6.             FRONT-ENDING TWO NEIGHBOURHOOD PARKS IN MATTAMY SUMMERSIDE

PHASE I AND II SUBDIVISIONS

 

ENTENTE INITIALE VISANT DEUX PARCS DE QUARTIER DANS LES LOTISSEMENTS MATTAMY SUMMERSIDE DE PHASES I ET II

 

 

 

Committee recommendationS

 

 

That Council :

 

1.                  Authorize the City to enter into a Front-Ending Agreement with Mattamy (Tenth Line) Limited to enable the design and construction of two neighbourhood parks – Summerside Phases I and II Parks – in accordance with the Council approved Park and Trail Front-Ending Policy contained in  Document 4 and the Front Ending Agreement Principles set out in Document 3 to the satisfaction of the Planning and Infrastructure Deputy City Manager and the City Clerk and Solicitor;

 

2.                  Authorize the expenditure of $539,361 plus applicable taxes for reimbursement of design and construction costs for Summerside Phases I and II Parks, as detailed in this report, subject to the execution of a Front Ending Agreement for each park with the reimbursement to occur in two instalments: $223,329 plus applicable taxes in 2015 for the Phase I Park; and $316,032 plus applicable taxes in 2017 for the Phase II Park; and

 

3.                  Authorize that the growth portion of the works be funded from development charges and the non-growth portion be funded from the City-Wide Cash-in-Lieu of Parkland Reserve Fund.

 

 

RecommandationS DU Comité

 

Que le Conseil :

 

1.                  Autorise la Ville à conclure une entente initiale avec la firme Mattamy (Tenth Line) Limited, afin de permettre la conception et la construction de deux parcs de quartier : le parc Summerside Phase I et II, conformément à la politique initiale sur les parcs et les sentiers approuvée par le Conseil et figurant dans le document 4, et les principes d’entente initiale établis dans le document 3, à la satisfaction du directeur municipal adjoint, Urbanisme et Infrastructure, et du greffier municipal et chef du contentieux;

 

2.                  Autorise le versement de $539,361 $, taxes en sus, pour le remboursement des coûts de conception et de construction des parcs Summerside Phase I et Phase II, tel qu’exposé en détail dans le rapport, sous réserve de l’exécution d’une entente initiale pour chaque parc. Le remboursement doit être effectué en deux versements : $223,329 $, taxes en sus, en 2015 pour le parc de la Phase I, et $316,032 $, taxes en sus, en 2017 pour le parc de la Phase II; et

 

3.                  Autorise le financement du volet croissance des travaux à partir des redevances d’aménagement, et celui de la partie des travaux non liée à la croissance à l’aide du fonds de réserve municipal provenant du règlement financier des frais relatifs aux terrains à vocation de parc.

 

 

 

 

 

Documentation

 

1.                  Deputy City Manager's report, Planning and Infrastructure, dated 10 February 2012 (ACS2012-PAI-PGM-0048).

 


 

Report to/Rapport au :

 

Planning Committee

Comité de l’urbanisme

and Council / et au Conseil

 

10 February 2012 / le 10 février 2012

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/Directrice municipale adjointe, Planning and Infrastructure/Urbanisme et Infrastructure

 

Contact Person/Personne ressource : Derrick Moodie, A/Manager - Development Review - Suburban Services

Planning and Growth Management/Urbanisme et Gestion de la croissance

(613) 580-2424 x 15134, derrick.moodie@ottawa.ca

 

Cumberland (19)

Ref N°: ACS2012-PAI-PGM-0048

 

 

SUBJECT:

FRONT-ENDING TWO NEIGHBOURHOOD PARKS IN MATTAMY SUMMERSIDE PHASE I AND II SUBDIVISIONS

 

 

OBJET :

ENTENTE INITIALE VISANT DEUX PARCS DE QUARTIER DANS LES LOTISSEMENTS MATTAMY SUMMERSIDE DE PHASES I ET II

 

 

REPORT RECOMMENDATIONS

 

That Planning Committee recommends that Council:

 

1.                  Authorize the City to enter into a Front-Ending Agreement with Mattamy (Tenth Line) Limited to enable the design and construction of two neighbourhood parks – Summerside Phases I and II Parks – in accordance with the Council approved Park and Trail Front-Ending Policy contained in  Document 4 and the Front Ending Agreement Principles set out in Document 3 to the satisfaction of the ISCS Deputy City Manager and the City Clerk and Solicitor;

 

2.                  Authorize the expenditure of $539,361 plus applicable taxes for reimbursement of design and construction costs for Summerside Phases I and II Parks, as detailed in this report, subject to the execution of a Front Ending Agreement for each park with the reimbursement to occur in two instalments: $223,329 plus applicable taxes in 2015 for the Phase I Park; and $316,032 plus applicable taxes in 2017 for the Phase II Park; and

 

3.                  Authorize that the growth portion of the works be funded from development charges and the non-growth portion be funded from the City-Wide Cash-in-Lieu of Parkland Reserve Fund.

