7.             FRONT-ENDING AGREEMENT - FRESHWATER PARKETTE IN HALF MOON BAY

 

ENTENTE INITIALE – PARC DE POCHE FRESHWATER À HALF MOON BAY

 

 

 

Committee recommendationS

 

 

That Council:

 

1.                  Authorize the City to enter into a Front-Ending Agreement with Mattamy (Half Moon Bay) Limited to enable the design and construction of Freshwater Parkette on Freshwater Way, Block 169 on 4M-1428 in the Half Moon Bay Community, in accordance with the Council approved Park and Trail Front‑Ending Policy in Document 1 and the Front-Ending Agreement Principles set out in Document 2 to the satisfaction of the Deputy City Manager, Planning and Infrastructure and the City Clerk and Solicitor;

 

2.                  Authorize the expenditure of $83,854, plus applicable taxes, for reimbursement of design and construction costs for Freshwater Parkette, as detailed in this report, subject to the execution of a Front Ending Agreement, with the reimbursement to occur in 2015; and

 

3.                  Authorize that the growth portion of the works be funded from development charges and the non-growth portion be funded from the City-Wide Cash-in-Lieu of Parkland Reserve Fund.

 

 

RecommandationS DU Comité

 

Que le Conseil :

 

1.                  Autorise la Ville à conclure une entente initiale avec la firme Mattamy (Half Moon Bay) Limited en vue de permettre la conception et la construction du parc de poche Freshwater sur la voie Freshwater, îlot 169 sur le plan 4M-1428, dans le lotissement Half Moon Bay, conformément à la politique initiale sur les parcs et les sentiers approuvée par le Conseil et figurant dans le document 1 et les principes d’entente initiale établis dans le document 2, à la satisfaction du directeur municipal adjoint, Urbanisme et Gestion de la croissance, et du greffier municipal et chef du contentieux;

 

2.                  Autorise le versement de 83 854 $, taxes en sus, pour le remboursement des coûts de conception et de construction du parc de poche Freshwater, tel qu’exposé en détail dans le rapport, sous réserve de l’exécution d’une entente initiale, le remboursement suivant devant être effectué en 2015; et

 

3.                  Autorise le financement du volet croissance des travaux à partir des redevances d’aménagement, et celui de la partie des travaux non liée à la croissance à l’aide du fonds de réserve municipal provenant du règlement financier des frais relatifs aux terrains à vocation de parc.

 

 

 

Documentation

 

1.                  Deputy City Manager's report, Planning and Infrastructure, dated 28 February 2012 (ACS2012-PAI-PGM-0073).

 


Report to/Rapport au :

 

Planning Committee

Comité de l’urbanisme

and Council / et au Conseil

 

28 February 2012 / le 28 février 2012

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice municipale adjointe, Planning and Infrastructure/Urbanisme et Infrastructure

 

Contact Person/Personne ressource : Derrick Moodie, A/Manager - Development Review - Suburban Services

Planning and Growth Management/Urbanisme et Gestion de la croissance

(613) 580-2424 x 15134, derrick.moodie@ottawa.ca

 

Ward: Barrhaven (3)

Ref N°: ACS2012-PAI-PGM-0073

 

SUBJECT:

Front-ending Agreement - Freshwater parkette in Half Moon bay

 

 

OBJET :

entente initiale – parc de poche Freshwater à Half Moon bay

 

 

REPORT RECOMMENDATIONS

 

That Planning Committee recommend Council:

 

1.                  Authorize the City to enter into a Front-Ending Agreement with Mattamy (Half Moon Bay) Limited to enable the design and construction of Freshwater Parkette on Freshwater Way, Block 169 on 4M-1428 in the Half Moon Bay Community, in accordance with the Council approved Park and Trail Front‑Ending Policy in Document 1 and the Front-Ending Agreement Principles set out in Document 2 to the satisfaction of the Deputy City Manager, Planning and Infrastructure and the City Clerk and Solicitor;

 

2.                  Authorize the expenditure of $83,854, plus applicable taxes, for reimbursement of design and construction costs for Freshwater Parkette, as detailed in this report, subject to the execution of a Front Ending Agreement, with the reimbursement to occur in 2015; and

 

3.                  Authorize that the growth portion of the works be funded from development charges and the non-growth portion be funded from the City-Wide Cash-in-Lieu of Parkland Reserve Fund.

