1. PinEcrest CreeK/Westboro Stormwater
Management Retrofit Study
ÉTUDE DE
MODERNISATION DE LA GESTION DES EAUX PLUVIALES DU RUISSEAU PINECREST/WESTBORO
COMMITTEE
RECOMMENDATIONS
That Council:
1. Approve the preferred Pinecrest Creek/Westboro Stormwater Management Retrofit Plan as described herein and listed as Document 14; and
2. Approve the filing of the Pinecrest Creek/Westboro Stormwater Management Retrofit Study for the 30-day public review period in accordance with the Ontario Environmental Assessment Act.
RECOMMANDATIONS DU COMITÉ
Que le Conseil :
1.
approuve le Plan privilégié de
modernisation de la gestion des eaux pluviales du ruisseau Pinecrest/Westboro
comme il est décrit dans la présente et soumis sous pli séparé;
2. approuve
le dépôt de l’Étude de modernisation de la gestion des eaux pluviales du
ruisseau Pinecrest/Westboro pour la période
d’examen public de 30 jours conformément à la Loi sur les évaluations environnementales de l’Ontario
DOCUMENTATION :
1.
Deputy
City Manager, Infrastructure Services and Community Sustainability report dated
20 September 2011
(ACS2011-ICS-PGM-0114);
Report to/Rapport au :
Comité de l'environnement
and Council / et au Conseil
20 September 2011 / le 20 septembre 2011
Submitted by/Soumis par : Nancy Schepers, Deputy City
Manager, Directrice municipale adjointe, Infrastructure
Services and Community Sustainability, Services d'infrastructure et Viabilité des
collectivités
Contact
Person/Personne-ressource : Richard Kilstrom, Manager/Gestionnaire, Policy
Development and Urban Design/Élaboration de la politique et conception urbaine,
Planning and Growth Management/Urbanisme et Gestion de la croissance
Élaboration de la politique et conception urbaine
(613) 580-2424 x22653, Richard.Kilstrom@ottawa.ca
SUBJECT: |
PinEcrest CreeK/Westboro
Stormwater Management Retrofit Study |
|
|
OBJET : |
ÉTUDE DE MODERNISATION DE LA
GESTION DES EAUX PLUVIALES DU RUISSEAU PINECREST/WESTBORO |
REPORT RECOMMENDATIONS
That Environment Committee recommend Council:
1.
Approve the preferred
Pinecrest Creek/Westboro Stormwater Management Retrofit Plan as described
herein and listed as Document 14; and
2.
Approve the filing of the Pinecrest Creek/Westboro Stormwater
Management Retrofit Study for the 30-day public
review period in accordance with the Ontario
Environmental Assessment Act.
RECOMMANDATIONS DU
RAPPORT
Que le Comité de
l’environnement recommande au Conseil :
1.
d’approuver le Plan privilégié de
modernisation de la gestion des eaux pluviales du ruisseau Pinecrest/Westboro
comme il est décrit dans la présente et soumis sous pli séparé;
2.
d’approuver le dépôt de l’Étude de
modernisation de la gestion des eaux pluviales du ruisseau Pinecrest/Westboro pour la période d’examen public de 30 jours
conformément à la Loi sur les évaluations
environnementales de l’Ontario.
Executive
Summary
Assumptions
and Analysis:
Stormwater management (SWM) retrofit refers to the insertion of various measures into established, older communities that were originally built without the infrastructure needed to mitigate the impacts of uncontrolled runoff. Unlike greenfield development, where SWM measures are incorporated as a matter of course, the challenge of SWM retrofit is to identify effective measures that can be implemented after the fact – when there is limited land available to implement conventional SWM facilities.
This Study was undertaken to develop a SWM retrofit plan for the Pinecrest Creek subwatershed and adjacent Westboro area, both of which drain to the Ottawa River upstream of Westboro beach. The study area, shown in Document 1, has little or no SWM controls in place as the great majority of the area was built out well before current SWM requirements were in place. The consequences of this historical lack of stormwater management include:
All of these concerns are directly traceable to the highly urbanized nature of the study area and its lack of stormwater management.
Beyond
the existing impacts of uncontrolled stormwater runoff, infill and
redevelopment is also occurring in the study area, the cumulative impacts of
which will further contribute to the problems noted above.
This Study is one of 17 Ottawa
River Action Plan (ORAP) projects, as adopted by City Council on February 24,
2010: http://ottawa.ca/calendar/ottawa/citycouncil/pec/2010/02-09/13%20-%20ACS2010-ICS-ESD-0007%20-%20FINAL%20-%20ORAP.htm.
Two key objectives of ORAP are to: optimize
recreational use and economic development of the river, with a focus on
reducing beach closures; and to maintain a healthy aquatic ecosystem, with a
focus on addressing challenges presented by existing infrastructure. To achieve
these objectives, ORAP identified that the impacts of uncontrolled stormwater runoff must be addressed.
The Retrofit Study is a first step toward addressing the impacts of uncontrolled stormwater on the Ottawa River and its many tributaries. It identifies a long-term plan composed of a range of programs, capital projects and outreach efforts aimed at reversing or partially reversing the historical impacts of development on the Creek and local reach of the Ottawa River. The Study has also served as a pilot for the future preparation of similar retrofit plans for older areas of the City that developed with little or no stormwater management. These additional retrofit studies are also identified in ORAP.
With respect to Westboro Beach, it is important to note that “wet weather,” while a key contributor to the high number of beach closures, is not the only factor. Other “dry weather” factors, unrelated to wet weather, may also warrant further consideration. This Study addresses only the wet weather aspects of beach closures.
The overall purpose of completing the Retrofit Study was to recommend what combination of retrofit measures to apply in the study area that would provide the best solution considering a number of economic, environmental and social factors.
To develop the Retrofit Plan, the following key steps were undertaken:
i) Setting the Stage: Existing Conditions and SWM Retrofit Potential;
ii) SWM Retrofit: Selection of the Preferred Scenario;
iii) Public Consultation and Communications; and
iv) Preparation of an Implementation and Monitoring Plan.
These steps were also completed
to ensure consistency with the requirements of the Municipal Class Environmental Assessment
(MCEA) given the anticipated identification of various capital projects. The study
was conducted as a Master Plan per the MCEA process. Existing conditions were described,
problems, opportunities and a range of solutions were identified, and the
various solutions evaluated to arrive at a preferred approach, the recommended
Retrofit Plan. Public consultation requirements of the MCEA were also fulfilled.
As a Master Plan, the Retrofit Study was completed at a broad level of
assessment. More detailed investigations will be required in order to fulfil
the MCEA requirements for Schedule B and C projects identified within the recommended
Retrofit Plan. As required by the MCEA process, the Retrofit Plan will be
reviewed every five years.
Subject to City Council adoption of the recommended Retrofit Plan, it will be posted for a 30‑day public review period as required by the MCEA.
The preferred Retrofit Plan is composed of:
A 50 year time frame has been suggested to
complete implementation of the preferred Retrofit Plan. This will allow for retrofits
within the rights-of-way and on City-owned properties to be completed
“opportunistically,” i.e., when roadways, City buildings and parking lots come
to the end of their life cycle. This time frame also recognizes the
considerable challenge of engaging sufficient participation from residential
and other private property owners. The 50 year life cycle cost of the preferred
Retrofit Plan is $43M.
The recommended Retrofit Plan, if adopted, will provide the basis for annual budget requests to support the long-term implementation of the various components of the Plan (initial pilot projects, capital projects, education/public outreach, monitoring of overall effectiveness, on-going maintenance of implemented projects, etc.).
For
the 2012 budget process, funding to begin implementation of the Retrofit Plan
has been included for consideration in the draft rate budget in the amounts of
$2M for 2012, $2M for 2013 and $9M for 2014. Earlier estimates of projected
annual costs for stormwater retrofit were also accounted for in the Cost, Rate
and Revenue Study (ACS2010-ICS-ESD-0002).
Public consultation and communication
efforts undertaken for the study included the following:
Technical Advisory Committee: The Technical Advisory Committee (TAC) was comprised of City staff from a variety of departments, and representatives from the National Capital Commission (NCC), Ministry of the Environment, Rideau Valley Conservation Authority and Algonquin College. The TAC met three times during the study - on December 3, 2009, June 17, 2010 and November 30, 2010 and provided advice and guidance to the study team on a range of issues.
Public Advisory Committee: The Public Advisory Committee (PAC) was comprised of five residents and met four times during the study – on October 6, 2009, January 13, 2010, June 17, 2010 and November 30, 2010. The PAC provided valuable comments on how best to reach people in the study area, reviewed interim reports, and constructively critiqued the study.
Open Houses: Open Houses were held on December 3, 2009 (attended by 14 people) and December 1, 2010 (attended by eight people).
Advisory Committees of Council: Presentations were made to the Environmental Advisory Committee on September 9, 2010, and May 12, 2011, and the Ottawa Forest and Green Space Advisory Committee on July 26, 2010 and July 25, 2011.
Participation in other City consultation events: Staff provided information about the study at Ottawa River Action Plan Open Houses held November 23, 26, and 30 and December 1, 2009.
Other Consultations: On November 14, 2009, a presentation was made to the annual Community Associations Forum on Environmental Sustainability, a gathering of city-wide community associations. On April 29, 2010, a presentation was made to the Westboro Beach Community Association at its Annual General Meeting. Finally, on June 17, 2010, a meeting was held with two local teachers to seek their advice regarding opportunities for potential future collaboration relating to retrofitting SWM measures. This included possible tie-ins to the curriculum, involving students in monitoring activities and liaising with School Boards on potential SWM projects such as disconnections of downspouts or the construction of rain gardens.
Newspaper Advertisements: Advertisements for the Open Houses (including the Notice of Study Commencement) were placed in local and daily newspapers.
Flyers: Flyers were developed in advance of the Open Houses to provide basic information about the study and promote the Open Houses. These were e-mailed to those on the study mailing list, which included individuals, environmental groups and community associations. Prior to the second Open House, flyers were posted at local community centres and other venues in the study area.
E-Newsletters: E-newsletters were developed to introduce the study and provide progress updates. These were sent to individuals, environmental groups, community associations and ward Councillors in July 2010, October 2010 and November 2010.
Website: A website was created to provide access to more detailed information about the study:
http://ottawa.ca/residents/public_consult/pinecrest_westboro/index_en.html
Comments received from the public, TAC and PAC were
generally supportive of the purpose and recommendations of the study.
RÉSUMÉ
Hypothèses et analyse :
La modernisation de la gestion des eaux
pluviales (GEP) renvoie à l’intégration de diverses mesures au sein de
collectivités anciennes et établies qui étaient au départ construites sans
l’infrastructure nécessaire pour réduire les répercussions des eaux de
ruissellement non contrôlées. Contrairement à l’aménagement des zones vertes,
où les mesures de GEP sont pratiques courantes, la modernisation de la GEP pose
le défi de cerner des mesures efficaces qui peuvent être mises en œuvre après
l’aménagement des terres – et lorsque les terres vierges disponibles sont
insuffisantes pour prévoir des installations de GEP traditionnelles.
Cette étude a été menée dans le but de
concevoir un plan de modernisation de la GEP pour le sous-bassin hydrographique
du ruisseau Pinecrest et le secteur adjacent de Westboro, les deux se déversant
dans la rivière des Outaouais en amont de la plage de Westboro. Le secteur à
l’étude, illustré dans le Document 1, possède peu d’installations de contrôle
de la GEP, voire n’en possède aucune, étant donné qu’il a été construit, dans
sa grande majorité, bien avant que les exigences actuelles en matière de GEP
soient introduites. Les conséquences de ce manque historique de GEP se sont
révélées être :
Toutes ces préoccupations sont directement
liées à la nature fortement urbanisée du secteur à l’étude et à son manque de
gestion des eaux pluviales.
En plus des conséquences connues des eaux de
ruissellement non contrôlées, l’aménagement sur terrain intercalaire et le
réaménagement sont aussi à blâmer dans ce secteur. Leurs impacts cumulatifs ne
feront qu’accentuer les problèmes susmentionnés.
Cette étude est l’un
des 17 projets à court terme du Plan d’action de la Ville visant la rivière des
Outaouais (PARO), tels que les a adoptés le Conseil municipal le 24 février
2010 : http://ottawa.ca/calendar/ottawa/citycouncil/pec/2010/02-09/13%20-%20ACS2010-ICS-ESD-0007%20-%20FINAL%20-%20ORAP.htm. Les deux principaux objectifs du
PARO sont, d’une part, d’optimiser le développement économique de la
rivière et son utilisation à des fins récréatives, notamment par la diminution
des fermetures de plages, et, d’autre part, de maintenir un écosystème
aquatique sain, en se consacrant surtout aux difficultés que posent les
infrastructures existantes. Pour atteindre ces objectifs, le PARO a identifié
les conséquences néfastes des eaux de ruissellement non contrôlées auxquelles
on doit remédier.
L’Étude de modernisation est un premier pas
vers la remédiation de ces conséquences sur la rivière des Outaouais et ses
nombreux affluents. Elle définit un plan à long terme composé de toute une
gamme de programmes, de projets d’immobilisations et d’efforts de rayonnement
qui visent tous à renverser, en tout ou en partie, les répercussions
historiques de l’aménagement dans le ruisseau et la rivière des Outaouais dans
lequel il se déverse. L’étude a également servi de pilote à la préparation
future de plans de rénovation semblables pour les vieilles zones aménagées de
la Ville ayant peu d’installations de gestion des eaux pluviales voire même
aucune. Ces études supplémentaires de modernisation sont elles aussi définies
dans le PARO.
En ce qui concerne la plage de Westboro, il
importe de noter que le « temps pluvieux », bien qu’il soit un
facteur contributif clé de la fréquence élevée des fermetures de la plage,
n’est pas le seul. D’autres facteurs en « temps sec », indépendants
du temps pluvieux, peuvent aussi être pris en compte. Or, la présente étude
aborde uniquement les aspects du temps pluvieux des fermetures de plages.
L’Étude de modernisation avait pour objectif
global de recommander quelles mesures pouvaient ensemble s’appliquer au secteur
à l’étude et offrir la meilleure solution possible étant donné les facteurs
économiques, environnementaux et sociaux existants.
Pour concevoir le Plan de modernisation, les
étapes clés suivantes ont été prises :
i)
Mise
en contexte : conditions existantes et potentiel de modernisation de la GEP;
ii) Modernisation de la GEP : Sélection
du scénario privilégié;
iii) Consultation et communication auprès
du public;
iv) Préparation d’un plan de mise en
œuvre et de contrôle.
Ces mesures visaient également à assurer la
conformité du plan aux exigences de l’Évaluation environnementale municipale de
portée générale (EEPG) à la lumière de la détermination prévue de divers
projets d’immobilisations. L’étude a pris la forme d’un plan directeur, mené
selon le processus de l’EEPG. Les conditions existantes y ont été décrites, les
problèmes, possibilités et solutions diverses y ont été identifiés, et les
solutions ainsi identifiées ont fait l’objet d’une évaluation pour en arriver à
l’approche jugée la meilleure : le Plan de modernisation recommandé (dit
privilégié). Les exigences en matière de consultation publique de l’EEPG ont
également été comblées.
En tant que plan directeur, l’Étude de
modernisation a été conclue à un niveau général d’évaluation. Des enquêtes plus
approfondies devront être menées pour remplir les exigences de l’EEPG vis-à-vis
des projets des Annexes B et C définis dans le Plan de modernisation
privilégié. Conformément au processus de l’EEPG, le Plan de modernisation sera
revu tous les cinq ans.
Sous réserve de l’adoption du plan recommandé
par le Conseil municipal, le plan sera affiché aux fins d’examen public pendant
une période de 30 jours tel que l’exige l’EEPG.
Le Plan de modernisation privilégié comprend ce
qui suit :
On a suggéré un délai de 50 ans pour la
mise en œuvre complète du Plan de modernisation privilégié. Ce délai permettra
d’entreprendre la modernisation des zones d’emprise et des propriétés gérées
par la Ville de manière « opportuniste », c’est-à-dire quand les
routes, les bâtiments municipaux et les terrains de stationnements arriveront à
la fin de leur cycle de vie. En outre, ce délai reconnaît le défi
considérable que pose la tâche d’obtenir une participation suffisante de la
part des propriétaires résidentiels et d’autres propriétés privées. Le cycle de
vie de 50 ans du Plan de modernisation privilégié s’élève au coût de 43
M$.
Ce
rapport n’est lié à aucune implication financière directe. Le Plan de modernisation
recommandé, s’il est adopté, fournira la base des demandes d’allocation du
budget annuel pour appuyer la mise en œuvre à long terme des diverses
composantes du plan (premiers projets pilotes, projets d’immobilisations,
activités de rayonnement/éducation auprès du public, contrôle de l’efficacité
d’ensemble, maintien continu des projets mis en œuvre, etc.).
