Report to/Rapport au :

 

Planning and Environment Committee

Comité de l'urbanisme et de l'environnement

 

18 January 2005 / 18 janvier 2005

 

Submitted by/Soumis par :  Ned Lathrop, Deputy City Manager / Directeur municipal adjoint

Planning and Growth Management / Urbanisme et Gestion de la croissance

 

Contact Person/Personne ressource : Grant Lindsay, Manager / Gestionnaire

Development Approvals / Approbation des demandes d'aménagement

(613) 580-2424 x13242, Grant.Lindsay@ottawa.ca

 

Bay (7)

Ref N°: ACS2004-DEV-APR-0019

 

 

SUBJECT:

SITE PLAN CONTROL - 446 Edgeworth Avenue (FILE NO. D07-12-04-0239)

 

 

OBJET :

demande de réglementation du plan d'implantation - 446, avenue edgeworth

 

 

REPORT RECOMMENDATION

 

That Planning and Environment Committee APPROVE the Site Plan Control application for 446 Edgeworth Avenue as shown on the following plans:

 

1.         “Site Plan, 446 Edgeworth Avenue ” prepared by Douglas Hardie on behalf of the Regional Group, dated January 2004, revised January 11, 2005 and dated as received by the City of Ottawa on January 14, 2005.

 

2.         “Landscape Plan, 446 Edgeworth Avenue ” prepared by James B. Lennox & Associates on behalf of the Regional Group, dated January 2004, revised January 11, 2005 and dated as received by the City of Ottawa on January 14, 2005.

 

3.         "General Plan of Services, 446 Edgeworth Avenue ” prepared by Novatech Engineering Ltd., dated July 2004, revised January 26, 2005, dated as received by the City of Ottawa on January 26, 2005 and dated as reviewed by the Infrastructure Approval Division on January 26, 2005.

 

4.         "Lot Grading Plan, 446 Edgeworth Avenue” prepared by Novatech Engineering Ltd., dated July 2004, revised January 14 2005, dated as received by the City of Ottawa on January 26, 2005 and dated as reviewed by the Infrastructure Approval Division on January 26, 2005.

 

And subject to the owner entering into a standard site development agreement consisting of the standard and special conditions outlined in Document 5.  In the event the Owner fails to enter into such agreement within one year, this approval shall lapse.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité de l'urbanisme et de l'environnement APPROUVE la demande de réglementation du plan d'implantation concernant le 446, avenue Edgeworth, qui est illustré par les plans suivants :

 

1.         « Plan d'implantation, 446, avenue Edgeworth », produit par Douglas Hardie au nom de Regional Group, daté du mois de janvier 2004, révisé le 11 janvier 2005 et reçu par la Ville d’Ottawa le 14 janvier 2005. 

 

2.         « Plan d'aménagement paysager, 446, avenue Edgeworth », produit par James B. Lennox & Associates au nom de Regional Group, daté du mois de janvier 2004, révisé le 11 janvier 2005 et reçu par la Ville d’Ottawa le 14 janvier 2005.

 

3.         « Plan général des services, 446, avenue Edgeworth », produit par Novatech Engineering Ltd., daté du mois de juillet 2004, révisé le 26 janvier 2005, reçu par la Ville d'Ottawa le 26 janvier 2005 et examiné par la Division de l'approbation des demandes d'infrastructure le 26 janvier 2005.

 

4.         « Plan de nivellement du lot, 446, avenue Edgeworth », produit par Novatech Engineering Ltd., daté du mois de juillet 2004, révisé le 14 janvier 2005 , reçu par la Ville d'Ottawa le 26 janvier 2005 et examiné par la Division de l'approbation des demandes d'infrastructure le 26 janvier 2005.

 

À la condition que le propriétaire conclue une entente d'aménagement type renfermant les conditions types et particulières énoncées dans le document 5. Si le propriétaire ne conclut pas une telle entente dans un délai d'un an, l'approbation ne sera plus valide.