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité de l’urbanisme recommande ce qui suit au Conseil :

 

1.                  Autoriser la Ville à conclure une entente initiale avec la firme Mattamy (Half Moon Bay) Limited en vue de permettre la conception et la construction du parc de poche Freshwater sur la voie Freshwater, îlot 169 sur le plan 4M-1428, dans le lotissement Half Moon Bay, conformément à la politique initiale sur les parcs et les sentiers approuvée par le Conseil et figurant dans le document 1 et les principes d’entente initiale établis dans le document 2, à la satisfaction du directeur municipal adjoint, Urbanisme et Gestion de la croissance, et du greffier municipal et chef du contentieux;

 

2.                  Autoriser le versement de 83 854 $, taxes en sus, pour le remboursement des coûts de conception et de construction du parc de poche Freshwater, tel qu’exposé en détail dans le rapport, sous réserve de l’exécution d’une entente initiale, le remboursement suivant devant être effectué en 2015; et

 

3.                  Autoriser le financement du volet croissance des travaux à partir des redevances d’aménagement, et celui de la partie des travaux non liée à la croissance à l’aide du fonds de réserve municipal provenant du règlement financier des frais relatifs aux terrains à vocation de parc.

 

 

BACKGROUND

 

Freshwater Parkette is located on Freshwater Way in Mattamy’s Half Moon Bay Phase 6 development, as shown on Document 3. The Half Moon Bay subdivision was registered in March 2011 with Phase 6 being constructed in 2011-2012. This phase of Half Moon Bay is near completion. Mattamy has the option to front-end the development of this .199 parkette as outlined in the subdivision agreement conditions and as outlined in the Park and Trail Front‑Ending Policy (Document1).

 

DISCUSSION

 

The developer is front-ending the design and construction of the parkette, and the agreement will tie the developer to implementing specific design plans to the City’s specifications.  The agreement will outline the specific documentation that will be required such as proof of expenditures, the specific upset limit for the project, requirements for inspections and reimbursements, and repayment timelines and parameters for the project.

 

Freshwater Parkette was scheduled to be constructed in 2015 under the current 10-year budget forecast. Mattamy has made a request to construct the parkette in 2012. Repayment will occur in 2015.  Phase 6 in Half Moon Bay is close to build-out and the developer wishes to ensure a fully operational park is available to home owners upon completion of the neighbourhood.

The completion of Freshwater Parkette will advance the delivery and use of the parkette by three years when compared to City’s standard construction schedule, which is based on the availability of development charges to fund park construction budgets.

The annual operating budget is estimated to be $8,000 commencing in 2013.

 

CONSULTATION

 

The Ward Councillor and the community have been consulted on the design of the parkette.

 

COMMENTS BY THE WARD COUNCILLOR

 

Councillor Harder is aware of this report.

 

LEGAL IMPLICATIONS

 

There are no legal implications associated with this report.

 

RISK MANAGEMENT IMPLICATIONS

 

There are no risk implications.

 

CITY STRATEGIC PLAN

 

Bringing Freshwater Parkette forward is in keeping with several City planning objectives:

 

A)    To manage growth and create liveable communities by ensuring that the community facilities are built concurrently with new housing and infrastructure development.

B)    To deliver parks in a more timely manner that keeps pace with development, as described in the new Park and Trail Front-Ending Policy approved by Council, 25th January, 2012.

 

For all front-ended park and trail projects, the agreement will outline the specific documentation that will be required as proof of expenditures, the specific upset limit for a project, requirements for inspections and reimbursements, and repayment timeline and parameters.

 

TECHNICAL IMPLICATIONS

 

There are no direct technical implications associated with this report.

 

FINANCIAL IMPLICATIONS

 

Reimbursement of design and construction costs for Freshwater Parkette is outlined in the table below.  The up-set limit is based on the current rate of development charges for parks. The budget is based on the calculation of $451,500 per hectare. The annual operating impact is estimated at $8,000 beginning in 2013.