Dans le cadre du processus
budgétaire de 2012, le financement prévu pour la mise en œuvre du Plan de
modernisation a été ajouté à des fins d’examen au budget préliminaire des
redevances aux montants de 2 M$ pour 2012, 2 M$ pour 2013 et 9 M$ pour 2014.
Des prévisions antérieures sur les coûts annuels de modernisation de la gestion
des eaux pluviales ont également été prises en compte dans l’Étude des coûts, des revenus et
des redevances : http://ottawa.ca/calendar/ottawa/citycouncil/pec/2010/04-13/9%20-%20ACS2010-ICS-ESD-0002%20-%20Rate%20Structure.htm.
Les
efforts de consultation et de communication déployés auprès du public dans le
cadre de cette étude comprenaient les suivants :
Comité consultatif technique : Le Comité
consultatif technique (CCT) se composait de membres du personnel municipal de
plusieurs départements et de représentants de la Commission de la capitale
nationale (CCN), du ministère de l’Environnement, de l’Office de protection
de la nature de la vallée Rideau et du Collège Algonquin. Le CCT s’est réuni trois fois durant
l’étude, soit les 3 décembre 2009, 17 juin 2010 et 30 novembre 2010, et a
formulé des recommandations et proposé des orientations à l’équipe de l’étude
sur une variété de sujets.
Comité
de consultation publique : Le Comité de consultation publique (CCP) était
composé de cinq résidents qui se sont réunis quatre fois durant l’étude, soit
les 6 octobre 2009, 13 janvier 2010, 17 juin 2010 et 30 novembre
2010. Le CCP a fait part de commentaires précieux sur la meilleure façon de
sensibiliser les gens dans le secteur à l’étude; il a examiné des rapports
provisoires et critiqué l’étude de manière constructive.
Portes
ouvertes : Des Portes ouvertes ont
eu lieu le 3 décembre 2009 (14 personnes s’y sont présentées) et le 1er
décembre 2010 (8 personnes étaient présentes).
Comités
consultatifs du Conseil : Le Comité
consultatif sur l’environnement et le Comité consultatif sur les forêts et les
espaces verts d’Ottawa ont assisté chacun à deux présentations données les 9
septembre 2010 et 12 mai 2011 et les 26 juillet 2010 et 25 juillet 2011
respectivement.
Participation
à d’autres activités de consultation municipale : Le personnel a donné des renseignements sur l’étude lors des
Portes ouvertes du Plan d’action de la Ville visant la rivière des Outaouais
tenues les 23, 26 et 30 novembre et 1er décembre 2009.
Autres
consultations : Le 14 novembre 2009,
une présentation a été donnée lors du Forum des associations communautaires sur
la viabilité environnementale, un rassemblement annuel de toutes les
associations communautaires de la ville. Le 29 avril 2010, une autre
présentation a été livrée à l’Association communautaire de la plage de Westboro
lors de son assemblée générale annuelle. Enfin, le 17 juin 2010, une réunion a
été convoquée avec deux enseignants locaux pour connaître leur avis sur des
possibilités de collaboration future dans la modernisation de mesures de GEP.
Ces possibilités visaient notamment l’intégration de ces mesures dans le
programme d’enseignement, en impliquant les étudiants dans les activités de
contrôle et en servant de liaisons avec les conseils scolaires pour discuter de
projets de GEP possibles (p. ex., débranchement de gouttières, construction de
jardins de pluie).
Annonces
dans les journaux : Des annonces dans
les journaux locaux et quotidiens ont paru au sujet des Portes ouvertes (y
compris des avis de début d’étude).
Prospectus
: Des prospectus ont été élaborés avant les Portes ouvertes pour souligner les
grandes lignes de l’étude et promouvoir les Portes ouvertes. Ces prospectus ont
été envoyés par courriel aux personnes inscrites sur la liste d’envoi de
l’étude, qui comprenait des particuliers, des groupes environnementaux et des
associations communautaires. Avant la tenue des deuxièmes Portes ouvertes, des
prospectus ont été affichés dans les centres communautaires et autres endroits
situés dans le secteur à l’étude.
Bulletins
électroniques : Des bulletins électroniques ont été rédigés pour présenter
l’étude et informer sur les derniers développements. Ces bulletins ont été
envoyés à des particuliers, des groupes environnementaux, des associations
communautaires et des conseillers de quartier en juillet, octobre et décembre
2010.
Site
Web : Un site Web a été créé pour donner accès à de l’information plus
détaillée sur l’étude:
http://ottawa.ca/residents/public_consult/pinecrest_westboro/index_fr.html
Le public, le CCT et le CCP
ont en général appuyé l’objectif et les recommandations de l’étude.
BACKGROUND
This project was undertaken to develop a SWM retrofit plan for the Pinecrest Creek subwatershed and adjacent Westboro area, both of which drain to the Ottawa River upstream of Westboro beach. The study area, shown in Document 1, has little or no SWM controls as the great majority of the area was built out well before current SWM requirements were in place. The consequences of this historical lack of stormwater management include:
All of these concerns are directly traceable to the highly urbanized nature of the study area and its lack of stormwater management.
Beyond the existing impacts of uncontrolled stormwater runoff, infill and redevelopment is also occurring in the study area, the cumulative impacts of which will further contribute to the problems noted above.
This Study is one of 17 Ottawa
River Action Plan (ORAP) projects, as adopted by City Council on February 24,
2010: http://ottawa.ca/calendar/ottawa/citycouncil/pec/2010/02-09/13%20-%20ACS2010-ICS-ESD-0007%20-%20FINAL%20-%20ORAP.htm. Two key objectives of ORAP are to: optimize
recreational use and economic development of the river, with a focus on
reducing beach closures; and to maintain a healthy aquatic ecosystem, with a
focus on addressing challenges presented by existing infrastructure. To achieve
these objectives, ORAP identified that the impacts of uncontrolled stormwater runoff must
be addressed.
As
documented in the ORAP staff report, comments received from the public in the
fall of 2009 about ORAP objectives and projects identified three key themes
(emphasis added):
·
The City must address impacts of uncontrolled
stormwater runoff as well as combined sewer overflows (CSOs). Several ORAP projects address urban
stormwater; however, it is recognized that stormwater pollution is as important
an issue as combined sewer overflows.
·
Residents and businesses must take responsibility
for their discharges to the environment (i.e., source control). At present, the City does not have a
communication plan for improving awareness of, and action on, water environment
issues at the community level. For this
reason, a new project was added to ORAP to allow for improved public outreach
and education on water environment matters.
·
A watershed approach is needed to ensure that
the full range of pollutant sources and impacts are addressed.
Public consultation for ORAP included an
on-line questionnaire that was also available at the ORAP Open Houses. From the
results of the questionnaire, some 300 of which were completed, most
respondents expressed the desire that the plan address stormwater pollution to
the same degree as CSOs; and to involve residents and businesses in reducing
pollution of surface waters at the lot level.
The Retrofit Study is a first step toward addressing the impacts of uncontrolled stormwater on the Ottawa River and its many tributaries. It identifies a long-term plan composed of a range of programs, capital projects and outreach efforts aimed at reversing or partially reversing the historical impacts of development on the Creek and local reach of the Ottawa River. The Study has also served as a pilot for the future preparation of similar retrofit plans for older areas of the City that developed with little or no stormwater management. These additional retrofit studies are also identified in ORAP.
With respect to Westboro Beach, it is important to note that “wet weather,” while a key contributor to the high number of beach closures, is not the only factor. Other “dry weather” factors, unrelated to wet weather, may also warrant further consideration. This Study addresses only the wet weather aspects of beach closures.
DISCUSSION
SWM retrofit refers to the insertion of various measures into established, older communities that were originally built without the infrastructure needed to mitigate the impacts of uncontrolled runoff. These impacts include degraded water quality, increased flooding and erosion, and the impairment or destruction of fish habitat. In other words, unlike greenfield development, where SWM measures are incorporated as a matter of course, the challenge of SWM retrofit is to identify effective measures that can be implemented after the fact – when there is limited land available to implement conventional SWM facilities.
These SWM measures are categorized by the location where they operate within the drainage system and include:
The overall purpose of the Retrofit Study was to recommend what combination of the above measures to apply in the study area that would provide the best solution considering a number of economic, environmental and social factors.
To develop such a Retrofit Plan for the study area, the following key steps were undertaken:
i) Setting the Stage: Existing Conditions and SWM Retrofit Potential;
ii) SWM Retrofit: Selection of the Preferred Scenario;
iii) Public Consultation and Communications; and
iv) Preparation of an Implementation and Monitoring Plan.
These steps were also completed
to ensure consistency with the requirements of the Municipal Class Environmental Assessment
(MCEA) given the anticipated identification of various capital projects. The study
was conducted as a Master Plan per the MCEA process. Existing conditions were described.
Problems, opportunities and a range of solutions were identified, and the
various solutions evaluated to arrive at a preferred approach: the recommended
Retrofit Plan. Public consultation requirements of the MCEA were also fulfilled.
As a Master Plan, the Retrofit Study was completed at a broad level of
assessment. More detailed investigations will be required in order to fulfil
the MCEA requirements for Schedule B and C projects identified within the recommended
Retrofit Plan. As required by the MCEA process, the Retrofit Plan will be
reviewed every five years.
Subject to City Council adoption of the recommended Retrofit Plan, it will be posted for a 30-day public review period as required by the MCEA.
i) Setting the Stage: Existing Conditions and SWM Retrofit Potential:
An overview of existing conditions within the study area was completed, documenting the impacted condition of Pinecrest Creek and the adjacent Ottawa River, including Westboro Beach.
Land use within the Pinecrest Creek subwatershed and adjacent Westboro
catchments has changed over the last century or so from forest, to agriculture,
to the current predominantly urban character. The study area is almost
completely built-out, with only minor undeveloped areas remaining.
The impacts of historical development and uncontrolled urban runoff on the study area are evident and well-documented:
Impacts on
Pinecrest Creek:
Impacts on the Ottawa River and Westboro Beach:
In addition to these on-going impacts of existing development, there are
continuing infill and redevelopment pressures within the study area.
Following the overview of existing conditions, an assessment of the
retrofit potential within the study area was undertaken. This involved completing
an inventory of stream corridor infrastructure, road and development types; stream bank
stability, erosion threats and flood risk. Existing storm sewer outfalls were
assessed for the potential to construct new end-of-pipe facilities and land use
and rights-of-way were characterized to assess the opportunities to implement
lot level and conveyance retrofits.
ii) SWM Retrofit: Selection of the Preferred SWM Retrofit Scenario:
The next steps involved:
The retrofit objectives, listed in Table 1, identify the aims of the
Retrofit Plan, providing direction to achieve the overall goal of a healthier creek
and river and reduced closures at Westboro Beach. Associated targets (see
Document 2) are numerical benchmarks that represent the desired condition to be
achieved, for example, improved water quality, reduced E.coli counts during wet weather, reduced flood and erosion risks,
etc.
Table 1: Objectives of the SWM Retrofit Plan*
|
Reduce flood risk to public health and safety and to property along the Pinecrest Creek corridor. |
|
Reduce erosion impacts in the Pinecrest Creek corridor that are detrimental to property, infrastructure and stream habitat. |
|
Re-establish a more natural hydrologic cycle for the Pinecrest Creek subwatershed. |
|
Improve water quality in Pinecrest Creek and the Ottawa River by reducing the impact of stormwater runoff. |
|
Reduce the impacts of stormwater runoff on Westboro Beach. |
|
Protect, enhance or rehabilitate natural features and functions along the Pinecrest Creek corridor. |
|
Increase public awareness about stormwater management and public involvement. |
* Note: the numbering is for convenience and does not indicate priority.
The retrofit scenarios considered were comprised of different
combinations and amounts of lot level, conveyance and end-of-pipe measures that
would be retrofitted into the existing rights-of-way, open spaces, and a
proportion of public and private properties within the study area. Table 2
identifies the list of measures included in the different retrofit scenarios (Note:
The retrofit measures selected for inclusion in the various scenarios were
chosen as a reasonable reflection of what measures could feasibly be
implemented locally but the list is not exhaustive. There is a large and
growing range of potential retrofit measures and exclusion from this exercise does
not preclude their implementation, for example, the implementation of green
roofs on public or institutional buildings, which may provide the same or
similar benefits as the retrofit measures that were considered for this Study).
Table 2: SWM
Retrofit Measures Comprising the Different Retrofit Scenarios
Type of Measure |
Measures Included |
Lot
level |
Downspout
disconnection/re-direction |
Rain
barrels/cisterns |
|
Porous/permeable
pavement/concrete (for sidewalks and parking lots) |
|
Rain
gardens |
|
Conveyance
|
Street
narrowing |
Infiltration
measures |
|
End-of-pipe |
Wet
ponds |
Oil/grit
separators |
A detailed description of each type of measure is provided in Document 3.
A total of five different retrofit scenarios were derived to encompass a
range of potential implementation levels (i.e., a greater or lesser amount of
retrofit effort) for the various measures within the study area. A primary consideration
was the degree of “uptake” or the extent of implementation that could
reasonably be anticipated. With respect to lot level measures on private
property, actual uptake will ultimately depend on a number of factors, for
example:
There is the further possibility that uptake of such measures could be increased via various incentives provided by the City. The examination of potential incentives was beyond the scope of this Study but should be given further consideration as implementation proceeds. For example, the further examination of options for the recovery of stormwater and drainage costs, as recommended by the Review of the Water, Sanitary and Stormwater Rate Structure, could consider the provision of incentives to increase “uptake” of lot level measures: http://ottawa.ca/calendar/ottawa/citycouncil/pec/2010/04-13/9%20-%20ACS2010-ICS-ESD-0002%20-%20Rate%20Structure.htm.
For each lot level measure, the percentage uptake assigned was based upon
homeowner surveys and social marketing efforts undertaken for a similar study
in the City of Toronto, as well as characteristics particular to the study
area.
With respect to conveyance measures, identification of the specific rights-of-way
to (ROW) to be
retrofitted was beyond
the scope of the Retrofit
Study. However,
the total length of ROW retrofits required to achieve the desired stormwater
management benefits was determined. (A further screening study will be required
to determine specific feasible locations for conveyance retrofits.)
The potential for implementation of retrofit end-of-pipe facilities was
determined through a screening process. Potential sites were screened for sufficient
space to implement a new facility, existing servicing conflicts, presence of
mature tree cover and property ownership to identify feasible sites to carry
forward. In the end, six locations were identified as feasible locations for new
end-of-pipe facilities, as shown on Document 4. Of the six candidate sites, five
are located on National Capital Commission (NCC) property (NCC owns most of the
Pinecrest Creek corridor) and one on City property (a subsurface facility
within Elmhurst Park). Note: the NCC was consulted regarding these sites and
provided various comments and conditions with respect to use of NCC land for
such purposes but was unable to provide endorsement of these locations without
further details that were beyond the scope of this study. Accordingly, prior to
the implementation of any end-of-pipe facility on NCC property, additional
study and consultation will be required.
The resulting five retrofit scenarios considered included:
1.
Existing Conditions –or “Do
Nothing:”
This scenario represents the existing land use and
storm drainage conditions, which include the very limited stormwater management
that currently exists in the study area.
2.
Highest Practical Retrofit
Implementation (without End-of-pipe Facilities):
This scenario was composed of the existing land use
with the implementation of all the selected lot level and conveyance measures
(as per Table 1), but excluding end-of-pipe facilities. “Highest practical” refers
to the highest level of implementation presumed to be achievable, that is, not
all property owners can be assumed willing to participate. This scenario
provides an indication of the improvements that could be achieved by the implementation
of lot level and conveyance measures only.
3.
Highest Practical
Implementation (with End-of-pipe Facilities)
This scenario was composed of the existing land use
with the implementation of all the selected lot level, conveyance and
end-of-pipe measures (as per Table 1). “Highest practical” again refers to the highest
level of implementation presumed or determined to be feasible for all measures.
4.
Moderate Implementation
This scenario was comprised of the same types of
measures as the “Highest Practical (with End-of-Pipe) Scenario,” however, the
extent of the implementation for lot level and conveyance measures was set
lower. The “Moderate” implementation percentages are based upon a 5-30%
reduction from the “Highest Practical” percentage uptakes assumed. For
end-of-pipe opportunities, only four of the six potential end-of-pipe
facilities were included in this scenario.
5.
Public Property Only
Implementation
This scenario included implementation of measures
on publicly-owned lands only, thereby providing an indication of the
improvements that could be achieved without any participation from private
landowners and individual homeowners. Publicly-owned lands have been defined as
municipal, federal, provincial and local institutional (school board) lands. As
all six potential end-of-pipe facilities would be located on public lands, all were
included in this scenario. Implementation percentages for lot level and
conveyance measures on public lands were equivalent to those used in the
“Highest Practical” scenario.
