19 FAIRMONT AVENUE FACILITY – REQUEST FOR BUDGET INCREASE |
That the Ottawa Police Services Board approve an increase in the capital budget for the leased premises located at 19 Fairmont Avenue by $490,000 (excluding taxes) to allow completion of interior renovations.
At the Ottawa Police Service Board meeting on 19 January 2009, the Board approved a lease for office space at 19 Fairmont Avenue for ten (10) years commencing 1 November 2009. Additionally, the Board delegated authority to the Chief to complete all required tenant fit-up, project management, and furniture and equipment acquisition in an amount not to exceed $1,375,000.
As at 30 June 2010, a total of $786,781 had been spent or committed on major items such as design consultants, construction of the 3rd floor and installation of the IT/ Telecom and security system infrastructure. These expenditures and commitments, as compared to budget, are identified in Table 1.
Table 1
Summary of Expenditures to 30 June 2010
Budget Category |
Approved Budget |
Spent / Committed |
Balance Remaining |
Tenant Fit-Up |
$575,000 |
$395,447 |
$179,553 |
IT/Telecom/Security equipment |
650,000 |
308,826 |
341,174 |
Office Furniture |
150,000 |
82,508 |
67,492 |
Total |
$1,375,000 |
$786,781 |
$588,219 |
Table 2 provides a revised budget estimate for work at 19 Fairmont which identifies a need for additional funding in the amount of $490,000 to allow for project completion.
Table 2
Revised Budget
Budget Category |
Approved Budget |
Revised Budget |
Additional Funding Requested |
Tenant Fit-Up |
$575,000 |
$1,282,000 |
$707,000 |
IT/Telecom/Security equipment |
650,000 |
350,000 |
(300,000) |
Office Furniture |
150,000 |
233,000 |
83,000 |
Total |
$1,375,000 |
$1,865,000 |
$490,000 |
Tenant Fit-Up
The original budget of $575,000 for design and construction of the space has proven to be insufficient. This amount included both construction costs, as well as design and project administration.
When estimates for the original budget were compiled, decisions as to which sections would move to the Fairmont facility had not been finalized. Following internal discussions and consultations, the following sections are now identified for relocation to Fairmont:
Quality Assurance and HR are already operating out of the Fairmont location. The other sections are scheduled to be relocated there by the end of 2010.
These sections are selected based on a review of numerous factors such as interaction with other OPS sections and functionality if allowed to work independently. Groups requiring minimal infrastructure relocation, minimal storage of operationally sensitive information and police equipment were also deciding factors. Based on these and other considerations, the groups noted above were deemed to be the most easily relocated away from 474 Elgin Street when compared to other sections in the OPS.
Design planning to accommodate these identified tenants yielded tenant fit-up work which was not specifically included in the original budget estimates. The space required the removal of old cooling equipment, the installation of baseboard heaters and the installation of partition walls and doors. The Professional Standards Section requires interview and video monitoring rooms which are subject to strict sound transmission requirements.
Resourcing & Development requires meeting and conference rooms for conducting interviews and general work meetings. Additionally, lockers areas are required for sworn members attached to these sections. A weapon proving chamber is required to ensure the safe storage of firearms. The parking areas have insufficient lighting and signage which has added to the budget shortfall.
Under the terms of the Lease, the Landlord secured competitive tenders on the majority of the aspects of the preliminary layout in November 2009. Construction prices received as a result of the tenders increased approximately 10% since the original budget was approved by the Board. Whereas these original tender results were received in late 2009, current prices indicate further increases of 4% to 10% in virtually all categories.
Additional design costs have been incurred in ensuring optimal use of the space. Under the Lease, the Landlord provides Project Management services calculated at 15% of the cost of the subcontracted work as well as a 5% administration fee. The OPS engaged Trefoil Inc. to coordinate the additional aspect of the project for items such as move management, environmental reviews, coordinating security and lighting requirements for the parking areas as well as coordinating the installation of the OPS telecom and the OPS security infrastructure. Both of these design and project management items applied upward pressure on the overall project costs.
IT/Telecom/Security Equipment
Revised budget estimates for such equipment as VoIP telephones, data switches and routers, computer workstations, and ISMS security systems are $300,000 lower than the original estimate. The primary reason for this difference is that existing computers from Elgin were relocated to Fairmont rather than acquiring new computers. There was also existing security infrastructure made available by the Landlord to the OPS which has reduced the security infrastructure costs.
Office furniture
In order to facilitate the required tenant fit-up, all of the existing furniture had to be removed and cleaned. The furniture will be reconfigured as necessary to reflect the OPS standards as much as possible. An increase to the budget of $83,000 is due to additional furniture required to accommodate the higher number of staff moving to Fairmont than originally estimated. As well, specific furniture requirements for interview and meeting rooms were not originally included in the estimates.
Evaluation of Alternative Options
In efforts to keep the costs within the original budget estimate, staff considered many factors and evaluated various options.
Public consultation is not required.
The Police Service Board has approved a budget of $1.375 million, in Capital Project 904531, for the refit of the leased premises located at 19 Fairmont. This budget was based on a Class D estimate in early 2009. According to industry standards, the range of confidence for this category of estimate is considered to be +/- 25%, equivalent to a budget variance of $343,750. An increase to the project budget, in the amount of $490,000, is being requested to allow for the completion of the refit project.
Funding for this increase has been identified from within existing Facilities Capital Projects. Staff recommends that the budget increase be funded by a transfer from existing capital projects, as noted in Table 3.
Table 3
Transfer of Funds from Existing Capital Projects
Project |
Budget |
Spent / Committed |
Balance |
This Request |
Available |
|
|
|
|
|
|
903132 – Accommodation Master Plan |
$ 1,358,000 |
$1,318,835 |
$ 39,165 |
$ 12,000 |
$27,165 |
904129 – 2007 Facilities Minor Capital |
300,000 |
263,734 |
36,266 |
25,000 |
11,266 |
904522 - 2008 Facilities Minor Capital |
500,000 |
383,202 |
116,798 |
110,000 |
6,798 |
903660 – Facility Strategic Plan |
150,000 |
52,442 |
97,558 |
95,000 |
2,558 |
903800 – BASC 2006/2007 |
1,300,000 |
1,160,108 |
139,892 |
125,000 |
14,892 |
905089 – 2009 Security Upgrades |
240,000 |
155,738 |
84,262 |
84,000 |
262 |
904134 - 2010 Security Upgrades |
500,000 |
34,663 |
465,337 |
39,000 |
426,337 |
|
|
|
|
|
|
Total |
$ 4,348,000 |
$3,368,722 |
$ 979,278 |
$ 490,000 |
$ 489,278 |
With Board approval of the funding sources listed above, a budget adjustment will be requested to consolidate the funding identified for one time fit-up costs within Capital project 904531 – “Operational Fit-up 2008”.
The leased premise at 19 Fairmont Avenue is an integral part of the short and mid-term term space requirements for the OPS. Ensuring that the space is functional, adequate and secure requires additional funding to successfully complete the project. The space has been designed to meet functional requirements of the Sections identified for relocation.
(original signed by)
Vern White
Chief of Police