REPORT RAPPORT |
DATE:
|
26 April 2011 |
TO/DEST:
|
Executive Director, Ottawa Police Services Board |
FROM/EXP:
|
Chief of Police, Ottawa Police Service |
SUBJECT/OBJET: |
ADDITIONAL FUNDING REQUIREMENT FOR REPLACEMENT OF EMERGENCY GENERATORS AT 474 ELGIN STREET
|
That the Ottawa Police Services Board approve an increase to the OPS Elgin Emergency Generator Project #904137 of $1,150,000 by way of a budget transfer from OPS Facilities Lifecycle Project #905486.
As part of the 2010 budget process, the Board approved a budget of $2,500,000 to replace the emergency generator at OPS Headquarters at 474 Elgin Street. This amount was based on a consultant’s best estimates using information available at that time.
An increase of $1,150,000 is now required for this project following the completion of detailed engineering studies and a clearer definition of the project’s scope after tendering of the major components.
DISCUSSION
The existing emergency backup power system for the OPS Headquarters at 474 Elgin Street was installed over 30 years ago. The existing main generator (650kW) is original to the building and only provides emergency power to 70% of the building’s requirements. Shortly after the building opened, a power failure, coupled with a failure of this main generator, left the entire facility without power — including the OPS Communications/911 Centre. As a result, a second smaller generator (125kW) was subsequently added to provide secondary backup power to the Communications/911 Centre and related support systems. Presently, both generators have reached the end of their useful life and are unable to support both current and future needs of this facility.
To further supplement these systems in the event of a power failure, an Uninterrupted Power Supply (UPS) system was added during the Year 2000 cut-over (Y2K) to ensure that critical areas of the building such as OPS Communications/911, Dispatch, City Radio and OPS Computer and IT Systems could remain operational in the event that a switch to backup power was necessary. This UPS is now at its maximum capacity and has reached the end of its useful life. Further expansion is impractical from both a design and cost basis and system reliability is at a critical point.
Expansion of Project Scope
In 2009, several investigations of the electrical systems at 474 Elgin Street were conducted due to operator safety issues encountered by City of Ottawa staff responsible for operating and testing the emergency power systems. The investigations sought to accomplish the following:
Following the completion of the investigations, staff concluded that combining the various smaller initiatives into a single, comprehensive solution would generate cost efficiencies while minimizing down time.
The project scope was therefore expanded and now includes:
Staff took delivery of the two new generators during March 2011. The project has now advanced to the construction tendering stage and the result of a competitive tender has determined that an additional $1,150,000 will be required to fund this project to its completion.
Cost Escalation
In addition to the impact of an expanded project scope, cost pressures from the original budget estimates are due to the following:
Details of the cost estimates to date are shown in below in Table 1:
Table 1
Cost Estimates for Emergency Generators
Description |
Amount |
Type |
Additional Consultant fees |
$ 42,445 |
Estimate |
Generator Purchase |
$ 766,834 |
Actual |
CCN #1 tank size changes to meet TSSA requirements, removal of canopy from between the 2 exiting units, additional storage due to project delays |
$ 31,250 |
Actual |
CCN #2 additional storage of generators until Board approves funds. |
$ 10,000 |
Estimate |
Building Permit |
$ 12,000 |
Estimate |
Tender Price |
$ 2,460,000 |
Tender |
Contingency (10% of tender) |
$ 246,000 |
Estimate |
Sub Total |
$ 3,568,529 |
|
Taxes (1.76%) |
$ 62,806 |
Estimate |
Estimated Total |
$ 3,631,335 |
|
Public consultation is not required.
A budget transfer in the amount of $1,150,000 is being requested to supplement the Elgin Generator Project. The budget base to be transferred has been identified within capital project # 905486 –“2011 Facility Lifecycle”.
Table 2
Capital Project Transfer
Elgin Emergency Generator Project # 904137
|
|
2011 Facility Lifecycle Project #905486 |
||
|
|
|
|
|
Approved Budget |
$2,500,000 |
|
Approved Budget |
$2,039,000 |
Budget Transfer Requested |
1,150,000 |
|
Budget Transfer Requested |
(1,150,000) |
Revised Budget |
3,650,000 |
|
Revised Budget |
889,000 |
Spent/Committed |
(780,400) |
|
Spent/Committed |
0 |
Available |
2,869,600 |
|
Available |
889,000 |
|
|
|
|
|
Table 3
Delayed Facility Lifecycle Projects
Project |
Amount |
Comments |
Elgin - Membrane and Topping Replacement - Phase 1 of 4 |
$ 620,000 |
Project prep in 2011 will use $5,000 of $625,000 budget. Project cannot proceed in 2011 due to site interference with Generator Project |
Elgin - Replace UPS Battery |
$ 60,000 |
Project eliminated due to scope inclusion in Generator Project |
Elgin - Replace Lobby Ventilation AHU |
$ 25,000 |
Project prep in 2011 will use $5,000 of $30,000 budget. Project delayed to 2012. |
Elgin - Replace Range Supply AHU |
$ 95,000 |
Project prep in 2011 will use $5,000 of $100,000 budget. Project delayed to 2012. |
Elgin - Garage Supply and Exhaust Fan Rebuild |
$ 50,000 |
Project delayed to 2012. |
10th Line - Lobby floor tile replacement |
$ 30,000 |
Project deferred to 2012. |
Greenbank - Modernize Existing Elevator & Cabs |
$ 120,000 |
Project can be delayed for maximum two years. |
Greenbank - Exterior Caulking
|
$ 150,000 |
Caulking scope reduced as 2010 temporary remediation work has performed better than anticipated. |
|
$1,150,000 |
|
CONCLUSION
The upgrade to the Emergency Generators at 474 Elgin Street is an essential requirement to ensure that, in the event of an electrical power outage, the OPS Communications/911 Centre, OPS computer and IT systems and City of Ottawa Radio Networks can continue to operate on an uninterrupted basis. With Board approval of this request, the Elgin Emergency Generator Project will be able to be awarded immediately with project completion anticipated by the fall of 2011.
(original signed by)
Vern White
Chief of Police