Modeling was then undertaken to predict the relative benefits of each
scenario in terms of reducing flood risk, pollution, erosion impacts, runoff
volumes, and E.coli counts at
Westboro Beach. This modeling included two steps: the pollutants generated
during wet weather by the study area under the five different scenarios were
modelled. Total suspended solids (TSS), total phosphorous (TP) and E.coli were the representative
pollutants modelled. The results for E.coli
were then input to a hydrodynamic model of the river to simulate the resulting
peak E.coli counts at Westboro Beach.
Table 3 summarizes the results of the modeling exercises, indicating the
predicted pollutant and runoff volume reductions for each retrofit scenario.
Table 3: Water Quality and
River Modeling Results
Water
Quality Modelling Results |
|||||
Water Quality Model (WinSLAMM) |
Pinecrest Creek |
|
|||
Highest Practical SWM with End-of-pipe |
Highest Practical SWM no End-of-pipe |
Moderate SWM |
Public Property Only |
||
% Reduction (Relative to Existing Conditions) |
|||||
Runoff Volume |
24% |
24% |
13% |
5% |
|
E.Coli Counts |
35% |
24% |
26% |
22% |
|
Yield of TSS |
43% |
11% |
35% |
39% |
|
Yield of TP |
32% |
12% |
25% |
25% |
|
Water Quality Model (WinSLAMM) |
Westboro Outfall River Outfalls |
||||
Highest Practical SWM with End-of-pipe |
Highest Practical SWM no End-of-pipe |
Moderate SWM |
Public Property Only |
||
% Reduction (Relative to Existing Conditions) |
|||||
Runoff Volume |
31% |
31% |
17% |
7% |
|
E.Coli Counts |
54% |
28% |
46% |
42% |
|
Yield of TSS |
46% |
15% |
42% |
40% |
|
Yield of TP |
34% |
15% |
28% |
24% |
|
Scenario Descriptions: |
|||||
Highest Practical with
End-of-pipe: More lot level and conveyance measures; six end-of-pipe
facilities |
|||||
Highest Practical (no
End-of-Pipe): More lot level and conveyance measures; no end-of-pipe
facilities |
|||||
Moderate: Less lot level
and conveyance measures; four end-of-pipe facilities |
|||||
Public Property: Lot level
and conveyance measures on public property only; six end-of-pipe facilities TSS=total suspended solids TP=total phosphorous |
|||||
River Modelling Results |
|||||
Storm Events |
Peak E.coli Concentration at Westboro Beach
(counts/100ml) |
||||
Existing Conditions |
Highest Practical SWM with End-of-pipe |
Highest Practical SWM no End-of-pipe |
Moderate SWM |
Public Property Only |
|
June 20, 1980 (10.8mm) |
102 |
63 |
82 |
68 |
71 |
July 7, 1980 (28.8mm) |
177 |
98 |
136 |
109 |
115 |
July 15, 1980 (20.9mm) |
157 |
88 |
120 |
99 |
104 |
|
|
% Reduction (Relative to Existing Conditions) |
|||
|
|
38% |
20% |
33% |
30% |
|
|
45% |
23% |
38% |
35% |
|
|
44% |
24% |
37% |
34% |
Average |
|
42% |
22% |
36% |
33% |
Notes: 1.Including background
concentrations: June = 30 counts/100mL; July = 25 counts/100mL 2. 1980 rainfall data has
been used as it is reflective of an “average year.” |
The five scenarios were then evaluated and ranked according to their predicted
ability to meet all of the Study’s objectives and targets (as per Table 1 and
Document 2) and a number of other considerations. The evaluation addressed five
main categories, including:
An overall scoring method was developed to capture the benefits and/or
limitations of each of the five scenarios evaluated. The resulting detailed evaluation
is provided in Document 5 and summarized in Table 4.
Table 4:
Summary of Evaluation of Scenarios
Scenario |
Overall
Score* |
Rank |
Timing
to Implement |
Degree
of Control** |
Cost*** |
Do Nothing |
116 |
5 |
none |
N/A |
N/A**** |
Highest Practical with End-of-pipe |
217 |
1 |
significant |
moderate |
$64M |
Highest Practical no End-of-pipe |
195 |
2 |
significant |
less
than moderate |
$49M |
Moderate |
192 |
3 |
moderate |
moderate
|
$43M |
Public Property Only |
177 |
4 |
moderate |
high |
$31M |
* Higher score is better
** Degree of control reflects amount of effort within
public control
*** Cost = 50 year life cycle cost
**** This evaluation has not accounted for the “cost
of doing nothing,” i.e., the cost/value of reduced beach usage, continuing
flood, erosion and water quality impacts, etc.
Based upon the evaluation
completed, the “Moderate” retrofit scenario was selected as the preferred
Retrofit Plan. Although the Moderate scenario did not score highest, it was
nevertheless selected as it provided the most cost-effective overall approach.
In other words, it achieves significant benefits, even if less than the two Highest
Practical scenarios. While additional improvements are provided by the Highest
Practical scenarios, these incremental improvements are not significantly
greater and were considered less cost-effective given the required significant increase
in cost to achieve them. A detailed estimate of the 50 year life cycle cost for
the preferred (Moderate) retrofit scenario is provided in Document 6.
The extent of retrofit proposed for this preferred Retrofit Plan (Moderate Scenario) includes:
iii) Public Consultation and Communications:
The public consultation undertaken for the study is described in detail below, in the CONSULTATION section of this report.
iv) Implementation and Monitoring Plan:
The preferred Retrofit Plan
includes a long-term Implementation and Monitoring Plan. The purpose of the two
components is, respectively, to direct the implementation of the wide range of retrofit
measures recommended based upon identified priorities and to guide the monitoring
required to determine overall progress in achieving the Retrofit Plan’s
objectives and targets.
Implementation Priorities:
The Implementation Plan was
prepared based upon the following considerations and priorities:
i) Provision of a long term strategy for retrofitting the study area
based on a 50 year implementation time span that will allow for retrofits
within the rights-of-way and on City-owned properties to be completed “opportunistically,”
i.e., when roadways, City buildings and parking lots come to the end of their
life cycle. In this way, the cost of retrofitting will represent only a portion
of or “premium” on the total cost of replacing existing infrastructure and
physical plant. Document 7 identifies all City properties within the study
area. Each of the associated building roofs,
parking lots, etc., has an assigned life cycle at the end of which replacement
should occur with methods and materials that will contribute to achieving the
Study objectives and that are appropriate to local site conditions and
constraints. For example, green roofs should be considered when roof areas need
to be replaced, permeable materials should be considered when parking lots are
re-surfaced, roof drainage disconnected where feasible, etc. The same approach
should be applied to road rehabilitation projects, i.e., as lengths of road
come up for rehabilitation, consideration should be given to implementing
conveyance retrofits where feasible and appropriate. While 50 years was chosen
as an initial time frame to complete the implementation, it could be achieved
in a shorter period of time but would result in higher overall costs for works
on public property if these were to proceed in advance of the end of their
projected life cycles.
ii) Implementation of lot level and conveyance retrofit measures on
publicly-owned properties as demonstration projects to inform the community
about these measures and encourage participation of private landowners. This
should include pilot installations on City property to gain direct experience with
such measures before their broader application. This would ideally occur at or
near life cycle end, as noted above.
iii) Promotion of the implementation of lot level measures on private,
commercial and industrial properties soon after the implementation of the pilot
lot level/conveyance measure installations on public property in order to
engage various communities and to realize the benefits of retrofitting the
predominant land uses found in the study area, i.e., private property. (As
previously noted the examination of potential incentives to private property
owners was beyond the scope of this Study but should be given further
consideration as implementation proceeds.)
iv) Planning, design and implementation of the proposed end-of-pipe
facility (EoP 16) located at the northeast corner of Baseline Road and
Woodroffe Avenue in the early years of the Retrofit Plan implementation, a
facility that has the potential to provide considerable quality and quantity control
benefits for the subwatershed.
v) Recognition of the need to restore natural landscape values within
the Pinecrest Creek corridor and to encourage the growth and on-going survival
of tree canopy in the study area as part of the Retrofit Plan; and
vi) Engagement of study area residents and business owners through an
on-going consultation, education and outreach program.
The proposed Retrofit Plan is intended to provide direction to achieve a
long-term vision. The suggested 50 year implementation provides a timeframe
that is commensurate with the broad scope of the overall undertaking and
recognizes the considerable challenges associated with retrofitting existing
communities. Notwithstanding the suggested total 50 year timeframe, the initial
focus will be on moving forward in five year increments. Based upon what is
learned from the first five and 10 years of implementation, the 50 year
timeframe would be re-revisited.
Following from the priorities suggested above, the Implementation Plan
is comprised of four complementary components:
The first component, “Awareness
and Engagement,” focuses on what is required to gain the individual and general
public support needed to complete the Retrofit Plan. Each of the next three
components focuses on a property type in which the retrofits are to occur, the
SWM measures involved, potential sites and uptake targets.
The four components are inter-related and complementary. For example,
demonstration (or pilot) projects implemented under “Leading by Example - SWM Retrofits on Public Properties” can
be used to increase awareness, knowledge and enthusiasm about retrofits that
could be implemented on other property types. The “Awareness and Engagement” component addresses the consultation,
education, stewardship and outreach strategies that can be used in the other
components. Audiences” targeted by the “Awareness
and Engagement” effort will necessarily play key roles in the
other implementation components whether they be on public,
commercial/institutional or private residential properties if the overall Retrofit
Plan is to achieve success.
Document 8 provides a proposed schedule that demonstrates how the
suggested 50 year Implementation Plan could be achieved. Table 5 provides a
summary of proposed priority projects for the first five years of implementation.
Table 5: Priority Projects for Initial Five Years of Implementation
Project |
Description |
1.
Pilot lot level measures on City property (within study area) |
Identify candidate
facilities (buildings/parking lots, etc.) and implement and monitor the performance of lot level measures (e.g.,
rainwater cistern, rain garden, pervious paving/pavers,
biofilter, etc.) |
2. Pilot a “green street” |
Identify a length of street
in the study area that could feasibly be retrofit as a "green
street." This could include street narrowing (to increase pervious
area), other infiltration measures, pervious sidewalks, tree-planting, etc.
This would require selection of an appropriate candidate site(s), public
consultation, and would ideally be implemented in conjunction with a
scheduled rehabilitation project. |
3. Workshops and training
opportunities for City staff, consultants and contractors |
Provide design,
construction and operational information regarding lot level and conveyance
measures based upon the experience of recent applications in other similar
jurisdictions. |
4. Study area-wide screening exercise to determine feasible locations for right-of-way (conveyance) retrofit
measures (e.g., street narrowing, "green streets," etc.) |
The Retrofit Plan recommends
a total of 9km of streets within the study area be retrofitted to provide
water quality benefits, however, identification of the specific rights-of-way (ROW) was beyond the scope of
the Retrofit Study. This exercise would examine more closely existing ROW within the
study area, develop criteria for feasibility, consult internally and with the
public, identify specific locations, and develop design standards for future
applications. |
5.
Pilot study of lot level measures at a neighbourhood scale |
Given the limited opportunities for retrofit end-of-pipe facilities in
the study area, water quality improvement over the longer-term will also
depend on the implementation of lot level measures on private residential
properties. There is, however, limited experience with some of these
measures. Challenges are also presented re: achieving sufficient homeowner
participation. This pilot study would look at the implementation of a range
of lot level measures on private property, focusing on a specific
neighbourhood to assess economic incentives (willingness to pay), public
acceptance, as well as the effectiveness of measures with respect to water
quality improvement and runoff volume reduction. This would be a multi-year
pilot including baseline monitoring, resident surveys/public awareness and
engagement efforts, installation of
various measures on willing participants'
properties; follow-up monitoring, etc. |
6. End-of-pipe facility 16: This proposed facility (see
Document 4 for location) would be constructed on NCC land immediately north
of Baseline
Road, east of Woodroffe Avenue, where the creek initially daylights. It would provide water quality and quantity benefits by
treating the large drainage area upstream of Baseline Road |
Complete Class Environmental Assessment,
detailed design and construction of the facility. |
7.Commence Monitoring Plan (summarized in Document
9) |
Begin monitoring to
establish/confirm existing conditions against which the effects of the
retrofit implementation can be tracked over the long term. |
Monitoring Plan:
The intent of the Monitoring
Plan is to track the effects of the retrofit implementation in order to
assess the overall progress in achieving the Study’s objectives and targets. In
other words, based upon data measured in the field as the implementation
proceeds over a number of years, is water quality improving? are flood and
erosion risks being reduced? are wet weather impacts on Westboro beach being
reduced? Monitoring the “on the ground” results of the retrofit implementation
is essential to evaluate the effectiveness of the proposed Plan and to adjust
it accordingly if it is not achieving the projected (i.e., modeled) benefits.
This type of approach is known as “adaptive management” and is particularly
applicable given the uncertainties and complexities associated with the
rehabilitation of urban subwatersheds and their receiving watercourses.
Adaptive management provides a means of working toward achieving desired
outcomes while managing uncertainties through an iterative learning process.
Successful adaptive management requires the clear articulation of the desired outcomes
(objectives and targets) and the ability to adjust actions if/as monitoring
results deem this necessary. The desired outcomes of the Retrofit Plan,
discussed earlier in this report, were identified based on current
understanding and knowledge. As the Retrofit Plan is implemented over time,
field monitoring of the resulting effects and the use of the improved knowledge
so gained will guide adjustments to future actions and continued implementation,
if required.
Document 9 provides a brief summary of the proposed Monitoring Plan.
Implementation
Roles and Responsibilities
The proposed
priority projects identified in Table 5 and the overall Retrofit Plan represent
a new initiative for the City for which some implementation responsibilities
will require confirmation and/or integration into existing programs.
Potential for the “Daylighting” of Pinecrest Creek:
As an open watercourse, Pinecrest Creek ends approximately 300 meters
upstream of Carling Avenue from which point it is piped for some 1400 meters
under the Ottawa River Parkway until it outlets to the Ottawa River .This
piping of the Creek represents a significant loss in terms of aquatic habitat
and the reduced conveyance capacity considerably increases flood risk to the transitway
(and candidate future light rail corridor). Specifically, it is estimated that the
inlet to the piped section has a capacity to convey only the two year peak flow
before overtopping and flooding of the transitway would begin. The piped
section also precludes the possibility of fish migrating from the Ottawa River
upstream into Pinecrest Creek.
In keeping with a key objective of this study (6. Protect, enhance or
rehabilitate natural features and functions along the Pinecrest Creek corridor.),
replacing
sections of this enclosed portion of the creek with an open channel, referred
to as “daylighting,” was assessed on a preliminary basis given the wide range
of benefits that could result, including:
Based upon a review of existing physical constraints, three sections have
been identified as potential locations where daylighting the enclosed creek would
be feasible, amounting to a daylighted length of approximately 900 meters. Daylighting
potential is illustrated on Document 10. Given only a preliminary assessment
could be competed within the scope of this Study, additional work would be required
to more fully assess existing and future constraints.
Daylighting the creek has not been included in
the recommended Retrofit Plan, but has been identified for consideration in the longer
term, for example, to be considered in association with other projects and any
on-going creek corridor naturalization efforts. Such an undertaking would
ultimately be subject to the full support of the NCC, owner of almost the
entire creek corridor.
Linkages to Other City Initiatives and Projects
The findings and recommendations of the Pinecrest Creek/Westboro SWM
Retrofit Study have potential linkages to a number of on-going City initiatives
and projects (beyond ORAP) including:
i)
Choosing
Our Future: A long-term sustainability and resiliency planning initiative is
being finalized for Council consideration in late 2011. Among the goals
of Choosing our Future is: “Water
resources are cherished, conserved and protected.” One of the actions
identified to support this goal is the transition to SWM practices that
integrate extensive source (or lot level) controls to better mitigate the
impacts of existing and future development. The Retrofit Plan explicitly
addresses this proposed direction for the study area by identifying a long-term
strategy to address the impacts of uncontrolled runoff that includes the
promotion of extensive lot level controls.
ii) Corporate Sustainability Program: As
outlined in the Corporate Sustainability Program Road Map 2011 to 2014,
this initiative has “been established
to embed sustainability into the City’s organizational structure and culture –
the way it does business, makes decisions, and delivers services.”
Implementation of the proposed Retrofit Plan will contribute directly to
fulfilling this goal as retrofit practices are incorporated into existing asset
management programs responsible for the rehabilitation of roads and City
properties. The Road Map also recommends the implementation of pilot projects
to gain familiarity with more sustainable practices and build internal
capacity. For these same reasons, undertaking pilot projects has been
identified as a key priority for the initial years of the Retrofit Plan’s
implementation.
iii) Public Transit projects: In addition to
the end-of-pipe facilities the Retrofit Plan proposes on NCC property, there
are a number of on-going or future transit projects that may have additional
impacts on the Creek corridor including the Southwest Transitway, the West
Transitway Extension, Baseline Intensive Transit and the Western LRT. NCC has
identified the need for a cumulative assessment of the impacts of all of these
projects on the Creek corridor that will include a landscape demonstration
plan, naturalization plan, and a fisheries strategy. The Retrofit Study
provides a comprehensive assessment of existing conditions within the Creek
corridor from which a cumulative impact assessment could readily proceed. The recommended
Retrofit Plan also offers a strategy to improve the overall health of the Creek
that should contribute to compensating for the cumulative impacts of these
future projects on the Creek corridor.
