Task Name Project Contract Costs (Estimated) City’s Share OSEG’s Share Contract Administered By
Stadium/Arena  
Design costs - prime  $          6,185,583 One hundred percent (100%) of Project Contract Costs, up to $6,185,583 Zero percent 0% of Project Contract Costs OSEG
Design costs - speciality  $          2,432,137 One hundred percent (100%) of Project Contract Costs, up to $2,432,137 Zero percent 0% of Project Contract Costs OSEG
Construction costs  $          2,810,000 One hundred percent (100%) of Project Contract Costs, up to $2,810,000 Zero percent 0% of Project Contract Costs OSEG
   
Parking  
Design costs - prime  $          2,077,397 Seventy three and seven tenths percent (73.7%) of Project Contract Costs, up to $1,531,041.59 The balance of Project Contract Costs, estimated to be 26.3% of Project Contract Costs OSEG
Design costs - speciality  $          1,283,952 Seventy three and seven tenths percent (73.7%) of Project Contract Costs, up to $946,272.62 The balance of Project Contract Costs, estimated to be 26.3% of Project Contract Costs OSEG
Construction costs  $             660,000 Seventy three and seven tenths percent (73.7%) of Project Contract Costs, up to $486,420 The balance of Project Contract Costs, estimated to be 26.3% of Project Contract Costs OSEG
   
Urban Park  
Design costs - prime  $          2,426,185 One hundred percent (100%) of Project Contract Costs Zero percent 0% of Project Contract Costs City of Ottawa
Design costs - speciality  $             159,660 One hundred percent (100%) of Project Contract Costs, up to $159,660 Zero percent 0% of Project Contract Costs OSEG
Construction costs  $          1,000,000 One hundred percent (100%) of Project Contract Costs Zero percent 0% of Project Contract Costs City of Ottawa
   
Residential and Office  
Design costs - prime  $                           - One hundred percent (100%) of Project Contract Costs Zero percent 0% of Project Contract Costs OSEG
Design costs - speciality  $             487,173 One hundred percent (100%) of Project Contract Costs, up to $487,173 Zero percent 0% of Project Contract Costs OSEG
Construction costs  $                           - One hundred percent (100%) of Project Contract Costs Zero percent 0% of Project Contract Costs OSEG
   
OSEG Retail and Other  
Retail design, leasing and financing (excluding parking costs listed above)  $          4,433,604 Zero percent 0% of Project Contract Costs One hundred percent (100%) of Project Contract Costs OSEG
Sports commitment, project management, administrative, legal and other costs  $          5,466,724 Zero percent 0% of Project Contract Costs One hundred percent (100%) of Project Contract Costs OSEG
   
City of Ottawa Other  
City of Ottawa project management, legal, finance and administrative costs  $          2,525,980 One hundred percent (100%) of Project Contract Costs Zero percent 0% of Project Contract Costs City of Ottawa
   
Total summary  $       31,948,394  $                                      21,036,728  $                                      10,911,666