de renseignements Motion Is there any update to, or new costing arising from the DOTT project? |
||
Response/Réponse Response to be listed on the Transit
Committee Agenda of November 17, 2010 and the Council Agenda of November 24,
2010 |
The
City of Ottawa has received a Provincial “Green Light” letter from the Ontario
Minister of Infrastructure for Ottawa’s Light Rail Transit (OLRT) project. This letter is step two in a three step
funding process that includes; funding announcement, green light letter, and
finally the formal contribution agreement.
This letter confirms that project costs from September 1, 2010 onwards
are now eligible for provincial reimbursement up to the $600 million announced
by the Premier on December 18, 2009.
Together with the Approval-In-Principle letter recently received from
the Federal Government, this has enabled us to commence preliminary
engineering.
As
indicated during the quarterly update to Transit Committee on August 30,
project costs remain the same at this time based
on the preliminary interpretation of the geotechnical borehole data collected
during the spring and early summer. Project cost estimates will be updated as part of the PE
process and will be presented to Council upon PE completion.
The
attached Ottawa’s Light Rail Transit
(OLRT) – Tunney’s Pasture to Blair Project Implementation Update Memo
contains further detail and a project update.