SWM Guidelines for Infill and Redevelopment in the Pinecrest
Creek/Westboro Study Area
The Retrofit Study has focused on mitigating the
historical impacts of a lack of stormwater management for existing development.
There is also considerable on-going infill and redevelopment within the study
area. The cumulative impact of this infill and redevelopment has the potential
to negate some of the benefits of future retrofit efforts. Accordingly, SWM
Guidelines for infill and redevelopment in the Pinecrest Creek/Westboro study
area (as shown on Document 1) that are consistent with the objectives of the
Retrofit Study are currently being developed. These will be brought forward
separately to Planning Committee in the first quarter of 2012. The development
of these Guidelines will involve consideration of the challenges specific to
infill and redevelopment and will include consultation with the Developer Working Group associated with the on-going review of
Small-Scale Infill Housing in Mature Neighbourhoods (http://www.ottawa.ca/residents/public_consult/infill/index_en.html).
ENVIRONMENTAL IMPLICATIONS
The implementation of the preferred Retrofit Plan will result in the following benefits to the local environment of Pinecrest Creek, the Ottawa River and Westboro Beach:
RURAL IMPLICATIONS
There are no rural implications.
CONSULTATION
Public consultation and communication
efforts undertaken for the Study included the following:
Technical Advisory Committee: The Technical Advisory Committee (TAC) was comprised of City staff from a variety of departments, and representatives from the National Capital Commission, Ministry of the Environment, Rideau Valley Conservation Authority and Algonquin College. The TAC met three times during the study - on December 3, 2009, June 17, 2010 and November 30, 2010 and provided advice and guidance to the study team on a range of issues.
Public Advisory Committee: The Public Advisory Committee (PAC) was comprised of five residents and met four times during the study – on October 6, 2009, January 13, 2010, June 17, 2010 and November 30, 2010. The PAC provided valuable comments on how best to reach people in the study area, reviewed interim reports, and constructively critiqued the study.
Open Houses: Open Houses were held on December 3, 2009 (attended by 14 people) and December 1, 2010 (attended by eight people). Comments received at the Open Houses are summarized in Documents 12 and 13.
Advisory Committees of Council: Presentations were made to the Environmental Advisory Committee on September 9, 2010, and May 12, 2011, and the Ottawa Forest and Green Space Advisory Committee on July 26, 2010 and July 25, 2011.
Participation in other City consultation events: Staff provided information about the study at Ottawa River Action Plan Open Houses held November 23, 26, and 30 and December 1, 2009.
Other Consultations: On November 14, 2009, a presentation was made to the annual Community Associations Forum on Environmental Sustainability, a gathering of City-wide community associations. On April 29, 2010, a presentation was made to the Westboro Beach Community Association at its Annual General Meeting. Finally, on June 17, 2010, a meeting was held with two local teachers to seek their advice regarding opportunities for potential future collaboration relating to retrofitting SWM measures. This included possible tie-ins to the curriculum, involving students in monitoring activities and liaising with School Boards on potential SWM projects such as disconnections of downspouts or the construction of rain gardens.
Newspaper Advertisements: Advertisements for the Open Houses (including the Notice of Study Commencement) were placed in local and daily newspapers.
Flyers: Flyers were developed in advance of the Open Houses to provide basic information about the study and promote the Open Houses. These were e-mailed to those on the study mailing list, which included individuals, environmental groups and community associations. Prior to the second Open House, flyers were posted at local community centres and other venues in the study area.
E-Newsletters: E-newsletters were developed to introduce the study and provide progress updates. These were sent to individuals, environmental groups, community associations and ward Councillors in July 2010, October 2010 and November 2010.
Website: A website was created to provide access to more detailed information about the study:
http://ottawa.ca/residents/public_consult/pinecrest_westboro/index_en.html
Document 11 provides a summary of comments received from the general public and TAC and PAC members. Documents 12 and 13 provide a summary of comments received at the Open Houses.
There are no legal impediments to implementing any of the recommendations in this report.
RISK MANAGEMENT IMPLICATIONS
There are no risk management implications associated with this report as it represents an overall Retrofit Plan that will guide various projects and programs. Risks associated with specific projects and programs will be identified and managed as they come forward for implementation.
Implementation of the proposed Retrofit Plan will contribute to achieving the following objectives in the City’s Strategic Plan:
i) Solid Waste and
Environment Objective 3: Protect the water environment and source water supply.
The Retrofit Plan will protect the water environment by improving water quality,
reducing flood and erosion risks, and improving the overall health of Pinecrest
Creek and the Ottawa River.
ii) Solid Waste and Environment Objective 4: Meet the intent of the Leadership in Energy and Environmental Design (LEED) standard by 2020 for existing City-owned buildings to support the implementation of Council-approved environmental goals and targets. Implementing SWM retrofit measures at City-owned buildings will contribute to achieving this objective.
N/A
FINANCIAL IMPLICATIONS
The recommended Retrofit Plan, if adopted, will provide the basis for annual budget requests to support the long-term implementation of the various components of the Plan (initial pilot projects, capital projects, education/public outreach, monitoring of overall effectiveness, on-going maintenance of implemented projects, etc.).
For the 2012 budget process, funding to begin implementation of the Retrofit Plan has been included for consideration in the draft rate budget in the amounts of $2M for 2012, $2M for 2013 and $9M for 2014. Earlier estimates of projected annual costs for stormwater retrofit were also accounted for in the Cost, Rate and Revenue Study (ACS2010-ICS-ESD-0002).
SUPPORTING DOCUMENTATION
Document 1 Study Area
Document 2 Study Objectives and Targets
Document 3 Description of SWM Retrofit Measures
Document 4 End of Pipe SWM Retrofit Locations
Document 5 Criteria and Scoring Used
for Scenario Evaluation
Document 6 Life Cycle Costing for the Preferred (Moderate) Retrofit Scenario
Document 7 City Properties within Study Area
Document 8 Implementation Schedule for 50 Year Plan
Document 9 Monitoring Program Summary
Document 10 Potential for Creek Daylighting
Document 11 Comments Received and Responses
Document 12 Comments Received from Open House No. 1
Document 13 Comments
Received from Open House No. 2
Document
14 Pinecrest Creek/Westboro SWM
Retrofit Study (May 2011) (Distributed
separately and held on file with the City Clerk)
DISPOSITION
Planning and Growth Management will work with Infrastructure Services
and Environmental Services to undertake the priority projects identified for
the first five years of implementation and to confirm departmental
responsibilities for the longer-term implementation of specific components of
the Retrofit Plan.
Planning and Growth Management will proceed with completing the Eastern
Subwatersheds SWM Retrofit Study making use of what has been learned from the
Pinecrest Creek/Westboro Study.
Infrastructure Policy and Transportation Planning staff will work
together to prepare a cumulative assessment of the impacts of future
transportation and SWM retrofit projects on the Creek corridor as requested by
the NCC.
STUDY
AREA DOCUMENT
1
1. Reduce flood risk to public health and safety and to
property along the Pinecrest Creek corridor.
Indicator |
Rationale |
Measurable
Parameter |
Existing Condition |
Target |
A)
Flood risk |
With potential infill and redevelopment, there is a
need to ensure that flood risk to public health and safety and to property is
not increased. |
Flood elevations Flood flows |
2010 flood levels generated in Pinecrest Creek/Westboro
SWM Retrofit Study |
Maintain or reduce existing flood elevations Maintain or reduce existing
peak discharge rates for all design events, particularly high flows |
B)
Flood-plain Storage |
Floodplain storage attenuates peak flows as the
flood wave moves downstream through the system; maintaining this feature of
the floodplain is important to avoid peak flow increases from future
potential works within the corridor |
Riparian storage
volumes for 2 to 100 year events |
As determined from 2010
hydraulic modelling generated in Pinecrest Creek/Westboro SWM Retrofit Study |
Maintain
existing riparian storage volumes for 2 to 100 year events |
2. Reduce erosion
impacts in the Pinecrest Creek Corridor that are detrimental to property, infrastructure
and stream habitat.
Indicator |
Rationale |
Measurable
Parameter |
Existing Conditions |
Target |
A)
Sediment
Regime and Sediment Size |
Sediment sources and sediment transport need to be
maintained in dynamic equilibrium to control loadings to reaches. |
Pebble count; visual inspection of channel
substrate; sediment transport samples in-situ; photo record |
Based on retrofit
work, two or three sensitive reaches should be measured prior to
implementation to determine baseline. |
General maintenance
of existing substrates; no increase or decrease in average sediment size (D50)
of more than 10 percent compared to existing conditions Maintenance of
sediment transport rates over a range of transport events based on measured
samples as opposed to theoretical transport results based on equations |
|
|
Substrate
Composition |
Based on retrofit
work, two or three sensitive reaches should be measured prior to
implementation to determine baseline. |
- Due to the
dynamic nature of the channel substrate, dimensional adjustment is
anticipated - As a
performance threshold, adjustment in grain size should not exceed an order of
magnitude over the long term; short-term adjustments should not increase or
decrease by more than 10 percent of the D50 size fraction compared to existing
conditions. |
B)
Channel
Stability and Erosion Potential |
Channel stability is a function of time series flows
and sediment regime, stabilizing bank features (e.g. woody vegetation,
artificial hardening). Erosion potential
needs to be reduced to more natural levels to stabilize and reduce erosion
damage and loss of riparian/floodplain lands. Maintain channel
stability to protect municipal and NCC infrastructure, to reduce annual
maintenance costs and increase longevity of infrastructure |
Cross-sectional
form and area from available survey data |
Based on retrofit
work, two or three sensitive reaches should be measured prior to
implementation to determine baseline. |
- Cross-sectional
area should not increase or decrease in excess of 20% - Cross-sectional
form should be maintained within accepted limits (visual comparison only) |
Longitudinal
Profile |
Based on retrofit
work, two or three sensitive reaches should be measured prior to
implementation to determine baseline. |
- Inter-pool and energy gradients
should not differ in excess of 5% - Riffle grades should not increase or decrease in
slope more than 20% - Riffle crest elevations should not increase or
decrease to the point of impacting upstream bedforms (visual analysis) |
||
Lateral Migration (meandering) |
Based on retrofit
work, two or three sensitive reaches should be measured prior to
implementation to determine baseline. |
- Annual migration rates exceeding 15 cm per year in
pools and 5 cm per year in riffles will trigger an assessment of the
channel conditions at the site |
||
Cross-sectional measurement of erosion-prone sites;
review of hydrologic and hydraulic data to determine changes to erosion
potential over time |
Based on retrofit
work, two or three sensitive reaches should be measured prior to
implementation to determine baseline. |
No significant increase in bed and bank erosion; no
significant decrease in erosion potential which could cause sedimentation in
problematic areas within the channel |
||
C)
Aquatic Habitat |
Improve the quality
and quantity of in-stream aquatic habitat. Improving the potential for a sustainable fishery is
a longer term objective. |
For example: Average pool depth Percent cover Bank stability |
Given the
existing degraded conditions in the creek corridor, the immediate focus is reducing
the impacts of uncontrolled runoff– see other objectives and targets. |
To be developed in future, subject to progress in
achieving water quality and quantity targets and mitigating existing
barriers. |
3. Preserve
and/or re-establish a more natural hydrologic cycle for the Pinecrest Creek
subwatershed.
Indicator |
Rationale |
Measurable
Parameter |
Existing Condition |
Target |
A)
Peak Flows and Runoff Volume for more Frequent Storms |
Reduce flashiness of runoff from the watershed |
Runoff volumes and peak flows for more frequent
storms (e.g. up to 25 mm) |
Retention assumed between 1.5-4.5 mm Detention assumed to be 0 mm |
Retain runoff
from first 10 mm of rain. Detain runoff from next 15 mm of rain. (To be confirmed
– subject to model calibration and confirmation of existing condition
watershed peak flows and runoff volume targets) |
B) Effective imperviousness (EI) The proportion of a catchment covered by
impervious surfaces directly connected to the stream by storm sewers |
The degree of effective imperviousness can greatly
impact the timing and amount of flows and pollutants into the receiving
watercourse. |
Area difference between total impervious area and
indirectly connected area |
Will be assessed on a site by site basis for
infill and redevelopment areas |
As a minimum, existing effective impervious should
not be increased; to be implemented as a requirement for infill and
redevelopment |
4. Improve water
quality in Pinecrest Creek and the Ottawa River by reducing the impact of
runoff.
Indicator |
Rationale |
Measurable
Parameter |
Existing Condition |
Target |
Instream
Nutrients, Total Suspended Sediment, Total Phosphorus |
Targets
are linked to achieving fish community targets, aesthetics and non-eutrophic
conditions and avoiding the creation of in-situ contaminant concerns |
TSS TP |
Pinecrest
Creek:* Wet weather
TSS- (min: 20 mg/L; max: 520 mg/L; avg: 189 mg/L) Wet weather TP
- (min: 0.03 mg/L; max: 0.57mg/L; avg: 0.10 mg/L) Wavell outfall:* Wet weather
TSS- (min: 28 mg/L; max: 450 mg/L; avg: 224 mg/L) Wet weather TP
- (min: 0.05 mg/L; max: 0.37mg/L; avg:0.15 mg/L) |
TSS
= less than 25 mg/L change from background TP
=0 .03 mg/L (85th percentile) |
*River Input Monitoring Program: 1998 Ottawa River.
Regional Municipality of Ottawa-Carleton (RMOC), 1999.
5. Reduce the impacts of runoff
on Westboro Beach.
Indicator |
Rationale |
Measurable Parameter |
Existing Condition |
Target |
Instream
E. coli (at
Pinecrest Creek Confluence and Adjacent Outfalls to Ottawa River) |
Setting
targets to approach the swimming beach PWQO in non-beach areas ensures that
risks of contracting disease from incidental exposure to recreational waters
are reduced (e.g. boating, water skiing, private dock swimming) |
E. coli |
Pinecrest
Creek:* Wet weather-
(min: 1000 cts/100 mL; max: 8400 cts/100
mL; avg: 3054 cts/100 mL) Wavell outfall:* Wet weather -
(min: 1000 cts/100 mL; max: 135,000 cts/100
mL; avg: 8132 cts/100 mL) |
Achieve
PWQO (E.coli= 200cts/100mL) (80th percentile) E.coli
(max.) not to exceed 2000 cts/100 mL To
be confirmed subject to potential new Guidelines for Canadian Recreational
Water Quality, and resulting modelled count at Westboro Beach. |
*River Input Monitoring Program: 1998 Ottawa River.
RMOC, 1999.
6. Protect, enhance or rehabilitate natural
features and functions along the Pinecrest Creek corridor.
Indicator |
Rationale |
Measurable
Parameter |
Existing Condition |
Target |
A)
Riparian Vegetation |
The
Environment Canada Habitat Guideline recommends the natural vegetation within
30 m of a watercourse be retained or re-established on each side of a watercourse
for 75% of its overall length. (This target was developed at a watershed
level and may not be appropriate to or achievable within an urban
subwatershed.) |
Riparian vegetation (field visits or aerial
photograph interpretation) |
The City Stream
Watch Annual Report found that 19% of the stream sections were in natural
condition, 46% were altered and 35% were highly altered, (although there may
not be a direct equivalency of these values to the extent of existing
riparian cover). |
To
be determined. |
B)
Tree Canopy |
Increased tree canopy in urban areas can reduce
runoff volume by intercepting rainfall, particularly for small events |
Area of tree
canopy. |
Existing tree canopy = 6 % |
Net increase in canopy To be developed. |
7. Increase public awareness about stormwater management and increase
public involvement.
Indicator |
Rationale |
Measurable Parameter |
Existing Condition |
Target |
A)
Increased
Public Awareness |
Increased public awareness will lead to greater
success and uptake of SWM Retrofit Plan recommendations |
N/A |
N/A |
To be developed
through monitoring and reporting |
B)
Increased
Public Involvement |
Increased public involvement required for successful
implementation of SWM retrofit |
N/A |
N/A |
To be developed
through monitoring and reporting |
Downspout Disconnection/Redirection
Downspout disconnection/redirection is the diversion of flow
from roof tops to pervious areas, as shown in Figures 1a and b. This SWM measure
prevents the routing of stormwater onto impervious surfaces which drain directly
to the storm sewer system (ref. Credit
Valley Conservation and Toronto and Region Conservation Authority. 2010. Low
Impact Development Stormwater Management Planning and Design Guide, Version
1.0). To produce a measurable benefit, simple
downspout disconnection requires a minimum flow path length of 5 m across a
pervious area before flowing onto an impervious surface or into the storm sewer
system. With respect to discharge and seepage, discharge locations for roof
downspouts should be a distance of 3 m away from building foundations, however,
this may not be necessary if the topography slopes 1 to 5% away from the
building (ref. Credit Valley Conservation and Toronto and Region
Conservation Authority. 2010. Low Impact Development Stormwater Management
Planning and Design Guide, Version 1.0).