 

BACKGROUND

 

Site Location

 

The subject property, 446 Edgeworth Avenue, is located between Richmond Road and Lawn Avenue beside the Ottawa River Parkway.  To the north, south and east are single and semi-detached residential dwelling units. Immediately to the south of the subject property across Lawn Avenue is a 13-unit two-storey townhouse development. Several high-rise apartment towers are also in the area, to the north and south ends of Edgeworth Avenue. Four freehold row houses are located on the east side of Wentworth Avenue in an R4A zone. To the west of the subject site is an open space area containing the Ottawa River Parkway. The western portion of Lawn Avenue (immediately south of the site) is an unopened road right-of-way that accommodates a public path leading to the Ottawa River Parkway area.  Primary access to the site is provided off Edgeworth Avenue with additional pedestrian access off Lawn Avenue. A residential building and garage are currently located on the subject property.  

 

Proposed Development

 

The applicant is proposing construct two semi-detached dwellings, four townhouses, and 16 stacked townhouses on the site. The proposed semi-detached unit will front onto Edgeworth Avenue. The remaining townhouses will be located along the southern and western sides of the property. Access to the townhouses will be provided via an internal private road. The preliminary development proposal calls for 25 parking spaces to be provided on site. 

 

Concurrent Applications

 

A Zoning By-Law Amendment application to change the current zoning from an R2A-Semi-Detached to R4F-Multiple Unit exception zone was approved by the Planning and Environment Committee on October 26, 2004 and by Council on November 10, 2004.  One appeal to the zoning change was received. Consequently final approval of the zoning is subject to approval by the Ontario Municipal Board.

 

DISCUSSION

 

Official Plan Considerations

 

As noted, a rezoning application to permit the development being proposed was considered and approved by Council.  The review of the rezoning application involved extensive review of the proposal in the context of the Official Plan polices set out in the Council Approved Official Plan, the former Region's Official Plan and the former City of Ottawa Official Plan.  As set out in the staff report for the rezoning, staff concluded that the proposed development was consistent with the relevant polices of all three Official Plans that support intensification in a way that provides for a compatible relationship between a proposed development and the community wherein the development is located.

 

Zoning

 

The proposed development is in full compliance with the zoning as approved by Council.  Given that an appeal has been received to the Council approved zoning, a condition is included that approval of the site plan will only come into effect once final approval of the zoning has been obtained from the Ontario Municipal Board.

 

Design and Built Form

 

The proposed development is consistent with the City’s goals of providing new infill development that is compatible with the character of the existing neighbourhood. The proposed development successfully blends into the existing neighbourhood by fronting the proposed semi-detached unit and the end unit of the proposed townhouse unit onto Edgeworth Avenue. In doing so the development creates a continuous street frontage that is compatible with the surrounding area. Also, the height and scale of the units fronting onto Edgeworth Avenue respect the existing scale of the surrounding residential neighbourhood. The addition of new street trees and other landscaping elements add to this effect.

 

The remaining units of the townhouse block and the two stacked-townhouse blocks are appropriately placed in the rear of the property and will not have a direct visual impact on the character of Edgeworth Avenue.  The proposed parking area for the development will be screened from the street by a decorative gate feature which will include additional soft landscaping features. The interior yard will be softened, where needed, by several new deciduous trees and various shrubs. The height of the proposed stacked-townhouse blocks will be stepped-up from the semi-detached unit on Edgeworth Avenue, thereby providing a smooth vertical transition from the front to the rear of the site.  New fencing materials along the sides and rear of the property, in concert with the large trees that surround the site, will further serve to help blend the proposed development into the existing fabric of the community.

 

Under the former City of Ottawa Zoning By-law the proposed development is required to have a minimum of 22 parking spaces for residents and visitors on the site. As per the plans submitted, the development will have a total of 25 parking spaces on site.   This number satisfies the By-law requirements and is supported by staff. Also, it should be noted that the subject site is well serviced by transit and is located close to the Lincoln Fields Transitway station.  

