Ottawa Police Service
Capital Budget Works In Progress
March 31, 2012
Capital Project        
      Spending Incl.    
Project # Description Budget Commitments Unspent Status
         
904516 Comm Centre/911 Refit 4,000,000 199,868 3,800,132 Preliminary work initiated.  Project scope being finalized
Accommodation Master Plan 4,000,000 199,868 3,800,132  
           
904531 2008 Operational Fit-up  1,535,000 1,471,370 63,630 Project closed 2011 4th Quarter Report
905090 Facility Minor Capital - 2009 300,000 300,000 0 Project closed 2011 4th Quarter Report
905485 Facility Minor Capital - 2010 510,000 412,805 97,195 PDC Reconfiguration, Greenbank Front Desk H&S, Kit Bag Storage
906165 Facility Minor Capital - 2011 440,000 207,145 232,855 Chair Replacement Program,Fire Safety Plan, Gun Locker Rekeying, Somerset CPC Space Fit Up
906560 Facility Minor Capital - 2012 840,000 45,272 794,728 Chair Replacement Program, Minor Facility Work to Meet Operational Needs
Facility Minor Capital 3,625,000 2,436,592 1,188,408  
         
902244 Algonquin Range 650,000 0 650,000 Purchase of remaining portion of the Range per agreement.
903447 Facility Acquisition - South 30,300,000 67,047 30,232,953 Initiating Site selection and project delivery methodology
903448 Facility Acquisition - West 20,596,000 20,223,452 372,548 Project to be identified for closure in Q2 2012
906166 Facility Strategic Plan 2011 2,950,000 1,182,310 1,767,690 Elgin Realignment, Fleet Realignment to Swansea, Minor Divisional Facility Realignments
Facility Acquisition Plan 54,496,000 21,472,809 33,023,191  
           
904134 BSAC Security Upgrades 2010 461,000 384,250 76,750 Security Enhancements & Upgrades,  Badgemaster
906164 BSAC Security Upgrades 2011 272,000 39,153 232,847 Security Enhancements and Fleet Key Management Systems
906559 BSAC Security Upgrades 2012 125,000 0 125,000 ISMS Upgrades to Divisional Facilities
Building Security and Access Control 858,000 423,403 434,597   38,696,328
         
904523 Facility Lifecycle - 2008 1,550,000 1,550,000 0 Complete, Project to be closed 2012 1st Quarter Report
905091 Facility Lifecycle - 2009 1,240,000 1,152,019 87,981 Project to be complete by Q2 2012
905486 Facility Lifecycle - 2011 889,000 454,015 434,985 Projects as identified in the 2011 Budget tabling document
906561 Facility Lifecycle - 2012 2,200,000 687,989 1,512,011 Projects as identified in the 2012 Budget tabling document
904524 Facility Initiatives-2008 650,000 650,000 0 Complete, Project to be closed 2012 1st Quarter Report
905092 Facility Initiatives-2009 750,000 612,722 137,278 Projects ongoing, Delays encountered as work must be sequenced with OPS Facilities to lessen impact on Police Operations
906260 Facility Initiatives-2011 655,000 63,708 591,292 Projects as identified in the 2011 Budget tabling document
906564 Facility Initiatives-2012 100,000 0 100,000 Projects as identified in the 2012 Budget tabling document
906563 Facility Security Initiatives 2012 250,000 0 250,000 Security enhancements to OPS Buildings and Grounds 
904137 Elgin Emergency Generator 3,650,000 3,658,316 -8,316 Replacement of Main Emergency Generator
RPAM Facility Workplan 11,934,000 8,828,769 3,105,231  
         