Figures 1a and 1b Downspout Redirection
Rain Barrels and Cisterns
Rain barrels and cisterns are rain harvesting BMPs that capture
roof runoff from frequent storm events and temporaily store it for reuse on
site. This practice reduces runoff and pollutants, and can provide a benefit in
terms of reduced water consumption. Figure 2 shows a private installation of a
rain barrel, and Figure 3 shows the installation of a public cistern
application.
Figure 2: Connected
Rain Barrel Application
Figure 3:
Connected Cistern Application
Rain Gardens (Bioretention)
Rain gardens, or bioretention areas, are designed to include
hydrophilic (water-loving) native species and amended soils in human-made
depressions to aid in capturing rainfall runoff. This lot level measure
decreases peak flows through additional on-site storage, and reduces pollutant
loads through both runoff volume reduction and filtration prior to discharge. Figures
4a and 4b provide examples of Rain Gardens.
Figure 4a: Rain Garden
Figure
4b: Rain Garden
Porous
and Permeable Pavement/Concrete
Porous or permeable pavement or concrete, an alternative to
impervious products, allows some surface runoff to flow through its surface to
be stored in a granular base prior to being released slowly to the storm sewer
system or infiltrated into the native soil beneath. An example of the use of permeable
pavers in a walkway and parking lot setting can be seen in Figure 5a. Figure 5b
shows water infiltrating through a slab of porous asphalt.
Figure 5a: Porous Pavers used for a Walkway and Parking
Area
Figure 5b:
Cross-Sectional View of Porous Asphalt
Grass Swales
Grass swales are vegetated, shallow, open channels designed
for conveyance and treatment of stormwater runoff, particularly from roadway
drainage. Grass swales reduce runoff volumes and pollutant loads by filtration
through the vegetation and infiltration into the underlying soils, and provide
discharge at lower rates. Grass channels are similar to ditch systems; however,
they have lower design velocities for water quality treatment due to their flatter
side and longitudinal slopes. See Figure 6a for an example of a roadside grass
swale, similar to the existing ditches within portions of the Pinecrest and
Westboro subwatersheds. Figure 6b is a digitally prepared image which
illustrates the option of installing a sub-drain below a grass swale.
Figure 6a: Roadside Grass Swale
Figure 6b: Digital
Rendition of a Grass Swale with Sub-Drain
Infiltration Trenches
Infiltration trenches are long, narrow, rock-filled trenches (Figure
7) that receive stromwater runoff from roadways or landscaped areas. As the
trenches have no outlet, the runoff is stored within the voids of the rocks and
infiltrates into the soil below. These trenches are effective in removing fine
particles and associated pollutants.
Figure
7: Side Yard Infiltration Trench
Street Cleaning
Streets are a significant contributor of pollutants to urban
runoff. Street cleaning can reduce this impact. The City of Ottawa uses tandem
street cleaning machines (shown in Figure 8) that make use of brooms and
vacuums.
Figure 8: Street Cleaning
Street
Narrowing
Street narrowing reduces impervious cover, stormwater runoff,
and associated pollutant loads. To maximize the benefits of street narrowing,
the narrowed area can be designed to promote increased infiltration/filtration
via granular media, plantings, etc. Figure 9a demonstrates a simple example of
street narrowing, Figure 9b demonstrates a more ambitious design, which
incorporates a vegetated infiltration trench in the narowed area.
Figure
9a: Street Narrowing
Figure 9b: Street
Narrowing with a Vegetated Infiltration Trench
Oil and
Grit Separators
Oil and
Grit separators (OGS) are underground structures installed in conventional
storm sewer systems to improve water quality downstream (shown in Figure 10). They
come in different designs, sizes and materials; some are commercially available
and others are custom designed and built.
OGS
consists of separate chambers through which stormwater is conveyed to remove
coarse sediments (grit), oils and other buoyant pollutants (floatables). The
principal site constraints in using OGS is the depth of the drainage outlet
that the device is to be connected to and the drainage area to be treated. The
outlet must be sufficiently deep to accommodate the required size of the unit.
In terms of SWM benefits, OGS provide quality control by capturing particulates,
oil and grease. OGS are one of few SWM features that can effectively remove
(retain) oil and grease from stormwater.
Figure 10: Oil and
Grit Separator
Screening
Action Type of OGS (e.g. Continuous Deflection Separation Systems)
Continuous
Defelection Separation (CDS) systems (shown in Figure 11a) are an example of
screening action type of OGS. The CDS systems are designed to treat stormwater
runoff from relatively large drainage areas. Stormwater runoff is conveyed
through the CDS system’s diversion chamber, where all flows are passed through
the separation chamber, which screens, separates and traps sediments and debris.
CDS units can be installed as pre-cast or cast-in-place structures, configured
as in-line, off-line, grate inlet or drop inlet and have multiple screen
aperature sizes (example in Figure 11b). In-line units can treat flows from drainage
areas up to 12 ha, while single off-line units can treat drainage areas up to
120 ha. The use of multiple pre-cast, or larger cast–in-place off-line units,
allows for treatment of drainage areas in excess of 120 ha.
Figure 11a: Typical Schematic
of a CDS Unit
Figure 11b: Typical
Installation of a CDS Unit
Wet Ponds
Wet ponds are end-of-pipe facilities
used to treat runoff from drainage areas of at least 5.0 ha, and preferably
greater than 10 ha. If adequate space is available, these facilities can be
designed and sized to provide erosion control, quality control and flood
control benefits. The ponds shown in Figures 12a and 12b are examples of
typical wet ponds in residential and commercial settings.
Figure 12a: Wet Pond in a Commercial Setting
Figure 12b: Wet Pond in a Residential Setting
Photo Credits
Figures 1a and 1b:http://www.amazoneaves.com/images/ddp01.jpg
Figure 2: http://www.devilsbackyard.com/2010/04/22/rain-barrels-for-your-home
Figure 3: http://www.lakecountyil.gov/Stormwater/LakeCountyWatersheds/BMPs/RainBarrelCistern.htm
Figure 4a: http://baywatersheds.org/wp-content/uploads/2010/07/rain-garden-from-www.carolstream.org_.jpg
Figure 4b: www.sws-sssd.org
Figure 5a: http://greenvalues.cnt.org/national/images/permeable_pavement.jpg
Figure 5b: http://www.inhabitat.com/wp-content/uploads/perviouspaving-ed04.jpg
Figure 6a: http://www.preinnewhof.com/images/Projects/Porous-Pavement-IRS/IRS-Lot-3.jpg
Figure 6b: http://www.wbdg.org/resources/lidtech.php
Figure 7 http://www.cob.org/services/environment/water-quality/homeowner-incentive-program.aspx
Figure 8: http://www.westlafayette.in.gov/egov/gallery/1251236693426196.jpg
Figure 9a: http://www.lakelandgov.net/publicworks/Traffic/TrafficCalming/TrafficCalmingProjects.aspx
Figure 9b: http://switchboard.nrdc.org/blogs/rhammer/managing_stormwater_and_making.html
Figure 10 www.watertectonics.com
Figure
11a: http://www.shawpipe.com, 2010
Figure 11b http://www.contech-cpi.com/Products/Stormwater-Management/Treatment/CDS.aspx
Figure 12a: http://www.rwmwd.org/index.asp?Type=B_BASIC&SEC=%7B82D57109-E41C-4CE8-B838-477FF4A2DDFD%7D
Figure 12b:http://www.co.thurston.wa.us/stormwater/facilities/facilities-home.html
LIFE-CYCLE COSTING FOR THE
PREFERRED
(MODERATE) RETROFIT
SCENARIO DOCUMENT 6
Event |
Source |
Comment |
Response |
PAC mtg June 23, 2009 |
PAC member July 3, 2009 |
What
is the source of the E.coli in Pinecrest Creek? If
we employed the methodology of the study that was done for Lake Huron can we
determine what % of the Ecoli is human, wild life or agricultural source? |
Given the urban nature of the subwatershed,
it is likely that E.coli in the
creek derives from a number of sources including domestic pets, and urban
wildlife/water fowl. Human sources can also contribute if/when
cross-connections exist (i.e., a sanitary sewage lateral pipe from a home or
business is mistakenly connected to the storm sewer). While there are various methodologies that
can identify the specific source of E.coli,
this knowledge would not be anticipated to result in a significant change to
the amount and types of SWM retrofit measures being evaluated for
implementation (e.g., lot level, conveyance, and end-of-pipe measures). |
If
some of the E.coli are from Human origins what changes in City procedure are
required to be able to trace down the sources, e.g., mandatory cooperation in
dye testing homes and business. |
Given the typically intermittent nature of
flows from cross-connections, it can be challenging to track down the source.
When/if discharges of sewage are noted and reported, the City does undertake
“search and destroy” efforts to eliminate the discharge. |
||
Besides
biological contaminates, e.g., E.coli and other bacterial/viruses, what other
substances (metals, anions, and other organic compounds) are present in the creek
waters? |
The stormwater that runs off into the creek
is typical of untreated, urban drainage and includes a range of pollutants
including suspended solids, metals, oil and grease, chlorides, nutrients,
etc. |
||
What
are the options for treatment of the Pinecrest Creek outflow into the Ottawa
River and where would they be done? |
In subsequent stages of the study, various
measures and opportunities have been considered and evaluated to determine
the preferred approach to treating stormwater runoff including lot level,
conveyance and end-of-pipe facilities. |
||
It
is my understanding that there will be modeling done for the flow and outflow
of the creek. However, as I have mentioned in the past what is missing from
studies to date is the actual measurement of E.coli flow as can be determined
by dye dilution studies. Modeling and reality may have a significant
differences! |
Measurements of E.coli in Pinecrest Creek and at various outfalls during wet
weather have been used to ensure that the modeling undertaken is reflective
of actual conditions in the creek and river. |
||
PAC mtg June 23, 2009 |
PAC member July 3, 2009 |
What
is the effect of rainfall on Ecoli outflow/vol from Pinecrest Creek, e.g.,
when there is rain what is the profile of E.coli level in the waters from
Pinecrest Creek. What volume of water "flushes" Pinecrest Creek.
Are there portions of the creek that have higher Ecoli levels and if so why? |
E.coli
readings can vary greatly depending
on a number of factors such as the amount/intensity of rainfall, the time
that has passed since the last rainfall, the time of year, presence of
cross-connections, etc. For the purposes of modeling the “existing condition”
an average E.coli count, based upon
available creek and outfall monitoring data, was used in the water quality
modeling. |
Steps 1 and 2 Report |
City of Ottawa, Env. Sustainability December 24, 2009 |
There has been discussion of the pre urban development and existing
condition hydrology. The only
assessment I see in the draft report is the 100 year flood line. A comparison of the range flow events
statistics – flow, volume, etc. would provide the pre and existing condition
reference as a basis for future targets. |
This has been documented in
the final study report. |
The geomorphic assessment regarding the culvert flags the
sedimentation problem in one of the twin barrel in a number of
locations. I believe I heard
confirmation that there was an assessment of the hydraulic capacity compared
to design events including the 100 year event. Please confirm capacities of existing
conditions relative to the 100 year event. |
This has been provided in
the final study report. |
||
Given the capacity of the culverts, I anticipate discussion of the
morphology in terms of longer term risks.
If the culvert has become a stable in side bend / point bar that still
functions during critical flows, is the sedimentation in it a problem? |
Sedimentation in the
culvert referred to has reached an equilibrium state and while watching it
over the years the level of sediment in the east cell has not changed to any
discernable degree. The discussion relating to sedimentation in culverts is
more centred around the impact of an environment that has gone from erosional
(excess energy) to one that is depositional (minimal energy for transport).
Under the proposed conditions, the sedimentation of culverts is predicted to
occur from the modelling of sediment transport and therefore there is a need
to be proactive with culvert assessment and maintenance to ensure blockages
do not occur. |
||
It is understood that trees that become obstacles to flow as the
channel adjusts cause excessive local erosion and removal is an appropriate
solution. The question of encroachment
is one that needs further clarification / discussion. There is the line of thought that the flood
plain is created by the creek as it moves through its meander belt. Given this is the case and it is adjusting
to its new size, when is it appropriate to just let it do the moving and when
are remedial works required or alternatively when are the costs of major
works to adjust it appropriate / cost effective? The fourth figure? GPS 439023 – 5023221 looks like the Transit way
berm that is out of date, works have been completed? Is this the only case? |
When there is nothing in
the way that is at risk and there are no concerns about the overall health of
a creek, it is prudent to let it do what it wants to do to adjust to new
flows—the creek knows what it wants to do and by intervening we are still
somewhat guessing at the end product. By far the best management strategy is
to let it go and when we see what it is doing then we can help it along if
there are concerns. That strategy requires buy-in by all involved because
there are a number of potential issues, including erosion/deposition within
the creek itself, but also the potential for treefall, sedimentation within
culverts and sediment loading of the outfall of Pinecrest Creek at the Ottawa
River. The data sheets have been
updated to indicate which locations underwent remediation in 2008. They are
all still considered areas of concern until the final phase of the monitoring
is completed in 2011. |
||
Steps 1 and 2 Report |
City of Ottawa, Natural Systems, PGM January 25, 2010 |
p.i. - Task number 2. Should this not follow some of the
subsequent tasks, or is it referring to options already developed under the
Centrepointe project? |
This task refers to
determining the various types of retrofit measures considered as best suited
to this study area (lot level, conveyance, end-of-pipe) as well as
identifying specific opportunities where they can be implemented (e.g.,
end-of-pipe retrofits can only be implemented where there is sufficient land
available near a given outfall). |
p.1 - Under study area, the
report says that the subwatershed area is 1,920 ha. The Existing Conditions Appendix gives
1,440 ha as the "drainage area."
Discrepancy? |
This has been corrected:
Pinecrest subwatershed= 1,920ha; Westboro outfalls total drainage area =
450ha. |
||
Table 4.1: For the Floodplain Storage indicator, I'm not sure
what the rationale means. Do we want
more frequent "spill[s]" into the floodplain, or fewer? How does the target related to the
rationale and the measurable parameter? |
The description for this
indicator has been revised to more accurately reflect its intent: Floodplain storage attenuates peak flows as the flood wave moves
downstream through the system; maintaining this feature of the floodplain is
important to avoid peak flow increases from future potential works within the
corridor. |
||
For Sediment Regime and
Sediment Size. The connections between the rationale, the measurable
parameters and the targets might not be obvious to a lay audience. For example, what does it mean to maintain
"sediment sources and sediment transport... in dynamic
equilibrium...?" How does it
relate to pebble count, and what is a "pebble count?" What is "substrate dimensional
adjustment?" More generally, is
this indicator really necessary, or does the channel stability and erosion
potential indicator provide the necessary information necessary for adaptive
management? Is it really practical to
monitor against the proposed targets, and will it get done? Is anyone really going to look for 5 cm
changes in substrate depth? |
Sediment sources and
transport is dynamic in that sources and transport are not continual but
somewhat random in step length and distance travelled. This is because of the
number of variables that have to be operating in tandem for transport to
occur. Sediment sources are those areas that provide sediment (usually in
controlled volumes) to the stream for transport. When transporting sediment
the stream uses energy to maintain the transport relationship; that energy
used in transport is lost to the erosion part of the energy cycle and
therefore less erosion can occur. If the sediment sources are cut off and
there is no delivery to the streams then the stream will erode the bed and
banks at accelerated rates to gather sediment for transport. So, when a basin
which was once agricultural (to use an extreme example) becomes paved as a
residential development site, the sediment supply to the channel is lost from
overland flow sources and the response by the creek is to erode the bed and
banks. A pebble count is a means
of determining the grain size characteristics of the bed for larger-sized
particles, those that are too large to put through a sieve or XRD process. Dimensional adjustment is
the change in grain size of the bed and it is critical to determining whether
a site is changing from stable to erosional or depositional. It is a means by
which change can be tracked before it becomes obvious by looking at other
parameters. Yes it is practical to measure
against targets, just as it is for all the other indicators. Changes in
substrate diameter through bulk analysis is part of all standard geomorphic
monitoring programs and is required. 5cm changes in bed material are very
significant in the process relationship of a stream. Will it get done? It is
part of the monitoring plan and therefore should be done. |
||
|
For Channel Stability and
Erosion Potential. Under the
longitudinal parameter, what are "inter-pool and energy gradients"
and what does it mean if they differ by more than 5%? |
Inter-pool gradient is the
line which connects the deepest part of pools in sequence with one another
(i.e., pool 1 to pool 2, pool 2 to pool 3, etc.). The slope of the line that
joins these depths is the inter-pool gradient and is a clear indicator of
stability. Under equilibrium conditions that gradient is consistent; a change
in that gradient (which is easily picked up through the long profile survey)
indicates whether a site is tending toward erosional or depositional. Energy gradients refer to
the water surface elevation as flow moves through a reach under different
flow conditions. It is also a slope, a line that joins points of water
surface. As a general rule, pool energy gradients are flatter than riffles,
and for the same riffle or pool, higher volume flows will generally have
higher gradients than lower ones. This is not always the case and needs to be
confirmed at the baseline data collection stage before implementation occurs. If they differ under the
same flow from existing to future then there is a corresponding change in the
energy regime to the reach; steeper gradients result in erosional situations,
gentler gradients result in depositional situations. |
|
Under In-stream Aquatic
Habitat, the composition and diversity of the benthic invertebrate community
will provide a better indicator than the fish community. |
Given the existing degraded conditions in the
creek corridor, the immediate focus is reducing the impacts of uncontrolled runoff (water quality and quantity)
– see other objectives and targets. As such, measurable
parameters and targets for this indicator are to be developed in future
subject to progress in achieving water quality and quantity targets and mitigating
existing barriers. |
||
The Riparian Habitat and
Forest Cover indicators will be of limited value in this subwatershed, but
should be retained for retrofits in other subwatersheds. |
Forest Cover has been
revised to Tree Canopy which is more reflective of an urban subwatershed
(with the emphasis being on reducing runoff from frequent events as opposed
to targeting large increases in forest cover). |
||
Appendix A, Existing
Conditions The comments on the
function of the Trail Road Landfill as a regional gull attractor are
interesting (especially as they may have originated with me). This implies, does it not, that there might
be a benefit to spending some Ottawa River Strategy money on a gull
management plan for Trail Road?
