Branch/Division Vehicle Description Qty Project Number Estimated Capital Cost Operating Impact 2011 Requirement Prorated 2012 Balance Programming Rationale
Roads and Traffic Operations and Maintenance 
South Roads  Single Axle Combo c/w plow and wing  1  $ 270,840.00  $ 59,373.00  $       14,429  $       44,944 Addition of Strandherd extension, widening of Woodroffe, Prince of Wales, Strandherd bridge and additional roads in subdivision off Jockvale/ Bren Maur
South Roads  Single Axle Combo c/w plow and wing  1  $ 270,840.00  $ 59,373.00  $       14,843  $       44,530 Additional roads to maintain in Manotick Minto subdivision, Half Moon Bay, Riverside South, Limebank Road widening
South Roads  Asphalt Hox Box Trailer 1  $   30,528.00  $ 10,114.00  $         5,057  $         5,057 Increased  demand on surface treated roads and availabity of year round hot patching material
Special Operations Roads Four Wheel Drive Tractor complete with Snowplow Blade and Snowblower with high chute and side discharge capability (drum rotation).  1  $ 122,112.00  $ 22,440.00  $         5,610  $       16,830 City wide growth in Transitway and Park and Ride inventory of 7.6 lane kms and 1,041 Parking Stalls is expected for 2011.  In order to service the increase in roadway and parking facilities inventory, an extra tractor with blade and snowblower unit is required to complete winter plowing and removal operations to meet maintenance quality standards.
Core Roads Asphalt Hox Box Trailer 1  $   30,528.00  $ 10,114.00  $         5,057  $         5,057 Increased demand for asphalt-related repairs on hard surface roads, and availability of year-round hot asphalt material.
Core Roads Sidewalk  scrubber was 50. 1  $   80,000.00  $ 15,000.00  $         7,500  $         7,500 Increased demand to scrub sidewalks in the Byward Market and BIA areas.
West Roads  Tandem Axle Combo spreader c/w one-way plow and cable wing  1  $ 305,280.00  $ 66,925.00  $       16,731  $       50,194 Additional snow clearing and road salting/sanding associated with the additions of the Terry Fox extension, and the widening of March and Hazeldean roads.
West Roads  Asphalt Hot Box Trailer 1  $   30,528.00  $ 10,114.00  $         5,057  $         5,057 Increased  demand on surface treated roads, and availabity of year round hot patching material.
East Roads  Single Axle Combo c/w plow and wing  1  $ 270,840.00  $ 59,373.00  $       14,843  $       44,530 Additional hard surfaced roads added to inventory through gravel road upgrades - O'Toole Rd, French Hill Rd, Smith Rd, Tenth Line Rd, and Willhaven Rd.
East Roads  One (1) Ton Crew cab Pickup Truck 1  $   40,000.00  $ 11,880.00  $         5,940  $         5,940 Increased demand for ditching on upgraded gravel to hard surface roads to improve performance of road.
East Roads  Tandem Hot Box Trailer 1  $   30,528.00  $ 10,114.00  $         5,057  $         5,057 Increased demand for asphalt-related repairs on hard surface roads, and availability of year-round hot asphalt material.
East Roads  Crew cab Landscape dump  truck , towing package 1  $   80,000.00  $ 39,500.00  $         9,875  $       29,625 Year-round use as tow unit to transport staff and haul andem Hot Box Trailer.
Signs and Pavement Markings 1 Ton PU Truck- Automated Cone Holder Machine  1  $ 132,288.00  $ 26,771.00  $       10,001  $       16,770 Purchase is required to address a safety concern with the way we place and pick-up traffic cones during pavement marking opeartion. Issue has been identified through Service Excellence initiative and through Occupation Health & Safety Committee.
Signals 2 Ton Trailer ( 5,000 lbs. ) 1  $     6,614.00  $    2,306.00  $         1,153  $         1,153 Increasing traffic signals network has resulted in the saturation of the only other existing flatbed unit within Traffic Operations Branch.  This additional trailer will support the continued expansion of the traffic signals network and will permit staff to transport traffic signal materials to new and existing sites.
Signals Aerial Device - non material handler - Articulating telescopic - Low profile chassis -  1  $ 183,168.00  $ 37,832.00  $         8,847  $       28,985 Year round use as unit for the proposed 2011 "Growth" Signal Maintenance Crew as result of the increase in number of new Traffic Signals and the amount of material/equipment used in Signal System.
Traffic Management and Operational Support
Traffic Management  1/2 Ton Extended PU Trucks 4    $ 122,112.00    $                -    $                -   Replace (4) Lease vehicles  (B2-6604, B2-6605, B2-6606 and B2-6607), due July 2011, with (4) new vehicles. Short box required - factors: turning radius, length of vehicle. These vehicles will be working in the downtown core, Glebe areas etc.  Background information provided in report.  Moving to own these vehicles rather than leasing will be advantageous because the City will avoid paying high lease rates, over usage penalties, and damage penalties when the vehicle is returned to the dealer
TOTAL 19 $2,006,206 $441,229 $130,001 $311,229