building permit revenues, costs of servicing building permits and enforcing the Building Code Act and Building Code and the reserve funds and to make the report available upon request. Accordingly, consultation was not undertaken.
Comments by the Ward Councillor(s)
Not applicable City-Wide report.
LEGAL IMPLICATIONS
There
are no legal implications associated with this report.
Financials associated with building permit fees/revenues, costs of servicing building permits, and deferred revenues are discussed within the report.
RISK MANAGEMENT
IMPLICATIONS
There are no risk management implications associated with this report.
ACCESSIBILITY IMPACT
There are no accessibility implications associated with this report.
Environmental Implications
There are no environment implications associated with this report.
Technology Implications
This report refers to the delivery of major business technology solutions including, mobile workforce solutions via Service Ottawa, scanning and electronic document storage, and the introduction of new software functionalities for implementation in 2013. Further discussion will be required in order to determine the level of impact this will have on IT resources as well as assessing associated costs. A detailed business case may need to be evaluated through the City of Ottawa’s Portfolio Value Management process for IT investments, in advance of any planned implementation. ITS cannot commit to the potential work identified in this report at this time, however ITS will work with Planning and Growth Management during the development phase of the program to further determine potential needs.
City
Strategic Plan
SE1 Provide consistent and high-quality information and services to residents, visitors and enterprises and improve clients’ interactions with the City by ensuring services are timely and coordinated, easy to find and access, and delivered in a way that respects residents’ needs.
SE2 Improve the effectiveness and efficiency of service delivery to reach targets that have been approved by Council and communicated to residents and staff.
The “Background” portion of this report outlines the legislative requirement for an Annual Report as per the Building Code Act. This portion of the report will be published on the City’s website and distributed upon request