Similarly, should we be encouraging the NCC to better manage their
goose population through passive measures, such as revegetation of grassed
areas? |
Agreed – there is a
committee of NCC and City staff tasked with resolving such issues. |
||
The greenspace identified
as a potential daylighting site at Woodroffe and Tallwood is Urban Natural
Feature 40 - Tallwood Woods. The most
valuable feature of this site is the mature maple grove in the center of the
lot. So daylighting the channel along
the east side of the woodlot should not cause any big impacts. In fact, it would probably increase the
ecological value of the feature. Sandy
soils, though. |
This location has been
eliminated as a potential daylighting section due to the very limited
length/improved function that could be achieved (for the cost) and the
significant depth of the sewer in this location (resulting in a very wide,
deep corridor that would take out much of the woods). |
||
|
NCC January 13, 2010 |
The NCC is willing to
explore the possibilities for dry ponds and daylighting on its property as
suggested in this report. Nothing in this report shall bind the NCC to accept
or complete specific proposals. Any proposal is subject to the Federal Land
Use and Design Approval process (pursuant to the National Capital Act), as
well as an environmental assessment, if required under the Canadian
Environmental Assessment Act. The
NCC’s primary concern is the environmental health of Pinecrest Creek and it
would wish to ensure that any proposal improves the water regime and the
environmental quality of the watercourse. The NCC would wish to ensure that
the facilities are not located solely on NCC property. |
Acknowledged. |
However, the NCC is most
interested by the possibilities for daylighting as these could represent a
valuable opportunity to regenerate the landscape and improve areas for
natural habitat, both aquatic and terrestrial. We encourage the City to fully
explore the opportunities presented in the report and others that may have
been overlooked. |
Daylighting potential has
been examined in the subsequent stages of work. |
||
Open House #1 |
Public December 4, 2009 |
The
question I asked last night on the "Total E.coli Load" as a
function of runoff volume could relate to treatment strategies, e.g., if a
large proportion of E. coli, metal cations and inorganic anions appear in the
"first flush" from a stream or outfall then one might envision a
different treatment regime than one concerned with total runoff volume. As
Darlene pointed out last night most rain falls being below 10 mm may make
this concern academic. However,
if one has two rainfalls say of 5 mm each separated by N hours is the
contamination of the run off for the second event diminished. Or put another
way, how much run off is required to "flush" the creek of
pollutants, i.e.,
what is the relationship of water volume from a rainfall to pollutants
flushing? |
Most pollutants common to
urban runoff demonstrate a “first flush” response, that is, the large
majority of the pollutant load present is washed off in the early portion of
a rainfall event. As a result, end-of-pipe facilities are typically designed
to capture and treat only the “first flush” (since larger capacity would not
result in significant improvements but would cost much more). E.coli
does not generally demonstrate a “first flush” response, however, typical SWM
measures as have been considered in this study are capable of removing a
large percentage of the E.coli load
from stormwater. |
Open House #1 |
Public December 4, 2009 |
Another
consideration for possible future treatment strategies is which areas of the
Pinecrest Creek catchment area contribute most to the pollution of the creek?
The map you showed last night indicated considerable geological and use
variation in the catchment area. Might it be possible to treat stormwaters
discharge from these areas before they run into the creek rather than trying
to manage
the total water volume of the creek? It might be simpler to build at some
selected locations small ponds if indeed certain areas are the major
contributors to the water pollution. Also such small ponds might be used to level
the large increase of water discharge after a rain storm thereby decreasing
damage to the creek structure. Even if there is not a difference in
pollutants from various areas the creation of a number of local stormwater
ponds rather than one large on may have a virtue. |
Yes, the use of
decentralized SWM facilities at various storm outfalls has been recommended
as it is not feasible to treat all of the Pinecrest Creek outflow in one
location at the confluence with the Ottawa River. Improving water quality
before the runoff reaches the creek will also meet the objective of improving
the health of the creek. |
I
am very encouraged with the draft report … good work! However,
I do have a major concern over three other issues that are, or should be part
of this pilot project. The first is a concern I share with John on the need
to involve schools in this project. I would even go further and suggest
that we should learn how the US cities got the citizens of their communities
involved and do the same ASAP, i.e., before the next Open House. The second
is the 2011 plan of implementation of study recommendations. Alex asked some
good questions last night about cost /benefit analysis that are essential to
be addressed when one goes to council seeking funding! The third is that
there should be a considerable effort to make the public in the drainage area
aware of the next open house. Ads in newspapers are good but, there are many
other routes that should be used, e.g., community association involvement, asking
area councillors for input and presence, ads in area stores, and articles in
the local community newspapers. |
Getting schools involved
has been identified in the implementation plan. The benefits achieved for
the cost required have been identified to the extent possible at this level
of study. Public education and
communication efforts have been identified as a key component of the
implementation plan. |
||
June 17, 2010 PAC mtg |
Public July 2, 2010 |
Darlene,
I realize the meeting wasn't intended to outline the measurables that will
eventually have to convince council for their support, but I worry about this
- remember Cullen's concern at the public meeting. While you certainly should
be looking for the best solutions at source, transmission and end of pipe, I
was sort of hoping to see some mention of the cost/benefits when applied to
various catchments - especially as it will affect Westboro Beach since this
is what will likely be foremost on the minds of councillors.
Wavell of course comes to mind as probably the biggest threat to the beach
and also the most costly to try and fix. So what to do, go for one of the
more fixable catchments that will have a more modest cost and at least get
something out of the study than can be held up as a model of accomplishment
even though it might not have much impact on the beach but hopefully sets a
positive direction for the future? I realize this wasn't the main purpose of
the meeting, but I feel relating things to the beach might not be a bad
mind-set as one works towards a conclusion. |
The evaluation of the
various retrofit scenarios and the following step of developing an
implementation plan was aimed at addressing these kinds of concerns, i.e.,
what are the priorities to implement first and where? What benefits can be
achieved and at what cost, etc.? |
|
Queensway Terrace North Community
Association July 20, 2010 |
Is this all about Westboro Beach water quality? Is this about handling
stormwater runoff only? |
As part of this study, the
water quality at Westboro Beach is only one of several objectives that we
have for the study. The objectives include:
Yes, stormwater is our main concern for this study. |
|
Queensway Terrace North Community
Association July 20, 2010 |
QTN Stormwater Management Today:
|
Yes, ditches are beneficial for stormwater management. The City has a ditch infill policy where we
try and maintain existing ditches where possible. |
Recommendations for Consideration to Reduce Runoff from QTN: 1. Repair and reset sewer
drains. 2. Review parks ability
to handle more runoff. 3. Rainbarrel purchase
and installation program. 4. Eavestrough runoff
control program. 5. Hard surface parking
space on private property control program. 6. Private property
direct to storm sewer drainage control program. 7. Severn Public School
used as a model for water management. 8. Stormwater drainage
study. |
These are great suggestions. We
will likely assess most of these as part of our study. Perhaps you can provide more detail about
Severn Public School and its role as a water management site and why it
should be used as a model. |
||
Recommendations for Consideration - Citywide: 1. Retail/Commercial/Institutional
parking lot runoff control program. - designated snow
dump collection areas with absorbent material, - use of buried
cisterns, more soft materials and trees. 2. Living roof program
for these buildings. 3. Repair and reset sewer drains. |
Excellent suggestions. Point #1 is interesting. We do plan to initiate a City-wide retrofit
study, so these recommendations could be considered then. |
||
|
Queensway Terrace North Community
Association July 20, 2010 |
Recommendations for
Pinecrest Creek: 1. Creation of settling ponds complete with native plants. 2. More bends in creek to control erosion and flow rate. 3. Create multiple parallel discharge points. 4. Expand Mud Lake. |
The first three
recommendations are being assessed for their feasibility for the Pinecrest
study area. Other retrofit options
include lot level strategies (pervious pavement, rain barrels, downspout
re-direction, etc.), conveyance (grass swales, infiltration trenches, road
narrowing, etc.) and end of pipe (stormwater management ponds). Due to the ecological significance of Mud
Lake, it would not be appropriate to use it to retain stormwater. |
Steps 3 and 4 Report |
Public December 17, 2010 |
The
JFSA report is a well done classical engineering study. It will, if
implemented, improve many aspects of the problems currently plaguing the
stormwater in Pinecrest Creek but, this will take decades to do if funding is approved.
However, I fear that the proposal for a stormwater pond near the Ottawa River
is unrealistic and has little chance of ever being done. Even if this was
done it would leave many stormwater outfalls dumping untreated into the
Ottawa River. Further, the report does not address any aspects of the sources
of E. coli in stormwaters and what might be done to immediately to reduce a
given source. |
The proposed retrofit plan
includes a SWM facility to treat the runoff from the Wavell and Ardmore
outfalls to the Ottawa River. NCC has identified specific conditions that
would have to be met for a SWM facility to be considered on their property
but have not eliminated this possibility. While it is true that it
will not be possible to provide end-of-pipe facilities at all outfall
locations (due to the lack of space available), other measures (lot level and
conveyance) will, as they are implemented over time, contribute to water
quality improvements. This study was not intended
to differentiate the various sources of E.coli,
which would require a separate, extensive monitoring study that was beyond
the scope of this pilot study. While improving the quality of runoff will
require a long-term effort given the size of the area that contributes and
the overall cost of the various measures, this does not preclude efforts to
prevent E.coli entering runoff in
the first place, such as discouraging large concentrations of water fowl.
Such efforts are under review by a joint committee of City and NCC staff. |
Steps 3 and 4 Report |
Public December 17, 2010 |
My concern is Public Health as well as
Ottawa River health. I propose that it is now an opportune time to submit my
proposal for the phenotyping of E. coli in Pinecrest Creek and the
outfalls. The identification of E. coli source may allow
"smart" short term actions to be undertaking to greatly reduce the
E. coli pollution of waters flowing into the Ottawa River. I trust I
will have your support in undertaking a pilot DNA phenotyping study to
address the Pinecrest Creek Westboro Beach outfalls. |
While differentiating the
various sources of E.coli might
provide some additional insight, it would not necessarily assist in
identifying different, less costly, or quicker solutions than have been
identified through the retrofit study. Given the urban nature of the study
area, it is a fair assumption that the sources are comprised of contributions
from domestic pets, urban wildlife, water fowl and possibly human sources.
Regardless of the proportional contributions, the measures to address these
sources would not change (e.g., discouraging water fowl concentrations,
existing by-laws, tracking and removal of cross-connections, etc.). |
Open House #2 |
Public December 5, 2010 |
I
was less enthusiastic regarding the level of recognition of the critical need
to significantly restore natural landscape values. It was good to highlight
three areas where 'daylighting' was readily do-able in order to free
significant portions of the creek from its entombment - but that was it.
There was no discussion of widening natural vegetation buffers along the
creek bank where they exist and of re-establishing them where they don't
presently. No discussion either of 'naturalizing' freed creek sections;
suggestions there was no room for re-establishing meanders (not correct in at
least the Carling Ave - Richmond Road section), or the establishment of side
pools and such. There's room for a lot more creativity to be injected into
this. The
biggest problem, though, is that creek naturalization and day-lighting is NOT
presently included in any of their solution alternatives. Ironically, it
seems that restoration of the creek itself is treated largely as a motherhood
'wouldn't-it-be nice' objective within the watershed management concept.
Remarkable, really, when the costs for undertaking such enhancements could be
largely if not entirely absorbed within construction programs related to upgrading
existing transportation facilities within the corridor. Day-lighting
(and naturalization) of significant sections of the creek must be an
over-riding focus of all management alternatives, something that is factored
into whatever happens in this watershed. Since this study represents the
pilot project for subsequent urban subwatershed studies in this city it would
be especially uninspiring if what is increasingly being seen across North
America as a vital component of urban waterway management received only
lip-service in the rehabilitation plan for our most urbanized watershed. If
it isn't going to happen here, it won't happen anywhere.This creek has been
in this unnatural transformed condition for less than 50 of its several
thousand years of life. The creek itself, not just the watershed, has got
tobe fixed for all sorts of economic, social and environmental reasons. |
A
key objective identified early in the study is to: Protect,
enhance or rehabilitate natural features and functions along the Pinecrest
Creek corridor (see Table 2.1 in Part B, Objectives and Targets).
However, given the existing degraded conditions, it
was determined that the immediate focus should be on mitigating the impacts
of uncontrolled runoff (water quality and quantity) that will contribute to
longer-term objectives and targets such as re-establishing and improving
aquatic habitat. With respect to
daylighting, the scope of this study was limited to the very preliminary step
of assessing physical feasibility. The preliminary work completed indicates
considerable potential as indicated by the cross-sections prepared. Given the
depth of the existing pipe, there may be some constraints related to
necessary side sloping and the desire to avoid retaining walls or other
hardened features. If/when daylighting is implemented in future, however, it
is recognized that re-creating natural features and functions (to the extent
possible) must be a key design outcome in keeping with the study objective
noted above. |
|
NCC: Correspondence dated
January 19, 2011 |
The NCC seeks clarity on
whether all seven objectives are equal or whether some have greater priority,
both in terms of policy and in investment. In particular, the NCC seeks
clarity on whether the SWM quantity and quality objectives for Pinecrest
Creek are considered to be equal to the water quality objectives for Westboro
Beach. |
The targets and objectives
for the study have been developed to cover the broad range of factors that
affect the overall “health” of both Pinecrest Creek and the receiving Ottawa
River (i.e., in the vicinity and downstream of the creek confluence with the
river). As such, there was no intent to rank or prioritize particular
objectives and targets given that many are inter-related or complementary.
For example, reducing runoff volumes will contribute to reduced erosion in
the creek as well as contribute to improved water quality. |
|
NCC |
Prior to accepting any end
of pipe solution on NCC property, the City must be able to demonstrate a
proactive commitment to ensure that programs to address improvements at the
lot level and conveyance level will be developed, implemented and maintained
to ensure their ongoing performance.