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité de l’urbanisme recommande ce qui suit au Conseil :

 

1.                  Autoriser la Ville à conclure une entente initiale avec la firme Mattamy (Tenth Line) Limited, afin de permettre la conception et la construction de deux parcs de quartier : le parc Summerside Phase I à l’angle de Portobello et Sunshine, et le parc Summerside Phase II à l’angle de Serra et Solstice, conformément à la politique initiale sur les parcs et les sentiers approuvée par le Conseil et figurant dans le document 4, et les principes d’entente initiale établis dans le document 3, à la satisfaction du directeur municipal adjoint, Urbanisme et Gestion de la croissance, et du greffier municipal et chef du contentieux;

 

2.                  Autoriser le versement de 539 690 $, taxes en sus, pour le remboursement des coûts de conception et de construction des parcs Summerside Phase I et Phase II, tel qu’exposé en détail dans le rapport, sous réserve de l’exécution d’une entente initiale pour chaque parc. Le remboursement doit être effectué en deux versements : 223 465 $, taxes en sus, en 2015 pour le parc de la Phase I, et 316 225 $, taxes en sus, en 2017 pour le parc de la Phase II; et

 

3.                  Autoriser le financement du volet croissance des travaux à partir des redevances d’aménagement, et celui de la partie des travaux non liée à la croissance à l’aide du fonds de réserve municipal provenant du règlement financier des frais relatifs aux terrains à vocation de parc.

 

 

BACKGROUND

 

The subdivision agreement for Summerside Phase I was registered in August, 2011.  The draft plan of subdivision for Summerside Phase II was approved in September and registration is anticipated soon.  Both agreements contain the standard condition giving an option for the developer to front-end the park, which is in accordance with City Policy and the Strategic Plan.  Mattamy has requested to front-end the parks so that they can be built concurrently with the subdivisions.  The locations are shown in Documents 1 and 2.

 

DISCUSSION

 

Summerside Phase I Park is a 0.53 hectare park that will serve primarily its immediate neighbourhood.  Under the current 10-year park budget forecast, this park is scheduled for funding in 2015.  Summerside Phase II Park is a 0.75 hectare park that will serve primarily its immediate neighbourhood.  Under the 10-year park budget forecast, this park is scheduled for funding in 2017.  Mattamy has requested that they front-end the design and construction of both parks so that they can be delivered to their communities in a shorter time frame than through typical City-build practice. 

Front-ending will be a benefit to the community as the parks will be completed during the early stages of subdivision development, and will be available for use by early occupants.  There will be less disruption to the new community as park construction will occur concurrently with subdivision construction. 

 

Facilities in the two parks will include a variety of park amenities such as playgrounds, shade structure, pathways, tree planting, benches, potentially a small puddle rink, splashpad and mini-soccer field.

 

The City’s Front-ending policy was approved in February 2011 providing an opportunity for the City to bring forward construction of parks following a request by the developer.

 

RURAL IMPLICATIONS

 

There are no implications.

 

CONSULTATION

 

As there are no existing surrounding communities at this stage of development, there was no ability to hold public consultation meetings.  However, consultation will occur with City staff, the Councillor and the Community Association during the concept design phase of the parks.

 

COMMENTS BY THE WARD COUNCILLOR

 

Councillor Stephen Blais is aware of this report.

 

LEGAL IMPLICATIONS

 

There are no legal implications associated with this report.

 

RISK MANAGEMENT IMPLICATIONS

 

There are no risk implications.

 

CITY STRATEGIC PLAN

 

Bringing forward Summerside Phase I and II Parks is in line with:

 

·         Strategic Priority HC2: Healthy and Caring Community: Provide accessible, inclusive and quality parks, recreation services and urban spaces for leisure, arts and heritage that respond to demographic trends in population and activity; and

·         The intent of the new Parks Front-Ending policy approved by Council in 2011 to provide parks in a timelier manner which keeps pace with development.

 

TECHNOLOGY IMPLICATIONS

 

There are no direct technical implications associated with this report.

 

FINANCIAL IMPLICATIONS

 

Reimbursement of design and construction costs for Summerside Phases I and II Parks are outlined in the table below.

Up-set limits are based on the current rate of development charges for parks. The annual operating impact for Summerside Phase I park is estimated at $15,000 beginning in 2014; and $25,000 for Summerside Phase II park $25,000 beginning in 2015.

 

Development Charge Item

Up-Set Limit

Criteria for Repayment

Design and Construction of Summerside Phase I Park

$223,329

plus applicable taxes

Repayment based on actual cost of park to an upset limit of $223,329 + applicable taxes, on acceptance of the park and no sooner than 2015.

Design and Construction of Summerside Phase II Park

$316,032

plus applicable taxes

Repayment based on actual cost of park to an upset limit of $316,032 + tax applicable taxes, on acceptance of the park and no sooner than 2017.

