Ottawa Police Service
Capital Budget Works In Progress
September 30, 2013
Capital Project          
      Spending Incl.      
Project # Description Budget Commitments Encumberance Residual Status
           
904516 Comm Centre/911 Refit 2,471,100 2,151,245   319,855 Project being finalized. Anticipated to be closed Q4 2013.  Construction, fit-up, furniture and equipment
907080 Facility Realignment Plan 2013 5,278,900 277,300   5,001,600 Space fit-ups, furniture and equipment
Accommodation Master Plan 7,750,000 2,428,545   5,321,455  
             
905485 Facility Minor Capital - 2010 510,000 520,957   -10,957 Funding Shortfall to be covered by project 906165 Facility Minor Capital - 2011
906165 Facility Minor Capital - 2011 440,000 317,850   122,150 Chair Replacement Program,Fire Safety Plan, Gun Locker Rekeying, Centretown CPC Space Fit Up
906560 Facility Minor Capital - 2012 840,000 354,948   485,052 Chair Replacement Program, Minor Facility Work to Meet Operational Needs
907078 Accommodations and Alterations 2013 695,000 102,884   592,116 Chair Replacement Program, Minor Facility Work to Meet Operational Needs
Facility Minor Capital 2,485,000 1,296,639   1,188,361  
           
902244 Algonquin Range 650,000 0   650,000 Purchase of remaining portion of the Range per agreement.
903447 Facility Acquisition - South 30,300,000 68,205   30,231,795 Initiating Site selection and project delivery methodology
906166 Facility Strategic Plan 2011 2,050,000 1,933,026   116,974 Elgin Realignment, Fleet Realignment to Swansea, Minor Divisional Facility Realignments
907378 Workplace Innovation Project 225,000 0   225,000  
Facility Acquisition Plan 33,225,000 2,001,231   31,223,769  
             
904134 BSAC Security Upgrades 2010 461,000 461,000   0 Project Complete - To be closed
906164 BSAC Security Upgrades 2011 272,000 272,000   0 Project to be complete Q4 2013 - Security Enhancements and Fleet Key Management Systems
906559 BSAC Security Upgrades 2012 125,000 11,498   113,502 ISMS Upgrades to Divisional Facilities
906772 Facility Security Initiatives 2012 714,000 38,929   675,071 Security enhancements to OPS Buildings and Grounds 
Building Security and Access Control 1,572,000 783,427   788,573  
             
905091 Facility Lifecycle - 2009 1,240,000 1,235,643   4,357 Project to be complete by Q4 2013
905486 Facility Lifecycle - 2011 889,000 696,462   192,538 Projects as identified in the 2011 Budget tabling document
906561 Facility Lifecycle - 2012 1,975,000 1,288,092   686,908 Projects as identified in the 2012 Budget tabling document
907079 Facility Lifecycle - 2013 2,200,000 526,863   1,673,137 Projects as identified in the 2013 Budget tabling document
905092 Facility Initiatives-2009 750,000 589,895   160,105 Projects ongoing, Delays encountered as work must be sequenced with OPS Facilities to lessen impact on Police Operations
906260 Facility Initiatives-2011 191,000 188,508   2,492 Project to be complete by Q4 2013
906564 Facility Initiatives-2012 100,000 0   100,000 Elgin Exterior Cladding
907081 Facility Initiatives-2013 250,000 0   250,000 Elgin Exterior Cladding & Greenbank UPS
904137 Elgin Emergency Generator 3,650,000 3,600,529   49,471 Project Complete - To be Closed
RPAM Facility Workplan 11,245,000 8,125,992   3,119,008  
           