904518 IT Upgrade & Expansion - 2008 1,340,000 1,148,784 191,216 474 Elgin Retrofit, wireless expansion
905736 IT Infrastructure - 2010 722,000 454,280 267,720 Microsoft Exchange upgrade, server replacement and virus software upgrade
905737 IT Storage - 2010 960,000 762,751 197,249 Enterprise storage solution for retaining, managing data
906048 IT Infrastructure - 2011 1,037,000 642,050 394,950 Hardware replacement, upgrade of security and network software, wireless expansion
906049 IT Storage - 2011 1,255,000 892,729 362,271 Enterprise storage solution for retaining, managing data
906553 IT Infrastructure - 2012 1,000,000 10,074 989,926 Hardware replacement, Microsoft Exchange upgrade, roadmap for Private Cloud Computing
906554 IT Storage - 2012 700,000 45,053 654,947 Enterprise storage solution for retaining, managing data
905100 IT Applications - 2009 290,000 211,647 78,353 Application upgrades
905739 IT Applications - 2010 420,000 52,375 367,625 Application upgrades; (this project includes a $97,000 credit for Fire CAD work)
906211 IT Applications - 2011 382,000 74,660 307,340 CAD, VGI, VCAP, etc upgrades and enhancements
906556 IT Applications - 2012 500,000 1,148 498,852  
905097 Telecommunications - 2009 365,000 255,162 109,838 Replace Network Switch
905738 Telecommunications - 2010 220,000 169,426 50,574 474 Elgin Retrofit
906210 Telecommunications - 2011 420,000 145,446 274,554 VoIP Greenbank, wireless hardware replacements, replace network switch
906555 Telecommunications - 2012 657,000 0 657,000 VoIP Elgin, partner assurance support service, wireless hardware replacement for cellphones and Blackberries
904133 IT Strategic Initiatives 1,370,000 831,104 538,896 Improvements to IT service delivery and upgrades to existing infrastructure - Social Media, and Sharepoint
905093 Collision Reporting 370,000 0 370,000 New electronic platform for collision reporting - moving to Business Transformation Project
905235 Livescan & Mugshot System 327,000 317,973 9,027 To be completed by Q2 2012
Information Technology & Telecommunications 12,335,000 6,014,663 6,320,337  
         
904125 IT Mobile Workstations-2007/2008 2,045,000 2,045,000 0 To be closed once commitments have cleared
905095 IT Mobile Workstations-2010/2011 1,400,000 1,400,000 0 To be closed once commitments have cleared
906047 IT Mobile Workstations-2011/2012 1,144,000 433,786 710,214 Third phase of in-car mobile workstation replacement program
Mobile Workstations 4,589,000 3,878,786 710,214  
         
905735 Vehicle Replacement - 2010 3,578,000 3,578,000 0 To be closed once commitments (for vessel and anti-idling technology) have cleared 
906046 Vehicle Replacement - 2011 2,293,000 2,024,971 268,029 P.O for vessels; sedans, SUVs etc from 2012 replacement plan; $32K for anti-idling
906552 Vehicle Replacement - 2012 2,850,000 1,816,079 1,033,921 For 75 vehicles based upon 2012 replacement plan
Vehicle Replacement 8,721,000 7,419,050 1,301,950  
         
905101 Strategic Growth Initiative 2009 300,000 300,000 0 Complete; Project to be closed 2012 1st Quarter Report
903806 Strategic Growth Initiative 2010 300,000 58,938 241,062 $84K for surveillance vehicles; rest held for SDP implementation
906212 Strategic Growth Initiative 2011 300,000 0 300,000 Held for non-compensation costs SDP
903450 Portable Radio Replacement 6,840,000 195,687 6,644,313 Phase 1 of radio upgrade
903452 OPS Share of Radio System 2,900,000 71,589 2,828,411 Working in partnership with the City of Ottawa, to upgrade existing radio network infrastructure
905103 2010 Ottawa Police Operational 318,000 247,194 70,806 For purchase of electronic control devices; JEPP Grant request
906214 2011 Ottawa Police Operational 215,000 177,904 37,096 Cameras, marine safety equipment
906557 2012 Ottawa Police Operational 932,000 165,517 766,483 Alcotesters, robot, line of site devices, cameras, mini-labs, gas masks
906213 Business Transformation 2,275,000 211,043 2,063,957 Collision reporting centres, Criminal records check process, Client Self-reporting
906220 Cellblock Security 350,000 342,441 7,559 Expansion of cellblock audio/video monitoring system
Other Projects    14,730,000 1,770,315 12,959,685  
Report Total   115,288,000 52,444,255 62,843,745  
sheila's groups from above 40,375,000 19,082,813 21,292,187
sheila's groups from SAP
POL30000 17,274,000 10,235,890 7,038,110
POL40000 8,721,000 7,419,050 1,301,950
POL45000 900,000 358,938 541,062
POL50000 13,792,000 1,380,935 12,411,065
40,687,000 19,394,813 21,292,187
see closed projects
Difference -312,000 -312,000 0