APPENDIX E
PLANNING COMMITTEE
PERFORMANCE MEASURES
STRATEGIC PRIORITY: TRANSPORTATION & MOBILITY
Strategic Objective Name & Description |
Performance Measure(s) |
TM2
- Maximize density in and around transit stations |
TM2-A: Complete 38% of the Transit-Oriented development studies by the end of 2012, 75% by the end of 2013 and 100% by the end of 2014. |
Strategic Initiative Name |
Performance Measure(s) |
Strategic Objective Supported |
7 - Community Planning Studies in Support of the Light Rail Transit Project |
7-A: Complete the projects outlined in the Transit-Oriented development studies on time and budget. |
TM2 |
STRATEGIC PRIORITY: ENVIRONMENTAL STEWARDSHIP
Strategic Initiative Name |
Performance Measure(s) |
Strategic Objective Supported |
16- Subwatershed Studies and Environmental Management |
16-A: Complete 100% of the Subwatershed Plans and Environmental Management Plan deliverables in 2012, 2013 and 2014. 16-B: Increase or maintain the percentage of watercourses meeting recommended vegetated buffer targets by 2014. |
ES1 |
22- Source Water Protection Plan |
22-A: Increase the percentage of area within wellhead protection areas and intake protection zones designated and zoned for Source Water Protection Land Uses to 75% by the end of 2013 and 100% by the end of 2014. 22-B: Increase the percentage of properties requiring Source Water Protection Risk Management Plans that have approved plans to 75% by the end of 2013 and 100% by the end of 2014. |
ES2 |
28 - Green Building Promotion Program |
28-A: Increase the number of approved planning applications that have used the green checklist and made an improvement with a positive environmental benefit by 20% by the end of 2014 (over established baseline from pilot/first year). |
ES3 |
STRATEGIC PRIORITY: HEALTHY AND CARING COMMUNITIES
Strategic Initiative Name |
Performance Measure(s) |
Strategic Objective Supported |
41- Housing and Homelessness Investment Plan |
41-C: Start 90 new affordable housing units in 2012, 60 units in 2013 and 20 units in 2014. |
HC3 |
STRATEGIC PRIORITY: SERVICE EXCELLENCE
Strategic Initiative Name |
Performance Measure(s) |
Strategic Objective Supported |
49 - Development Review Process Continuous Improvement |
49-A: Increase the percentage of planning applications that are decided "On-time" to 60% by the end of 2011, 65% by the end of 2012, 75% by the end of 2013 and 80% by the end of 2014. |
SE2 |
STRATEGIC PRIORITY: GOVERNANCE, PLANNING & DECISION-MAKING
Strategic Initiative Name |
Performance Measure(s) |
Strategic Objective Supported |
65 - Review of the Official Plan, Transportation Master Plan and Infrastructure Master Plan |
65-A: Complete 20% of the Official Plan Review deliverables by the end of 2012, 80% by the end of 2013 and 100% by the end of 2014. |
GP3 |
STRATEGIC PRIORITY: FINANCIAL RESPONSIBILITY
Strategic Initiative Name |
Performance Measure(s) |
Strategic Objective Supported |
75 - Development Charge Review |
75-A: Complete 50% of the Development Charge Review deliverables by Q4 2012 and 100% by Q3 2014. |
FS2 |
RECOMMENDED AMENDMENTS TO THE TERM OF COUNCIL PRIORITIES
The table below contains recommended amendments to the Term of Council Priorities as identified through consultation with the Chairs and Vice-Chairs of the Transit Commission and Standing Committee’s of Council.
Oversight |
Strategic Priority Affected |
Nature of Amendment |
Recommended Amendment |
PLC |
Financial Responsibility |
Edit the name of strategic initiative Mid-term Development Charge Review
|
Change from: Mid-term Development Charge Review To: Development Charge Review
|