 

The proposed development conforms to the yard requirements and amenity space provisions of the Council approved zone for this location. As part of this zoning, the interior lane was reduced from 6.7 metres to 6.0 metres so that the townhomes on the southern edge of the property would benefit from an additional 0.7 metres of rear yard amenity space. The overall provision of amenity space is enhanced by large outdoor decks for each unit. Also, it should be noted that the subject site is bounded on the south side by an unopened right-of-way, which is used as a green space, and to the west by the Ottawa River Parkway and it’s associated green space. Subsequently, staff are satisfied that the residents of the proposed development will have adequate access to outdoor amenity areas.

 

In reviewing the plans for this development, staff are satisfied that as many trees as possible will be retained on the site and that an adequate amount of new landscaping, including several new tree species, will be provided. Furthermore, all existing trees will be protected during the construction of the proposed development. The trees that are situated in the Lawn Avenue right-of-way and the Ottawa River Parkway corridor will not be affected by this development and their existence will continue to enhance the environmental quality of the site and the immediate neighbourhood.

 

The provision and location of on-site garbage and recycling collection meets the guidelines of the City’s Solid Waste Division and Planning staff. Garbage and recycling for the three units that front onto Edgeworth Avenue will be collected by on-street City collection. Garbage and recycling for the interior townhomes and the stacked-town home units will be collected in two large, centrally located garbage bins which will be emptied by City trucks. Recycling for these units will be collected and stored in 6 large bins that will be located next to the garbage bins and will be emptied in the same manner.

 

Staff is satisfied with the Site Servicing and Grading Plans submitted for the proposed development. All storm water will be dealt with in accordance with the City’s stormwater management requirements. The management of snow within the proposed development will be the responsibility of the owners. The City is satisfied that there is adequate space for the temporary storage of excess snow on site. 

     

 

ENVIRONMENTAL IMPLICATIONS

 

The Municipal Environmental Evaluation Process (MEEP) checklist indicates that there will be no impacts as a result of this application. 

 

CONSULTATION

 

Notice of this application was carried out in accordance with the City’s Public Notification and Consultation Policy. Information signs were posted on-site indicating the nature of the application.  The Ward Councillor is aware of this application and the staff recommendation.

 

Detailed responses to the notification/circulation are provided in Document 6.

 

FINANCIAL IMPLICATIONS

 

N/A

 

APPLICATION PROCESS TIMELINE STATUS

 

This application was processed within the timeframe established for the processing of Site Plan Control applications in which Delegation of Authority is removed.

 

SUPPORTING DOCUMENTATION

 

Document 1 –   Location Map

Document 2 –   Site Plan

Document 3 –   Landscape Plan

Document 4 –   Site Grading and Drainage

Document 5 –   Conditions of Site Plan Control Approval

Document 6 –   Consultation Details

 

 

DISPOSITION

 

Department of Corporate Services, Legal Services Branch to prepare the Site Plan Control agreement.

 

Department of Planning and Growth Management to notify the owner/applicant (Steve Cunliffe, The Regional Group, 700 Catherine Street, 6th Floor, Ottawa, ON, K2P 2K9, the architect Douglas Hardie, 311 Richmond Road, Ottawa, ON, K1F 6X3), All Signs, 8692 Russell Road, Navan, ON  K4B 1J1, and all interested parties of Planning and Environment Committee’s decision.

 

 


LOCATION MAP                                                                                                         Document 1

 

 


SITE PLAN                                                                                                                    Document 2

 


LANDSCAPE PLAN                                                                                                     Document 3

 


SITE GRADING AND DRAINAGE                                                                           Document 4

 


CONDITIONS OF SITE PLAN CONTROL APPROVAL                                        Document 5

 

SCHEDULE “D”

 

SITE SPECIFIC CONDITIONS

 

STANDARD CONDITIONS

 

1.  Permits

 

The Owner(s) shall obtain such permits as may be required from Municipal or Provincial authorities and shall file copies thereof with the Director, Planning and Infrastructure Approvals Branch.

