Ottawa Police Service |
|
|
|
Project Works In
Progress |
|
March 31, 2014 |
|
Capital Projects |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Spending Incl. |
|
|
|
|
Project # |
Description |
Budget |
Commitments |
Encumbrance |
Residual |
Status |
|
|
|
|
|
|
|
|
904516 |
Comm Centre/911 Refit |
2,471,100 |
2,139,501
|
|
331,599
|
Project being
finalized. Construction, fit-up,
furniture and equipment |
|
907080 |
Facility Realignment Plan 2013 |
5,278,900 |
3,768,861
|
|
1,510,039
|
Space fit-ups,
furniture and equipment |
|
907491 |
Elgin Refit 2014 |
1,220,000 |
1,528
|
|
1,218,472
|
Refit of
Operational Space @ Elgin |
|
907492 |
Swansea Refit |
150,000 |
0 |
|
150,000
|
Refit of Fleet
& Material Management Space @ Swansea |
|
Accommodation Master Plan |
9,120,000
|
5,909,890
|
|
3,210,110 |
|
|
|
|
|
|
|
|
|
|
906165 |
Facility Minor Capital - 2011 |
440,000 |
339,064
|
|
100,936
|
Chair
Replacement Program, Fire Safety Plan, Gun Locker Rekeying, Centretown CPC
Space Fit Up |
|
906560 |
Facility Minor Capital - 2012 |
840,000 |
380,790
|
|
459,210
|
Chair
Replacement Program, Minor Facility Work to Meet Operational Needs |
|
907078 |
Accommodations and Alterations
2013 |
695,000 |
266,974
|
|
428,026
|
Chair
Replacement Program, Minor Facility Work to Meet Operational Needs |
|
Facility Minor Capital |
1,975,000
|
986,828
|
|
988,172 |
|
|
|
|
|
|
|
|
|
|
902244 |
Algonquin Range |
650,000 |
0 |
|
650,000
|
Purchase of
remaining portion of the Range per agreement. |
|
903447 |
Facility
Acquisition - South |
30,300,000
|
68,205
|
|
30,231,795
|
Initiating Site
selection and project delivery methodology |
|
906166 |
Facility
Strategic Plan 2011 |
2,050,000
|
1,920,921
|
|
129,079
|
Elgin
Realignment, Fleet Realignment to Swansea, Minor Divisional Facility
Realignments |
|
907378 |
Workplace Innovation Project |
225,000 |
162,423
|
|
62,577
|
|
|
Facility
Acquisition Plan |
33,225,000
|
2,151,549
|
|
31,073,451
|
|
|
|
|
|
|
|
|
|
|
|
904134 |
BSAC Security Upgrades 2010 |
461,000 |
461,000
|
|
0 |
Project
Complete - To be closed |
|
906164 |
BSAC Security Upgrades 2011 |
272,000 |
272,000
|
|
0 |
Project
Complete - To be closed |
|
|
906559 |
BSAC Security Upgrades 2012 |
125,000 |
97,038
|
|
27,962
|
ISMS Upgrades
to Divisional Facilities |
|
|
906772 |
Facility Security Initiatives 2012 |
714,000 |
137,781 |
|
576,219 |
Security
enhancements to OPS Buildings and Grounds |
|
Building
Security and Access Control |
1,572,000 |
967,819
|
|
604,181 |
|
|
|
|
|
|
|
|
|
|
905486 |
Facility Lifecycle - 2011 |
889,000 |
711,682 |
|
177,318 |
Projects as
identified in the 2011 Budget |
|
906561 |
Facility Lifecycle - 2012 |
1,975,000 |
1,738,351 |
|
236,649 |
Projects as
identified in the 2012 Budget |
|
907079 |
Facility Lifecycle - 2013 |
2,200,000 |
1,132,898 |
|
1,067,102 |
Projects as
identified in the 2013 Budget |
|
905092 |
Facility Initiatives-2009 |
750,000 |
587,403 |
|
162,597 |
Projects
ongoing, Delays encountered as work must be sequenced with OPS Facilities to
lessen impact on Police Operations |
|
906564 |
Facility Initiatives-2012 |
100,000 |
0 |
|
100,000 |
Elgin Exterior
Cladding |
|
907081 |
Facility Initiatives-2013 |
250,000 |
0 |
|
250,000 |
Elgin Exterior
Cladding & Greenbank UPS |
|
904137 |
Elgin Emergency Generator |
3,650,000 |
3,600,529 |
|
49,471 |
Project
Complete - To be Closed |
|
|
RPAM
Facility Workplan |
9,814,000 |
7,770,863 |
|
2,043,137
|
|
|
|
|
|
|
|
|
|
|
|
|
904518 |
IT Upgrade & Expansion - 2008 |
1,340,000 |
1,282,130 |
|
57,870 |
474 Elgin
Retrofit, Netmotion Upgrade, Active Directory Upgrade |
|
905736 |
IT Infrastructure - 2010 |
722,000 |
581,120 |
|
140,880 |
Microsoft
Exchange upgrade, server replacement and firewall replacement |
|
905737 |
IT Storage - 2010 |
960,000 |
960,000 |
|
0 |
Project
Complete - To be closed |
|
906048 |
IT Infrastructure - 2011 |
1,037,000 |
1,006,629 |
|
30,371 |
Server
Upgrades and Wireless expansion to all main OPS buildings |
|
906049 |
IT Storage - 2011 |
1,255,000 |
1,180,160 |
|
74,840 |
FIS Equipment |
|
906553 |
IT Infrastructure - 2012 |
1,000,000 |
741,608 |
|
258,392 |
VMWare
upgrade, Server replacement, Wireless expansion project |
|
906554 |
IT Storage - 2012 |
700,000 |
649,523 |
|
50,477 |
Enterprise