Education and outreach programs appear to be very important in this
regard. It may be necessary to review
how the Ontario Ministry of the Environment views lot level and conveyance
measures in its approval process for end of pipe facilities to determine if
this is a hindrance or deterrent to the adoption and implementation of such
measures (i.e., are lot level and conveyance measures excluded from SWM pond
sizing calculations) as well as if there are any potential solutions. |
Acknowledged. With respect to the
Ministry of the Environment’s approval process, no hindrance is anticipated
given that the proposed end-of-pipe facilities are retrofits (i.e., not
greenfield applications) and further, part of an overall retrofit strategy
that includes both lot level and conveyance measures. In other words,
implementation of the proposed end-of-pipe facilities does not preclude the
need for lot level and conveyance measures to achieve the various targets and
objectives. For example, reducing runoff volumes can only be accomplished via
lot level and conveyance measures. |
|
NCC |
The NCC is not currently
able to agree in principle to the recommended retrofit scenario since it is
too early to determine if such a very clear demonstration of a proactive
commitment by the City to ensure that programs to address improvements at the
lot level and conveyance level will be developed, implemented and continued. |
Acknowledged. |
|
NCC |
Cost and ease of
implementation must not be the only factors in choosing to site any facility
or structure on NCC property. Alternatives, such as other public and private lands
should also be examined. |
Acknowledged. One of the
end-of-pipe facilities proposed (EOP 3) has been located within a City park
(Elmhurst Park). |
|
NCC |
The NCC will be writing a
separate letter to discuss the potential cumulative effects of the proposed
SWM ponds in addition to the effects of the proposed West Transitway
extension from the SW Transitway (Pinecrest Creek corridor) to Pinecrest Road
and the proposed extension of light rail from Bayview Station to Baseline
Station. Such major interventions would require a comprehensive approach to
the corridor including a landscape demonstration and naturalization plan as
well as fisheries strategy. |
Acknowledged. |
|
NCC |
Ownership and
responsibility for drainage and infrastructure in several areas is not agreed
between the City and the NCC. This should be clarified for this project and
will be a requirement should larger projects occur on NCC property. For any
new infrastructure, the City shall be responsible for its operation and
maintenance, and any study should include the real estate costs associated
with the use of lands not owned by the City. |
Acknowledged. The City would be wholly
responsible for the operation and maintenance of any future end-of-pipe
facilities implemented on NCC property. |
|
NCC |
We encourage the City to
create an inventory of possible sites not just a list of preferred
sites. As part of any specific
proposal, alternative sites should be examined, including other public lands,
such as City of Ottawa and school board lands. |
For this initial study, a
total of 18 sites were screened down to the four sites recommended in the
preferred Moderate retrofit scenario (see Table H1 in Appendix H). However,
prior to proceeding with the implementation any end-of-pipe facility, further
study would be required, including a more detailed examination of location
alternatives (that was beyond the scope of this Master Plan level study). |
|
NCC |
We also encourage the City
to continue its efforts in studying the urban tree cover and where
improvements can be made to improve both the urban forest but also stormwater
management. |
Acknowledged. |
|
NCC |
The NCC encourages the City
to develop and adopt SWM criteria such as those developed for the 2010
Pinecrest/Centrepointe SWM Criteria Study to ensure that development
applications under the Ontario Planning
Act create opportunities to achieve the objectives of the Steps 3 and 4
Study. |
Stormwater management
criteria for new/infill and re-development sites will be provided in the
final study report (similar to those developed in the Pinecrest/Centrepointe
SWM Criteria Study, JFSA/JTBES,
February 2010). |
|
NCC |
The NCC would like to
ensure that if some or all the SWM measures were realized that the resulting
water and sediment regime in Pinecrest Creek would be compatible with the
Creek’s fluvial geomorphology and not cause or require major redesign efforts
changes at the NCC’s cost. The NCC
would like the final study to comment if the Creek will have to be redesigned
or further fluvial geomorphology rehabilitation measures and to what extent
if some or all of the SWM measures are implemented. |
This concern has been
addressed in the final report (see section 3 in Part D of the main report and
noted in Appendix K). |
The Study does not address
the effects of the multi-cell culverts in the Creek. This merits mention in the report and where
it may be potentially addressed. There
is potential for this to be addressed as part of the City’s transitway
proposals. We encourage your study to
provide guidance should the Pinecrest Creek corridor be selected. |
Multi-cell culverts and
their impacts on Pinecrest Creek have been addressed in the 2007
JTBES/JFSA/LGL study for the NCC and again in the 2009 JTBES study for the
City, and a protocol has been developed for use by the NCC so there is lots
of information out there that both NCC and the City should be aware of. That
said, this really was not part of the scope of this project and the impacts
may need to be addressed fully again at the implementation study stage. |
||
Ottawa River Parkway Corridor: The
study proposes a SWM facility on NCC property near the Ottawa River, which
would, according to the study, assist in improving the water quality at
Westboro Beach. In addition, any proposal for a SWM pond on NCC property near
the Ottawa River must include a very thorough analysis of alternative sites,
including those not on NCC property. Cost and ease of implementation must not
be the only factors in choosing to site any facility on NCC property. Other
requirements include: ·
Landscape and
naturalization design must be to a very high standard and context sensitive ·
A cultural
landscape analysis of effects may be required ·
An application
for Federal Land Use and Design Approval must be submitted ·
NCC is
concerned about the City’s (or any other public agency) ability to maintain
any surface SWM ponds ·
Shoreline and
stream enhancements will be necessary |
All requirements
acknowledged and to be incorporated in future implementation (EAs, detailed
design, etc.) of any end-of-pipe facilities proposed to be located on NCC property.
|
||
|
NCC |
Pinecrest Creek Corridor: The study proposes at least two SWM ponds within the
corridor and potentially a third. ·
Landscape and
naturalization design must be to a high standard and context sensitive. ·
An application
for Federal Land Use and Design Approval must be submitted ·
NCC is
concerned about the City’s (or any other public agency) ability to maintain
any surface SWM ponds |
All requirements
acknowledged and to be incorporated in future implementation (EAs, detailed
design, etc.) of any end-of-pipe facilities proposed to be located on NCC
property. |
Daylighting potential: The NCC is
very supportive in principle of daylighting opportunities where vegetation
and views would not be affected and the opportunity to reintroduce an open
air creek would support naturalization efforts. Any daylighting project should respect
natural channel design principles and include a landscaping and
naturalization component. |
All requirements
acknowledged and to be incorporated should daylighting of the creek be
implemented in future. |
||
|
City of Ottawa SWM Section, comments dated March
9, 2011 |
3.1.1
Lot Level Private and Public Controls Rain
barrels and Cisterns The
proposed BMP’s are highly dependable on home owner’s long term participation.
Can you please demonstrate with the help of some statistical data that would
indicate the effectiveness of these practices in long-term? (City of Ottawa launched in 2003 a Rain
Barrel Program, 400 rain barrel units were sold, the addresses of the houses
are still available in the City’s file.) |
It is recognized that,
beyond the Water Links effort referenced, there is minimal local knowledge
and experience related to long-term participation on the part of individual
homeowners. That experience and knowledge cannot be expanded without further
efforts that were beyond the scope of this preliminary study, the main
purpose of which was to provide a direction forward. This has been identified
in the study’s implementation plan that recommends further initial steps to
study and test the effectiveness of various lot level measures via pilot
efforts as wells as the willingness of the public to participate, etc. |
Porous and Permeable Pavement Provide
us with a few examples of implementation of those BMP’s used in equivalent to
the City of Ottawa climate conditions.
(Cold winters, clogging conditions, frost heave…) |
There has been considerable
progress made in the application of these types of measures in cold climates
in recent years. A recent literature review of this experience is provided
here: http://www.sustainabletechnologies.ca/Portals/_Rainbow/Documents/SW_Infiltration%20Review_0809.pdf It is also recognized that,
prior to broader application, it will be essential to pilot these measures in
Ottawa to gain local experience and this recommendation has been made in the
study’s implementation plan. |
||
|
City of Ottawa SWM Section |
3.1.2
Conveyance Controls Grass
Swales, Infiltration Trenches Implementation
of infiltration trenches and swales are highly dependable on soil
conditions. Please demonstrate that
these controls would function in the Pinecrest subwatershed since the Soil
Map indicates mostly clay conditions. |
Acknowledged. There are
limitations to the application of some selected measures, and this will be
accounted for accordingly via the preparation of design standards for such
measures (as recommended in the study’s implementation plan). |
3.1.2
Conveyance Controls Street
Narrowing Street
narrowing practice should be discussed with the Surface Operation in term of
accessibility. (i.e. snow removal) |
Agreed. The purpose of this
study was to identify a proposed “suite” of measures that could achieve water
quality improvements and runoff volume reductions. Further study and consultation with City
staff and the public will be required to identify specific locations in the
study area where such measures can be feasibly implemented. |
||
3.1.1.3
End of
Pipe Facilities Oil
and Grit Separators It
is inappropriate to specify singular brands of OGS’s within this report.
Either remove the singular reference or provide numerous more manufactures
examples. Maintenance
aspects are also very important factors regarding the brand selection. |
Agreed. Agreed. Upon implementation
of the proposed OGS’, the Stormwater Management Section will be consulted to
ensure operation and maintenance requirements are addressed. |
||
3.3.
Stormwater Retrofit Scenarios Has
the consultant considered some other alternative options such as the use of
City’s existing parklands? |
One of the end-of-pipe
facilities proposed (EOP 3, an oil grit separator) has been located within a
City park (Elmhurst Park) and other park locations were considered but
screened out. However, prior to the implementation of any end-of-pipe
facility, alternative locations will be revisited again in more detail via
the required Class EA process. |
||
4.1
WindSlamm Modelling Baird
& Associate Ltd Report: Assessment of the Relative Impact of SWM Retrofit
Alternatives Developed for The Pinecrest Creek Study Can
you please provide a comparison of results generated by the WinSlamm modeling
and the Baird’s Assessment report (Pg 23- 5.0 Conclusions- 1st
bullet) |
The WinSLAMM modeling was used
to generate E. coli loading from
the study area (Pinecrest Creek and the Westboro outfalls) for the existing
condition (no retrofits) and then adjusted to reflect the various retrofit
scenarios. These resulting “pollutographs” were then input to the hydrodynamic
model of the Ottawa River to model the effect of this E.coli loading at Westboro Beach (that could not be assessed by
WinSLAMM). In other words, the WinSLAMM results represent the wet weather
input to the river model, which then simulated the resulting E.coli counts at the beach. |
||
5.2 SWMHYMO Models Can you please provide a better explanation of Table 5.2 –Improvements
in Producing a More Natural Hydrologic Cycle Within Pinecrest Creek, since
this is maybe a “Key Selling Factor” in order to secure a Capital Budget. |
Table 5.2 is a summary of
the benefits of implementing SWM retrofit measures that reduce runoff volume.
Since the study area is almost completely urbanized, existing runoff volumes
are much higher and have impacted the creek over the last several decades.
Aiming to reduce the runoff volume for relatively frequent rainfall events
will result in a more “natural” hydrologic cycle than now exists. |
||
5.4.1. Existing Hydraulic Conditions Please clarify the 4th paragraph from the top “All proposed
Scenarios produce lower peak flows than the existing conditions.” This does not correspond to your statement
quoted in the report Pinecrest/Centrepointe Stormwater Management Criteria –
Page17, 5.1 Flood Control -Recommended SWM Criteria for Quantity Control for
Flood Control Purposes on the Pinecrest Creek: “All future Development shall
control their 1:100 year peak flow to 36 l/s/ha in order to maintain the
existing1:100-year peak flows in the creek”. |
This statement is based upon the
implementation of the proposed retrofit end-of-pipe facilities that will
provide some quantity/flood control if/when they are eventually implemented,
in particular the facility at Baseline and Woodroffe (EOP 16). These retrofit
facilities were not modeled during the preparation of the
Pinecrest/Centrepointe Town Centre SWM Criteria Study (JFSA, JTBES, 2010) as
they had not yet been identified (a task that was beyond the scope of that
study). The recommended retrofit
end-of-pipe facility does not preclude the need for the quantity control
criterion recommended for new/infill/redevelopment since it is uncertain when
this facility will ultimately be built. In the interim, increased flood
levels and risk resulting from new development must be prevented. However,
if/when this facility is implemented in future, then the required quantity
control criterion will revisited and potentially eliminated if it can be
shown that the flood control benefits of the pond are adequate to compensate
for the remainder of anticipated future development at that time. |
||
Table 5.4.1.-Level of
Service of the ORP pipe Can you please clarify the meaning of the 2-year Level of Service of
the Ottawa River Parkway culvert and the following interpretation in Table
5.4.1 |
This table indicates that,
under existing conditions, peak flows beyond the two year event will not be
fully conveyed by the piped section but will spill onto the Parkway. With the
implementation of some retrofit quantity control storage, the level of
service of the piped section can be improved. |
||
7.0 Costing of Scenarios We have noticed that the in-stream works were not a part of the
retrofit‘s alternative costing analysis. Maintenance cost should be adjusted
accordingly to confirm the values provided by the “TCAR study.” |
The
identification of potential future stream rehabilitation works was beyond the
scope of this study. However, significant amounts of such works are not
anticipated since the overall objective is to reduce erosion and maintain or
improve stability. If/when major works proceed (e.g., proposed SWM facility
at Baseline/Woodroffe), the need for any associated in-stream works would be
identified at that time (and this requirement has been identified in the
implementation plan). |
COMMENTS RECEIVED FROM
OPEN HOUSE No. 1 DOCUMENT 12
Pinecrest Creek/Westboro
Stormwater Management Retrofit Study
Open House and Information
Session #1
December 3, 2009
Meeting Notes
Introduction
In the fall of 2009, the City of Ottawa launched the Pinecrest Creek/Westboro Stormwater Management Retrofit Study to identify a Retrofit Plan to improve stormwater management in Pinecrest Creek subwatershed and the adjacent Westboro area. The Retrofit Study is one of sixteen short-term projects included in the City’s Ottawa River Action Plan and is being conducted as a Master Plan under the Municipal Class Environmental Assessment process.
The Pinecrest Creek/Westboro area – like much of the core of the City –
was developed before there was a requirement for municipalities to manage
stormwater. For this reason, there are few facilities to treat stormwater in
the study area. When it rains, stormwater collects on roofs, roads and parking
lots, is transported in storm sewers and then is discharged into Pinecrest
Creek or directly into the Ottawa River, carrying a host of pollutants with it.
Uncontrolled stormwater leads to large volumes of runoff and high peak flows in
streams. This affects water quality, exacerbates erosion, degrades fish
habitat, threatens infrastructure, and contributes to beach closures at
Westboro Beach.
When implemented, the Pinecrest Creek/Westboro Stormwater Management
(SWM) Retrofit Strategy will help to:
· improve water quality in Pinecrest Creek and the Ottawa River;
· reduce flooding and erosion in the Creek;
· improve the health of the Creek; and
· reduce closures at Westboro Beach.
The City hosted the first Open House for the project on December 3, 2009 from 6:30 to 9:30 pm at the Ben Franklin Centre. The focus of the Open House was Existing Conditions in the study area and the objectives of the retrofit strategy. A display provided highlights of the work carried out to date, and the study team gave a presentation at 7:30 pm, which was followed by a question and answer session. In total, 14 people attended the Open House.
This meeting report was prepared by Joanna Kidd, meeting facilitator and is intended to reflect the major comments, suggestions and questions raised at the meeting and in Comment Forms. Any errors or omissions are the work of the author.
Presentation
Facilitator, Joanna Kidd from Kidd Consulting reviewed the agenda and introduced key members of the study team. Darlene Conway from the City of Ottawa provided an overview of the rationale for the SWM Retrofit Study. The absence of stormwater management facilities in the study area causes large volumes of stormwater run off and high peak flows to Pinecrest Creek. This degrades water quality, increases erosion, degrades fish habitat, threatens infrastructure and contributes to closures at Westboro Beach. Darlene reviewed the objectives of the SWM Retrofit Strategy which are to:[1]
1.
Reduce
flood risk to public health and safety and to property along the Pinecrest
Corridor.
2.
Reduce
erosion impacts in the Pinecrest Creek corridor that are detrimental to
property, infrastructure and stream habitat.
3.
Preserve
and/or re-establish a more natural hydrologic cycle for the Pinecrest Creek
subwatershed.
4.
Improve
water quality in Pinecrest Creek and the Ottawa River by reducing the impact of
stormwater runoff.
5.
Reduce
the impacts of stormwater runoff on Westboro Beach.
6.
Protect,
enhance or rehabilitate natural features and functions along the Pinecrest
Creek corridor.
7.
Increase
public awareness about and involvement in stormwater management.
Darlene noted that the study will look for opportunities to retrofit
stormwater management controls into the existing community, and will consider
lot level, conveyance and end-of-pipe measures, along with stream
rehabilitation. The study will define a range of retrofit scenarios, evaluate
how well they meet the study objectives, and identify a Preferred Retrofit Plan
for the Pinecrest Creek/Westboro area.
Heather Wilson from J.F. Sabourin &
Associates provided information on the existing conditions in the study area
and began with a virtual tour that followed Pinecrest Creek from its headwaters
to its confluence with the Ottawa River and then along the Ottawa River
downstream to Westboro Beach. Water
quality in Pinecrest Creek is characteristic of urban watercourses, and
levels of bacteria, chlorides, nutrients and heavy metals in the Creek
frequently exceed the Provincial Water Quality Objectives. While water quality
in the main section of the Ottawa River is good, water quality at Westboro
Beach often exceeds the swimming guidelines. With respect to hydrology, she noted that Pinecrest
Creek is the most urbanized subwatershed in the city, with 36% of the area
covered by hard surfaces. Because of this, the Creek has a “flashy” response to
rain: during a small rainfall event (about 10mm), flow velocities in the creek
can triple in less than 15 minutes and erosive forces can increase by over
450%.
John Beebe from JTB Environmental
Systems provided an overview of stream
processes. The banks of the Creek are generally well-vegetated, but bank
erosion and channel downcutting are common along many reaches, He provided a
number of photographs of parts of the Creek where this was occurring, along
with images of some of the stream restoration work that has been undertaken by
the National Capital Commission.