 

 

2.  Barrier Curbs

 

The Owner(s) agrees that the parking areas (and entrances) shall have barrier curbs and shall be constructed as approved by the Director, Planning and Infrastructure Approvals.

 

3.  Water Supply for Fire Fighting

 

The Owner(s) shall provide adequate water supply for fire fighting for every building. Water supplies may be public water works system, automatic fire pumps, and pressure tanks for gravity tanks.

 

4.  Maintenance Agreements for Condominium Corporations

 

The Owner(s) shall, within 15 days of the formation of a Condominium Corporation or Corporations, and while the Owner has control of the Corporation as Owner of the majority of units, cause the condominium corporation to execute under seal and register upon title to the lands, a Maintenance Agreement in favour of the City in such form and in such terms as the City may require. In the event that the Owner shall fail to comply herewith prior to loss of control of the Condominium Corporation, the existence of this agreement shall be deemed to constitute a grant and conveyance to the City of Ottawa of the free and uninterrupted right, in perpetuity, to enter upon the lands for purposes of maintenance of the works until such time as such Maintenance Agreement is so executed and registered.

 

5.  Private Agreement for Common Elements

 

(a)        The Owner(s) agrees that should the site be severed in the future, that it shall ensure that the future Owner of the freehold units shall enter into a Private Agreement which shall be binding upon the owners and all subsequent purchasers to deal with the joint use, maintenance and liability of the common elements, including but not limited to the private roadway and concrete sidewalks; common grass areas; common party walls, exterior walls; common structural elements such as the roof, foundations; common parking areas; private sewers: and watermains for the mutual benefit and joint use of the owners; and any other elements located in the common property; and the private Agreement shall be filed with the Director, Planning and Infrastructure Approvals.

 

(b)        The Owner(s) shall file with the Director, Planning and Infrastructure Approvals, an opinion from a solicitor authorized to practice law in the Province of Ontario that the private Agreement is binding upon the owners of the land and all subsequent purchasers to deal with the matters referred to Paragraph (a).              

 

(c)        The Joint Use, Maintenance and Liability Private Agreement shall be registered on the Owner’s land at no cost to the City, and a copy shall be provided to the City.

 

 

6.  Reinstatement of City Property

 

The Owner(s) shall reinstate at its expense, to the satisfaction of the Director of Planning and Infrastructure Approvals, any property of the City, including, but not limited to, sidewalks and curbs, boulevards, that are damaged as a result of the subject development.

 

7.  Waste Collection on Private Streets

 

All prospective purchases shall be informed through a clause in the Agreements of Purchase and sale, that individual curbside waste collection and/or recycling collection for properties fronting onto the private street may not be provided by the City, and that waste collection and/or recycling collection by the City of such properties may take place at common collection pad(s) provided by the Owner(s).

 

8.  Completion of Works

 

No building will be occupied on the lands, nor will the Owner(s) convey title to any building until all requirements with respect to completion of the Works as identified in this Agreement have been carried out and received Approval by the Director, Infrastructure Services, including the installation of municipal numbering provided in a permanent location visible during both day and night and the installation of any street name sign on relevant streets. Provided that notwithstanding the non-completion of the foregoing Works, conveyance and/or occupancy of a lot or structure may otherwise be permitted, if in the sole opinion of the Director, Planning and Infrastructure Approvals, the aforesaid Works are proceeding satisfactorily toward completion.  The Owner shall obtain the consent of the Director, Planning and Infrastructure Approvals for such conveyance and/or occupancy in writing.

 

SPECIAL CONDITIONS

 

9.  Sanitary Sewer Charge on Additional Sanitary Flow

 

The proposed development is located within a sanitary collector area which has been assessed by the City to be at capacity. The Owner(s) shall liaise with the City to identify extraneous wet weather flow sources. Where flow removal cannot be achieved on site, removal of extraneous flows will be conducted through a flow removal program. The Owner(s) shall contribute  $4,772/l/s x [increase in avg. sanitary flow x 1.5 peaking factor + infiltration (0.28 l/s/ha)] for additional sanitary flow generated by this site.