904518 IT Upgrade & Expansion - 2008 1,340,000 1,208,588   131,412 474 Elgin Retrofit, Netmotion Upgrade, Active Directory Upgrade
905736 IT Infrastructure - 2010 722,000 581,120   140,880 Microsoft Exchange upgrade, server replacement and firewall replacement
905737 IT Storage - 2010 960,000 960,000   0 To be closed once commitments have cleared
906048 IT Infrastructure - 2011 1,037,000 998,719   38,281 Server Upgrades and Wireless expansion to all main OPS buildings
906049 IT Storage - 2011 1,255,000 1,134,679   120,321 FIS Equipment
906553 IT Infrastructure - 2012 1,000,000 646,498   353,502 VMWare upgrade, Server replacement, Wireless expansion project
906554 IT Storage - 2012 700,000 634,820   65,180 Enterprise storage solution for retaining, managing data
907073 IT Infrastructure - 2013 1,450,000 409,771   1,040,229 Hardware replacement, Windows 7 upgrade, network monitoring solution, print management solution, roadmap for increased functionality of mobile workstations
905739 IT Applications - 2010 420,000 179,853   240,147 Disaster Recovery, Identity & Access Management; (this project includes a $97,000 credit for Fire CAD work)
906211 IT Applications - 2011 382,000 245,826   136,174 VGI, VCAP, Succession Management Software, CAD Upgrade
906556 IT Applications - 2012 320,000 26,018   293,982 Service Catalogue, GIS Server Enhancement, Entity Analytical Suite
907075 IT Applications - 2013 350,000 126,481   223,519 Application upgrades including RMS, MDT, MSDM 
906210 Telecommunications - 2011 420,000 362,030   57,970 Replace network switch, Upgrade NICE phone system
906555 Telecommunications - 2012 837,000 809,677   27,323 Upgrade NICE phone system, partner assurance support service, wireless hardware replacement, router upgrade
907074 Telecommunications - 2013 650,000 364,052   285,948 VoIP infrastructure and cabling, replacement of servers and data switches
904133 IT Strategic Initiatives 1,370,000 1,184,988   185,012 Improvements to IT service delivery and upgrades to existing infrastructure
Information Technology & Telecommunications 13,213,000 9,873,122   3,339,878  
             
906047 IT Mobile Workstations-2011/2012 899,000 866,136   32,864 Third phase of in-car mobile workstation replacement program
Mobile Workstations 899,000 866,136   32,864  
             
906046 Vehicle Replacement - 2011 2,293,000 2,276,425   16,575 Balance to be used for anti-idling for 2 Paid Duty vehicles
906552 Vehicle Replacement - 2012 2,850,000 2,502,844   347,156 Balance to be used for : anti-idling for Tauruses; MDT's for paid duty; 2012 replacement plan 
907072 Vehicle Replacement - 2012 2,850,000 2,277,628   572,372 2013 replacement plan plus $480K for anti-ilding
Vehicle Replacement 7,993,000 7,056,897   936,103  
           
903806 Strategic Growth Initiative 2010 300,000 244,309   55,691 Succession management tools and policy; Corporate Support business process improvement 
906212 Strategic Growth Initiative 2011 545,000 545,000   0 Project Complete - To be closed
903450 Portable Radio Replacement 6,840,000 195,687   6,644,313 Phase 1 of radio upgrade
903452 OPS Share of Radio System 2,900,000 93,452   2,806,548 Working in partnership with the City of Ottawa, to upgrade existing radio network infrastructure
906214 2011 Ottawa Police Operational 215,000 150,000   65,000 Marine safety equipment
906557 2012 Ottawa Police Operational 932,000 867,983   64,017 Alcotesters, robot, line of site devices, cameras, mini-labs, gas masks
907077 2013 Ottawa Police Operational 600,000 325,424   274,576 Public Order protective equipment, water safety program, final phase of camera standardization program, gas masks, forklift
906213 Business Transformation 2,645,000 1,235,210   1,409,790 Collision reporting centres; E-disclosure;  race based data collection, IT Infrastructure
907076 Business Solutions 2013 500,000 348   499,652 Project funding aimed at improving service delivery
Other Projects    15,477,000 3,657,412   11,819,588  
Report Total   92,623,450 35,013,779   57,609,671