Heather reviewed soils and hydrogeology, noting that soils tend to be thicker in the
southern and western parts of the study area. With respect to terrestrial and aquatic ecology, she
noted that forest cover makes up less than 3.8% of the study area. Aquatic
habitat is degraded because of uncontrolled stormwater runoff. Fish surveys
found four species in 1993, but only 1 in 2000. In terms of the built
environment, the study area is drained by separated sewers, partially separated
sewers and roadside ditches. There are only 8 stormwater management facilities
in the study area, and there are 9 major stormwater outfalls in the Creek
corridor and 10 along the Ottawa River.
Heather finished by outlining some of
the inventory and database work that has been done to date. This includes the
identification of infrastructure in the stream corridor, the assessment of
flood risk, measurements of water levels and flows, and lot level surveys.
Joanna finished the presentation by outlining the
next steps in the planning process which include:
·
Public
Advisory Committee meeting (January 2010);
·
assessment
of scenarios and development of a Preferred Retrofit Plan (January to April
2010);
·
Open
House #2 and finalization of Retrofit Plan (Spring 2010);
·
30-day
review period (Summer 2010); and
·
commencement
of implementation of Retrofit Plan (2011).
Discussion
Treatment
of Stormwater
In response to a question about whether
the study would look at end-of-pipe treatment for stormwater as well as
reduction in volume of stormwater runoff, the following points were made:
·
The
study has multiple objectives;
·
A
major objective is to reduce the amount of stormwater entering the Creek and
slow down the release of stormwater into the Creek through use lot level,
conveyance and end-of-pipe SWM measures;
·
The
study will also be looking at ways of improving the quality of stormwater
entering the Creek and Ottawa River through the use of stormwater settling
ponds and technologies such as Dunker’s Flow Balancing; and
·
Other
non-stormwater management actions, such as waterfowl management and increased
riparian plantings will also contribute to improved water quality.
Measurable
Outcomes
In response to questions about
measurable targets relating to the Objectives, the following points were made:
·
Measurable
targets for each Objective have been or will be set to track and measure
progress;
·
Many
of the targets are derived from objectives set in the Lower Rideau Watershed
Strategy and the City’s stormwater management policies;
·
The
targets include Provincial Water Quality Objectives for water quality;
·
There
are no currently no Provincial standards for water quality at the outflow of
Pinecrest Creek;
·
The
modeling in the study will predict what the water quality will be at the mouth
of Pinecrest Creek with the implementation of SWM Retrofit measures; and
·
Baird
and Associates will insert these values into their Ottawa River model to
predict the impact on Westboro Beach water quality.
Value
for Money
In response to a question about the
value of spending millions of dollars to gain 4 or 5 more days of swimming at
Westboro Beach, the following points were made:
·
Improving
water quality at Westboro Beach is only one of 7 Objectives;
·
Reducing
the amount and timing of runoff into the Creek will address all of the
objectives;
·
A
more stable Creek will provide multiple benefits including the protection of
infrastructure; and
·
A
participant noted that an improved Pinecrest Creek Corridor could serve as an
outdoor learning centre for schools in the area.
Potential
for Daylighting the Creek
In response to a question about the
potential for daylighting (opening up) parts of the Creek that are now buried,
the following points were made:
·
The
study is considering the potential for daylighting parts of Pinecrest Creek;
·
The
Retrofit Plan will be a long-term plan, as it will take time to undo the
impacts of decades of development; and
·
A
participant shared an aerial photo from 1945 that showed the downstream reaches
of the Creek were still in an open, meandering state at that time. A copy of
the photo will be provided to the study team.
Potential
for Stormwater Management Ponds
In response to a question about the
potential for developing SWM ponds in the study area, the following points were
made:
·
The
study is looking at potential sites for retrofit SWM ponds;
·
Infill
and redevelopment projects in the study area will also be required to implement
SWM measures to meet the objectives of the Retrofit Plan; A participant
suggested that land near the confluence of the Creek and the River that had
been set aside to provide SWM for stormwater from outside the study area be
used for SWM from Pinecrest Creek / Westboro. The study team will investigate
the feasibility of this.
Ponding
A participant noted that there was
sometimes ponding of water between Carling Avenue and the River. The study team
will investigate.
Transport
of Contaminants from Land
In response to a question about whether
the study was investigating the first flush of contaminants from the land, the
following points were made:
·
From
a water quality perspective, the study is focusing on smaller, more frequent
rainfall events (e.g., events in the order of less than 25mm of rainfall); and
·
It
is generally accepted (based on numerous monitoring studies throughout North
America) that these smaller events are responsible for most of the wash off of
contaminants into water bodies.
Raising
Public Awareness
A number of points were made about
public awareness:
·
There
is a need to educate upstream communities about downstream effects of
pollution;
·
There
is a need to build interest in the community in the study.
Notification
of the Open House
In response to a question about how
notification was made of the Open House, the following points were made;
·
Notification
included ads in the Ottawa Citizen and local papers, invitations to e-mail
lists, a presentation at a city-wide meeting of residents’ associations (CAFES)
and material handed out at the recent Open Houses for the Ottawa River Action
Plan; and
·
A
participant suggested that more promotion should be done for future events.
Improving
Forest Cover
In response to a question about whether
the study is considering improving forest cover in the study area, the
following points were made:
·
The
study is looking at how urban tree canopy can be enhanced and the impacts of
doing so;
·
Enhancing
the tree canopy has multiple benefits; and
·
A
participant noted that the National Capital Commission has held two tree
plantings in the area and is interested in doing additional plantings.
Stormwater
Management in New Developments
In response to a question as to whether
the City would be requiring stormwater planning similar to what was done for
recent development in the Centrepointe area, e.g. applying those requirements
to other new developments, the following point was made:
The Retrofit Plan will provide SWM guidelines that new development will
be required to meet (e.g., for water quality/quantity control and runoff volume
reduction).
Other Feedback Received
Comment forms were available for participants to
make additional comments. Completed forms were received from five people. Four
of the five respondents live in the study area. Comments are provided below.
Information
on Existing Conditions
·
Long-term
compromised nature of the watershed (beginning in the 1920s).
·
Are
familiar with some of the work carried out at Algonquin College.
Comments
on the Objectives
·
The
study should look at “bang for the buck”. For example, what impact would
reducing downspout disconnections have on stream quality? What impact would a
SWM pond at X location have? And what would be the costs?
·
An
objective should be to liberate the creek (open it up).
·
The
naturalization of bank vegetation should be emphasized.
·
The
priority should be on improving water quality.
Other
Comments on the Study
·
The
existing SWM area at the mouth of the Creek should be utilized.
·
Would
like to see significant improvements in water quality – should consider the use
of SWM retention ponds.
·
Lack
of public interest/awareness. More people will be interested once a dollar
figure is better known and it ends up on our tax bill.
·
Cost
of the project with minimal returns.
·
Accurately
measuring the effectiveness of any retrofit.
·
What
are other Ontario and North American cities doing concerning SWM?
Open House and Information
Session #2
December 1, 2010
Meeting Notes
Introduction
In the fall of 2009, the City of Ottawa launched the Pinecrest
Creek/Westboro Stormwater Management Retrofit Study to identify a Retrofit Plan to improve stormwater management in
Pinecrest Creek subwatershed and the adjacent Westboro area. The Retrofit Study
is one of sixteen short-term projects included in the City’s Ottawa River
Action Plan and is being conducted as a Master Plan under the Municipal Class
Environmental Assessment process.
The Pinecrest Creek/Westboro area – like much of the core of the City –
was developed before there was a requirement for municipalities to manage
stormwater. For this reason, there are few facilities to treat stormwater in the
study area. When it rains, stormwater collects on roofs, roads and parking
lots, is transported in storm sewers and then is discharged into Pinecrest
Creek or directly into the Ottawa River, carrying a host of pollutants with it.
Uncontrolled stormwater leads to large volumes of runoff and high peak flows in
streams. This affects water quality, exacerbates erosion, degrades fish
habitat, threatens infrastructure, and contributes to beach closures at
Westboro Beach.
When implemented, the Pinecrest Creek/Westboro Stormwater Management
(SWM) Retrofit Strategy will help to:
·
improve
water quality in Pinecrest Creek and the Ottawa River
·
reduce
flooding and erosion in the Creek
·
improve
the health of the Creek and
·
reduce
closures at Westboro Beach
The City hosted a second Open House for the project on December 1, 2010
from 6:30 to 9:30 pm at the Churchill Seniors Centre. The second Open House
focused on how future stormwater management retrofit scenarios were identified
and evaluated and what the proposed Stormwater Management Retrofit Strategy
would mean for the creek and river, the community and the City. A display provided highlights of the work
carried out to date and City staff and members of the study team were on hand
to answer questions. The study team gave a presentation at 7:30 p.m., which was
followed by a question and answer session. In total, 8 people attended the Open
House.
This meeting report was prepared by Joanna Kidd, meeting facilitator
and is intended to reflect the major comments, suggestions and questions that
were raised at the meeting, in Comment Forms and in emails received after the
meeting. Any errors or omissions are the work of the author.
Presentation
Facilitator, Joanna Kidd from Kidd Consulting reviewed the agenda and
introduced key members of the study team. Darlene Conway from the City of
Ottawa provided an overview of the rationale for the SWM Retrofit Study. She
noted that the absence of stormwater management facilities in the study area
causes large volumes of stormwater to run off resulting in high peak flows to
Pinecrest Creek. This degrades water quality, increases erosion, damages fish
habitat, threatens infrastructure and contributes to closures at Westboro
Beach. Darlene noted that the Pinecrest Creek/Westboro Stormwater Management
Retrofit Study is one of the projects included in the City’s Ottawa River
Action Plan, and is a pilot project for a City-wide strategy to retrofit
stormwater management measures.
Heather Wilson from J.F. Sabourin & Associates began by reviewing
the impacts of uncontrolled stormwater runoff and the seven objectives of the
study. These are to:[1]
1.
Reduce
flood risk to public health and safety and to property along the Pinecrest
Corridor.
2.
Reduce
erosion impacts in the Pinecrest Creek corridor that are detrimental to
property, infrastructure and stream habitat.
3.
Preserve
and/or re-establish a more natural hydrologic cycle for the Pinecrest Creek
subwatershed.
4.
Improve
water quality in Pinecrest Creek and the Ottawa River by reducing the impact of
stormwater runoff.
5.
Reduce
the impacts of stormwater runoff on Westboro Beach.
6.
Protect,
enhance or rehabilitate natural features and functions along the Pinecrest
Creek corridor.
7.
Increase
public awareness about and involvement in stormwater management.
She then
reviewed how the study was carried out.
Step 1: Background Information and Inventory
In Step 1, the study team collected
background information on existing conditions in the study area. This included
information on soils, land uses, development types and existing stormwater
management measures.
Step 2: Develop Stormwater Management Objectives and Targets
In Step 2, objectives were developed for the
study and numerical targets were set for the objectives.
Step 3: Identify Potential Stormwater Management Measures and Scenarios
In Step 3, the study team pre-screened a long
list of potential stormwater management measures for suitability and
effectiveness in the study area. Any that were not cost-effective, or which had
significant negative environmental or social impacts were eliminated from
consideration. The remaining measures were used in the development of future
scenarios. The stormwater management measures on the “short list” included “at
source” measures (downspout disconnection or redirection, rainbarrels and rain
gardens), “conveyance” measures (infiltration trenches and street narrowing),
and “end-of-pipe” measures (oil and grit separators and stormwater management
ponds). The study team then developed four scenarios that represent a range of
level of effort in retrofitting stormwater management measures. These were
compared with the existing condition. The future scenarios were:
Step 4: Evaluate the Scenarios
against Key Factors
In this Step, the study team used modelling to determine the relative
effectiveness of the scenarios in removing the key pollutants (Total Suspended
Solids, Total Phosphorus and E. coli
bacteria) and reducing the rate of runoff. Modelling was also used to determine
the reduction of E. coli at Westboro
Beach. The scenarios were evaluated against the following criteria:
Water quality Aquatic
habitat
Runoff impacts at beach Open space/parks
Flood risk Terrestrial
systems
Erosion impacts Natural features
Hydrologic
cycle
Step 5: Select Preferred
Retrofit Scenario
Heather noted that the “Moderate Implementation” scenario was selected
as the preferred Retrofit Scenario because it:
Heather also noted that the much higher cost for the Highest Practical
Implementation scenarios does not provide a proportional increase in benefits
relative to the Moderate Implementation scenario.
She reviewed the elements of the preferred Retrofit Plan, which
includes the installation or construction of:
·
Daylighting
·
Heather
noted that there are three locations in which there is sufficient physical
space to daylight parts of the now-buried sections of Pinecrest Creek that
begin just south of Carling Avenue. There are a number of constraints on these
areas, and additional work is required to assess these constraints.
·
Next Steps
·
Heather
finished her presentation with the next steps which include:
December
2010 - February 2011
Spring
2011
Fall
2011
·
Begin
implementation of Retrofit Plan
Discussion
·
Ditches and
Swales
·
On
Tweedsmuir Avenue, the City is replacing roadside ditches with storm sewers,
which flies in the face of the need to manage stormwater better.
·
The
City of Ottawa does have a Ditch Infill policy that discourages ditch infilling
and/or requires that if ditches are to be replaced that the new drainage system
provide the equivalent benefits of ditches.
·
The
Pinecrest Creek/Westboro Stormwater Management Retrofit Study will help
demonstrate the value of retaining roadside ditches and swales.
·
Road Narrowing
·
The
community was pushing for road narrowing on Tweedsmuir for traffic calming
reasons, but the City wanted it wider.
·
Some
street narrowing designs can be a problem for cyclists.
·
Street
narrowing can be done on a block-by-block basis and needs to balance many issues.
·
End-of Pipe
Treatment
·
If
the NCC does not allow stormwater management ponds on its property, the
benefits of the Moderate Implementation scenario will be reduced.
·
There
may be other opportunities for retrofitting end-of-pipe facilities, such as
McKellar Park.
·
The
study team will document all potential locations for end-of-pipe facilities.
·
There
may be community support for putting oil and grit separators (for example)
underneath parks.
·
It
is good that the City is embracing a range of stormwater management measures
and is not planning to rely only on large stormwater management ponds.
·
Terrestrial
Habitat
·
The
City should take an aggressive approach to restoring habitats in the Pinecrest
corridor, including naturalized buffers.
·
This
should include not allowing more structures in the corridor.
·
Daylighting
·
Daylighting
the creek is very important and the City should be more optimistic about the
potential to daylight.
·
Evaluation
Criteria
·
Improving
the natural environment should be the overriding objective of the study.
·
Policy Coherence
·
The
City should develop a coherent policy for stormwater management that is applied
to all development proposals. This needs to be communicated to all departments,
including the Building Department.
·
Incentives
·
The
City should consider providing incentives for high cost actions such as the
replacement of impervious surfaces on driveways with pervious surfaces.
·
Preferred
Retrofit Scenario
·
A
number of participants noted that they supported the general direction and the
selection of the Moderate Implementation scenario.
·
The
Westboro Community Association will promote the use of rainbarrels to its
members.
·
Implementation
·
It
is vital that implementation of the strategy takes place.
Other Feedback Received
·
Comment
forms were made available at the Open House for participants to make additional
comments. Completed forms were received from two people and email comments were
received from three others. The comments are summarized below.
·
Support
All five people
indicated their general support for the proposed Retrofit Plan. Specifically,
support was expressed for:
·
The
general approach being taken for retrofitting stormwater management measures;
·
Not
relying too much on end-of-pipe treatment;
·
Placing
a lot of emphasis on lot level controls on private land;
·
The
use of rainbarrels, downspout re-direction, rain gardens and use of pervious
products on driveways when they are re-done;
·
Rehabilitation
of the creek corridor, which is important for the quality of human and natural
life in the watershed; and
·
Identifying
where the creek can be daylighted.
·
Concerns
·
Concerns
raised included the following:
·
The
lack of consideration of restoration of the natural landscape in the study
(e.g., widening existing natural vegetation buffers along the creek, re-establishing
vegetation where it doesn’t presently exist, tree-planting, and naturalizing
daylighted creek sections);
·
That
creek naturalization and daylighting are not an overriding focus, and are not
included in any of the alternative scenarios being considered;
·
Locating
a stormwater management pond near the Ottawa River is unrealistic;
·
The
study does not address any aspects of the sources of E. coli in stormwater and what could be done to reduce a given
source immediately; and
·
Concern
about impact of rainbarrels on moisture levels around the foundations of
houses.
·
Suggestions
·
A
number of suggestions were made including:
·
Replace
the term “daylighting” with “liberating” to convey the concept of restoration
of form and function;
·
Support
a DNA phenotyping study to address sources of E. coli in the Pinecrest Creek and Westboro Beach outfalls; and
· Review the rainfall data for 2010 to look at correlation with E. coli levels at Westboro Beach (i.e., was the low number of days of beach closures related to a low number of rainfall events).