 

10.   Final Zoning Approval

 

The Site Plan Approval will not come into effect until such time as the Zoning approved by Council on November 10, 2004 has received final approval by the Ontario Municipal Board and all levels of appeal are exhausted.

 

 


CONSULTATION DETAILS                                                                                       Document 6

 

 

NOTIFICATION AND CONSULTATION PROCESS

 

Notification and public consultation was undertaken in accordance with the Public Notification and Public Consultation Policy approved by City Council for Site Plan Amendments. 

 

PUBLIC COMMENTS

[U1] 

No comments regarding the Site Plan Control application for 446 Edgeworth Avenue were received during the Public Circulation process.

[U2] 

COUNCILLOR’S COMMENTS

[U3] 

Councillor Alex Cullen is aware of the application.

[U4] 

COMMUNITY ORGANIZATION COMMENTS

[U5] 

One email sent on behalf of the Woodpark Community Association was received on November 10, 2004. The content of the email is stated below:

[U6] 

"The Board of the Woodpark Community Association and community residents have reviewed the submitted site plans for 446 Edgeworth Avenue.  We have  serious concerns regarding this site plan including: insufficient resident and visitor parking; insufficient amenity space; inadequate tree preservation and protection; excessive lot coverage in regards to the percent of  impermeable surface and resulting storm water runoff; inadequate snow storage; a lack of privacy fencing on the property's periphery; no apparent lighting fixtures designed to prevent spill over onto abutting and adjacent properties; and, no apparent provision for garbage storage or pick up for the proposed condo units."

 

Response to Comments:

 

a)         Insufficient resident and visitor parking:

 

Under the former City of Ottawa Zoning By-law the proposed development is required to have a minimum of 22 parking spaces for residents and visitors on the site. As per the plans submitted, the development will have a total of 25 parking spaces on site.  

 

b)         Insufficient amenity space:

 

The proposed development conforms to the yard requirements and amenity space provisions of R4F-exception zone which was created for this location. As part of this zoning, the interior lane was reduced from 6.7 metres to 6.0 metres so that the townhomes on the southern edge of the property would benefit from an additional 0.7 metres of rear yard amenity space.

 

c)         Inadequate tree preservation and protection:

 

The City is satisfied that as many trees as possible will be retained on the site and that an adequate amount of new landscaping, including several new tree species, will be provided. Furthermore, all existing trees will be protected during the construction of the proposed development.

 

d)         Excessive lot coverage in regards to the percent of  impermeable surface and resulting storm water runoff:

 

The proposed lot coverage conforms to the performance standards of the R4F-exception zone. All storm water will be dealt with in accordance with the City’s stormwater management requirements, as shown in the Site Service Plan.

 

e)         Inadequate snow storage:

 

The management of snow within the proposed development will be the responsibility of the owners. The City is satisfied that there is adequate space for the temporary storage of excess snow on site. 

 

f)          A lack of privacy fencing on the property's periphery:

 

The City is satisfied that privacy fencing on the property's periphery is appropriate.

 

g)         No apparent lighting fixtures designed to prevent spill over onto abutting and adjacent properties:

 

The revised Site Plan shows the location of light stands within the proposed development. Light spill over from the property will be minimized through the strategic placement of light fixtures and the use of low wattage fixtures.

 

h)         No apparent provision for garbage storage or pick up for the proposed condo units:

 

A garbage and recycling collection area has been provided in accordance with the City of Ottawa Solid Waste Division's Standards.

 

 

 


 [U1]Summarize the public notification and consultation undertaken.

 [U2]Provide details of any public meeting(s).

 [U3]Insert Councillor’s comments

 [U4]Insert our response

 [U5]Insert Community Organization Comments

 [U6]Insert our response