Total

$539,361

plus applicable taxes

 

 

ACCESSIBILITY IMPLICATIONS

 

The park designs will apply the accessibility lens.

 

SUPPORTING DOCUMENTATION

 

Document 1    Location of Summerside Phase I Park

Document 2    Location of Summerside Phase II Park

Document 3    Front-Ending Agreement Principles

Document 4    Park and Trail Front-Ending Policy

 

DISPOSITION

 

Legal Services will prepare the final form of the agreement in consultation with the Planning and Growth Management Department, Infrastructure Services and Community Sustainability Branch.

 

Location of Summerside Phase I ParkText Box:                                              DOCUMENT 1

 


 

Location of Summerside Phase II Park                                           DOCUMENT 2

 

Phase 2

FRONT-ENDING AGREEMENT PRINCIPLES                                              DOCUMENT 3

 

 

1.      The parks shall be designed and constructed in accordance with City planning priorities, to City and all applicable regulatory standards and the City’s purchasing policy of a competitive procurement process.

 

2.      Reimbursement by the City to Mattamy (Tenth Line) Limited will be based on actual park cost, and will be in two instalments to an upset limit of $223,465 in 2015 and $316,225 in 2017.

 

3.      Mattamy (Tenth Line) Limited shall agree to all terms and conditions for design, construction and maintenance of the parks, in accordance with City and regulatory standards, to the satisfaction of the General Manager Planning and Growth Management and the General Manager, Infrastructure Services.

 

4.      All operating and maintenance costs associated with the park property will be the responsibility of Mattamy (Tenth Line) Limited until take-over by the City, to the satisfaction of the General Manager, Planning and Growth Management.

 

5.      Park construction is to commence no later than September 1, 2012 for Summerside Phase I Park and no later than 12 months following registration of the subdivision agreement for Summerside Phase II Park.

 

6.      No repayment may occur until park construction is complete and to the satisfaction of the General Manager Planning and Growth Management and the General Manager, Infrastructure Services.

 

7.      The letter of credit for the registered subdivisions in which the parks are situated will not be reduced beyond what is required for the works associated with the subdivision plus the cost of the front-ended parks works until such time as the front-ended parks works are accepted by the City.

 

8.       Mattamy (Tenth Line) Limited and the City shall commit by way of agreement to the terms noted in sections 1- 7.

 

PARK AND TRAIL FRONT-ENDING POLICY                                              DOCUMENT 4

 

POLITIQUE INITIALE RELATIVE AUX PARCS ET AUX SENTIERS

ACS2011-ICS-PGM-0040  CITY WIDE/À L'ÉCHELLE DE LA VILLE

 

Front-ending agreements for parks and trails are requested by developers who wish to have specific new growth-related park and trail works in place in advance of the City’s capital project funding for emplacement of these same works.  Developers may voluntarily agree to finance the works at the “front end” and recover their costs from the City at a later date.  The following conditions must be met for the City to enter into a front-ending agreement for parks and trails:

 

1.                  All front-ending agreements with the City will be for new park and trail growth-related capital works that have been included in the City's Development Charges Background Study. A park front-ending agreement is only available for parkettes and neighbourhood parks.

 

2.                  The contract for front-ended works shall be awarded by the front-ender in accordance with the City’s Purchasing Policy of a competitive procurement process and subject to the review and satisfaction of the General Manager, Planning and Growth Management Department.  Where the front-ender does not award the work in accordance with the City’s purchasing policy, they must demonstrate that competitive pricing has been obtained, through analysis of an independent, qualified professional, to the satisfaction of the General Manager, Planning and Growth Management Department.  The contract for the work must be made available to the City to provide to the public.

 

3.                  A lump sum payment, both the development charge portion and the City portion, will be paid back to the front-ender in the year the project is identifed in the City's Development Charges Background Study based on the 10-year capital program at the time the front-ending agreement is approved.

 

4.                  The capital project upset limit for design and construction, project management and contingency shall be established in the Council report approving the front-ending agreement in accordance with the Development Charge By-law and shall be incorporated into the agreement.  Any expenditures incurred above and beyond the amount approved in the agreement cannot be claimed and must be incurred by the front-ender.

 

5.                   Where a front-ender is eligible for reimbursement, documentation is required to support the reimbursement in accordance with the City’s Purchasing Policy.  The front-ending agreement shall identify what documentation and at which stage it shall be required. 


 

 

6.                  A report to Council is required to authorize staff to enter into a front-ending agreement.  The recommendation will include the financial commitment of the City and specify the funding source(s) and the project timeline.  The financial comment in the report will specify the timelines for repayment, an operating budget impact and an estimate of the year in which the operating budget impact will begin.  The report will also specify that the letter of credit for the registered subdivision in which the park is situated with not be reduced beyond what is required for the works associated with the subdivision plus the cost of the front-ended works until such time as the front-ended works are accepted by the City.  A capital project will be established upon Council approval to enter into the front-ending agreement.