 

Development Charge Item

Up-Set Limit

Criteria for Repayment

Design and Construction of

Freshwater Parkette

$ 83,854

plus applicable taxes

Repayment based on actual cost of the park, to the upset limit

 

ACCESSIBILITY IMPLICATIONS

 

The park design will apply the accessibility lens.

 

SUPPORTING DOCUMENTATION

 

Document 1    Park and Trail Front-Ending Policy

Document 2    Framework for the Agreement- Freshwater Parkette

Document 3    Location Map - Freshwater Park

 

DISPOSITION

 

Legal Services will prepare the final form of the agreement in consultation with the Planning and Growth Management Department, Infrastructure Services and Community Sustainability Branch.

 

PARK AND TRAIL FRONT-ENDING POLICY                                              DOCUMENT 1

 

POLITIQUE INITIALE RELATIVE AUX PARCS ET AUX SENTIERS

ACS2011-ICS-PGM-0040  CITY WIDE/À L'ÉCHELLE DE LA VILLE

 

Front-Ending Agreements for parks and trails are requested by developers who wish to have specific new growth-related park and trail works in place in advance of the City’s capital project funding for emplacement of these same works.  Developers may voluntarily agree to finance the works at the “front end” and recover their costs from the City at a later date.  The following conditions must be met for the City to enter into a Front-Ending Agreement for parks and trails:

 

1.                  All Front-Ending Agreements with the City will be for new park and trail growth-related capital works that have been included in the City's Development Charges Background Study. A park Front-Ending Agreement is only available for parkettes and neighbourhood parks.

 

2.                  The contract for front-ended works shall be awarded by the front-ender in accordance with the City’s Purchasing Policy of a competitive procurement process and subject to the review and satisfaction of the General Manager, Planning and Growth Management Department.  Where the front-ender does not award the work in accordance with the City’s purchasing policy, they must demonstrate that competitive pricing has been obtained, through analysis of an independent, qualified professional, to the satisfaction of the General Manager, Planning and Growth Management Department.  The contract for the work must be made available to the City to provide to the public.

 

3.                  A lump sum payment, both the development charge portion and the City portion, will be paid back to the front-ender in the year the project is identifed in the City's Development Charges Background Study based on the 10-year capital program at the time the Front‑Ending Agreement is approved.

 

4.                  The capital project upset limit for design and construction, project management and contingency shall be established in the Council report approving the Front-Ending Agreement in accordance with the Development Charge By-law and shall be incorporated into the agreement.  Any expenditures incurred above and beyond the amount approved in the agreement cannot be claimed and must be incurred by the front‑ender.

 

5.                  Where a front-ender is eligible for reimbursement, documentation is required to support the reimbursement in accordance with the City’s Purchasing Policy.  The Front-Ending Agreement shall identify what documentation and at which stage it shall be required.

 

6.                  A report to Council is required to authorize staff to enter into a Front-Ending Agreement.  The recommendation will include the financial commitment of the City and specify the funding source(s) and the project timeline.  The financial comment in the report will specify the timelines for repayment, an operating budget impact and an estimate of the year in which the operating budget impact will begin. 

The report will also specify that the letter of credit for the registered subdivision in which the park is situated with not be reduced beyond what is required for the works associated with the subdivision plus the cost of the front-ended works until such time as the front-ended works are accepted by the City.  A capital project will be established upon Council approval to enter into the Front-Ending Agreement.

 

FRAMEWORK FOR THE AGREEMENT- FRESHWATER PARKETTE  Document 2

 

FRAMEWORK FOR AGREEMENT – MATTAMY (Half Moon Bay) LIMITED –

 

Freshwater Parkette

 

Parkette Amenities

Mattamy (Half Moon Bay) Limited will construct Freshwater Park, a 0.199 ha parkette located at on Freshwater Way, to the satisfaction of the General Manager of the Planning and Growth Management Department. Parkette amenities include:

 

Park Construction

Mattamy (Half Moon Bay) Limited through its agents, contractors and assigns will construct Freshwater  Parkette to the following standards, and confirm that construction meets City requirements:

 

Costs

 

Schedule

 

Repayment

 

Parkette Design

 

Parkette Maintenance