storage solution for retaining, managing data |
|
907073 |
IT Infrastructure - 2013 |
1,450,000 |
520,903 |
|
929,097 |
Hardware
replacement, Windows 7 upgrade, network monitoring solution, print management
solution, roadmap for increased functionality of mobile workstations |
|
907488 |
Infrastructure Support |
1,290,000 |
0 |
|
1,290,000 |
Hardware
replacement, storage expansion, introduction of Anywhere, Anytime, Any device
platform, roadmap for increased functionality of mobile workstation |
|
905739 |
IT Applications - 2010 |
420,000 |
180,973 |
|
239,027 |
Disaster
Recovery, Identity & Access Management; (this project includes a $97,000
credit for Fire CAD work) |
|
906211 |
IT Applications - 2011 |
382,000 |
311,579 |
|
70,421 |
VGI, VCAP,
Succession Management Software, CAD Upgrade |
|
906556 |
IT Applications - 2012 |
320,000 |
199,526 |
|
120,474 |
Service
Catalogue, GIS Server Enhancement, Entity Analytical Suite |
|
907075 |
IT Applications - 2013 |
350,000 |
244,179 |
|
105,821 |
Application
upgrades including RMS, MDT, MSDM |
|
906210 |
Telecommunications - 2011 |
420,000 |
347,382 |
|
72,618 |
Replace
network switch, Upgrade NICE phone system |
|
906555 |
Telecommunications - 2012 |
837,000 |
810,050 |
|
26,950 |
Upgrade NICE
phone system, partner assurance support service, wireless hardware
replacement, router upgrade |
|
907074 |
Telecommunications - 2013 |
650,000 |
432,622 |
|
217,378 |
VoIP
infrastructure and cabling, replacement of servers and data switches |
|
907489 |
Secure Communications Connectivity |
765,000 |
(346) |
|
765,346 |
VoIP
infrastructure and cabling, firewall replacement, geo-redundant call pilot
enhancement, replace data switches |
|
904133 |
IT Strategic Initiatives |
1,370,000 |
1,192,142 |
|
177,858 |
Improvements
to IT service delivery and upgrades to existing infrastructure |
|
907495 |
New Facility South - IM/IT |
1,000,000 |
0 |
|
1,000,000 |
Purchase of
redundancy equipment for the Communication Centre |
|
Information
Technology & Telecommunications |
16,268,000 |
10,640,179 |
|
5,627,821 |
|
|
|
|
|
|
|
|
|
|
906047 |
IT Mobile Workstations-2011/2012 |
899,000 |
863,816 |
|
35,184 |
Third phase of
in-car mobile workstation replacement program |
|
Mobile
Workstations |
899,000 |
863,816 |
|
35,184 |
|
|
|
|
|
|
|
|
|
|
906046 |
Vehicle Replacement - 2011 |
2,293,000 |
2,276,425 |
|
16,575 |
Balance to be
used for anti-idling for 2 Paid Duty vehicles |
|
906552 |
Vehicle Replacement - 2012 |
2,850,000 |
2,514,494 |
|
335,506 |
Balance to be
used for : anti-idling for Tauruses; MDT's for paid duty; 2012 replacement
plan |
|
907072 |
Vehicle Replacement - 2013 |
2,850,000 |
2,421,417 |
|
428,583 |
2013
replacement plan plus $480K for anti-idling |
|
907487 |
Vehicle Replacement - 2014 |
2,850,000 |
566,733 |
|
2,283,267 |
2014
replacement plan plus $185K for fleet strategic initiatives |
|
Vehicle
Replacement |
10,843,000 |
7,779,069 |
|
3,063,931 |
|
|
|
|
|
|
|
|
|
|
903806 |
Strategic Growth Initiative 2010 |
300,000 |
232,397 |
|
67,604 |
Succession
management tools and policy; Corporate Support business process
improvement |
|
903450 |
Portable Radio Replacement |
6,840,000 |
292,743 |
|
6,547,257
|
Phase
1 of radio upgrade |
|
903452 |
OPS Share of Radio System |
2,900,000 |
0 |
|
2,900,000 |
Working in
partnership with the City of Ottawa, to upgrade existing radio network
infrastructure |
|
906214 |
2011 Ottawa Police Operational |
215,000 |
150,000 |
|
65,000 |
Marine safety
equipment |
|
906557 |
2012 Ottawa Police Operational |
932,000 |
868,205 |
|
63,795 |
Alcotesters,
robot, line of site devices, cameras, mini-labs, gas masks |
|
907077 |
2013 Ottawa Police Operational |
600,000 |
325,970 |
|
274,030 |
Public Order
protective equipment, water safety program, final phase of camera
standardization program, gas masks, forklift |
|
906213 |
Business Transformation |
2,645,000 |
1,683,280 |
|
961,720 |
Collision
reporting centres; E-disclosure; race
based data collection, IT Infrastructure |
|
907076 |
Business Solutions 2013 |
500,000 |
206,308 |
|
293,692 |
Project
funding aimed at improving service delivery |
|
Other Projects |
|
14,932,000 |
3,758,901 |
|
11,173,099 |
|
|
Report Total |
|
94,163,000 |
37,873,970
|
|
56,289,030
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|