1.             MINISTRY OF TRANSPORTATION PRESENTATION ON HIGHWAY 417 - BRIDGE REPLACEMENT AT cyrville road

 

PRÉSENTATION DU MINISTÈRE DES TRANSPORTS CONCERNANT L’AUTOROUTE 417 - remplacement du pont au chemin Cyrville

 

 

 

Committee Recommendation AS AMENDED

 

That Council approve that the City urges the Province to maintain all-day lane capacity in both directions on the Queensway during the reconstruction of the Cyrville Road Bridge.

 

 

Recommandation MODIFÉE du comité

 

Que le Conseil d’approuver la décision de la Ville de faire pression auprès de la Province pour que celle-ci maintienne ouvertes toutes les voies de circulation toute la journée dans les deux directions du Queensway pendant le réaménagement du pont du chemin Cyrville.

 

 

 

 

 

 

 

 

 

 

 

 

Documentation

 

1.         Transportation Committee report dated 8 May 2010 (ACS2010-CCS-TRC-0015).

 


Report to / Rapport au:

 

Council / et au Conseil

 

8 May 2010 / le 8 mai 2010

 

Submitted by / Soumis par : Transportation Committee / Comité des transports

 

Contact/Personne-ressource:  Rosemary Nelson, Standing Committee Coordinator /
Coordonnatrice des comités permanents,
City Clerk’s Branch/Direction du greffe

580-2424, Ext. / poste : 21624, Rosemary.Nelson@ottawa.ca

 

Beacon Hill-Cyrville (11)

 

File. No. ACS2010-CCS-TRC-0015

 

 

SUBJECT:    MINISTRY OF TRANSPORTATION PRESENTATION ON HIGHWAY 417 - BRIDGE REPLACEMENT AT cyrville road

 

OBJET:             PRÉSENTATION DU MINISTÈRE DES TRANSPORTS CONCERNANT L’AUTOROUTE 417 - remplacement du pont au chemin Cyrville

 

 

 

COMMITTEE RECOMMENDATION

 

That the Transportation Committee recommend Council approve that the City urges the Province to maintain all-day lane capacity in both directions on the Queensway during the reconstruction of the Cyrville Road Bridge.

 

 

RECOMMANDATION DU COMITÉ

 

Que le Comité des transports recommande au Conseil d’approuver la décision de la Ville de faire pression auprès de la Province pour que celle-ci maintienne ouvertes toutes les voies de circulation toute la journée dans les deux directions du Queensway pendant le réaménagement du pont du chemin Cyrville.

 

 

BACKGROUND

 

On 5 May 2010, the Transportation Committee received a verbal presentation from the Ministry of Transportation Ontario with regards to their plans to replace the Highway 417 Cyrville Road bridge overpass between the Hwy 417 / OR174 split and St. Laurent Boulevard in 2011.  A copy of their presentation is attached as Document 2 to this report.

 

 

DISCUSSION

 

The Committee discussed at length the proposed bridge replacement and the impact of closure of Cyrville Road for nine months during the bridge replacement.  The aforementioned Motion was approved by the Committee.  Details of the discussion of the matter are contained in the extract of draft Minutes, appended as Document 3 to this report.

 

 

CONSULTATION

 

No consultation was carried out in the preparation of this report.

 

 

LEGAL/RISK MANAGEMENT IMPLICATIONS

 

N/A

 

RURAL IMPLICATIONS

 

N/A

 

 

FINANCIAL IMPLICATIONS

 

N/A

 

 

SUPPORTING DOCUMENTATION

 

Document 1– General Manager, Public Works memo dated 3 May 2010

Document 2 – MTO PowerPoint Presentation

Document 3 – Extract of Draft Minute, 5 May 2010

 

 

DISPOSITION

 

Following Council approval, a letter will be prepared by the City Clerk and forwarded to the Ministry of Transportation.

 


Document 1

 

M E M O   /   N O T E   D E   S E R V I C E

 

Ottawa bw

 

To / Destinataire

Mayor and Members of Council /

Maire et membres du Conseil

File/N° de fichier:  File Number

From / Expéditeur

General Manager

Public Works /

Directeur général,

Travaux publics

 

Subject / Objet

Transportation Committee – May 5, 2010 - Ministry of Transportation - Presentation on Highway 417 – Bridge Replacement at Cyrville Road / Comité des transports – le 5 mai 2010 - Présentation du ministère des Transports concernant l’autoroute 417 - Remplacement du pont à la hauteur du chemin Cyrville

Date: May 3, 2010 / le 3 mai 2010

 

Date

 

In 2011, the Ministry of Transportation (MTO) is scheduled to replace the Highway 417 Cyrville Road bridge overpass between the Hwy 417 / OR174 split and St. Laurent Boulevard.  The intention is to complete the bridge replacement prior to the widening of the highway from the 417/174 split to Nicholas Avenue.  This is a key infrastructure project to address the traffic congestion concerns expressed by east end commuters.

 

As part of the project’s consultation process, MTO have requested an opportunity to present the scope of the project to the City’s Transportation Committee on May 5, 2010 and will address, among other details, the following:

 

Ø  The bridge’s position in MTO’s overall scheduled improvements for Hwy 417 from the split to Nicholas Avenue;

Ø  The intended closure of Cyrville Road for the duration of the proposed construction period (9 months) between February and November 2011;

Ø  The City’s request to rebuild the bridge to accommodate a future widening of Cyrville Road to four lanes, with cycling lanes and sidewalks; and,

Ø  The proposed traffic detour plan.

A Public Open House is planned for May 12, 2010, which follows a recently conducted consultation with the Cyrville Road and adjacent area businesses.

 

Frank Vanderlaan, Senior Project Engineer, Ministry of Transportation and James Scale, Senior Project Manager, AECOM, will provide a 15-minute presentation (attached) at the May 5 Transportation Committee meeting.  It will be the first item of business on the agenda that day.

 

All members of Council are invited to attend the presentation.  For further information, please contact Kevin Wylie, Manager, Operations, Engineering and Technical Support at extension 19013.

 

 

Original signed by

John Manconi

 

 

Attach: (1)

 

 

cc:        Executive Committee

            Chief, Corporate Communications

            Program Manager, Media Relations

            Manager, Operations, Engineering and Technical Support


Document 3

 

            MINISTRY OF TRANSPORTATION PRESENTATION ON HIGHWAY 417 - BRIDGE REPLACEMENT AT cyrville road

PRÉSENTATION DU MINISTÈRE DES TRANSPORTS CONCERNANT L’AUTOROUTE 417 - remplacement du pont au chemin Cyrville

Verbal Presentation / Présentation Orale

 

Frank Vanderlaan, Senior Project Engineer, MTO (Eastern Region) and Jim Scale, Design Consultant, AECOM gave a detailed presentation on the item.  Also in attendance was Scott Bisson of AECOM.  The more salient points highlighted were as follows:

-          The project limits will be the transitway to the north (southern limit of existing bridge) to about 100 m south of Labrie Avenue

-          The MTO will construct the ultimate four-lane Cyrville Road bridge deck, which includes provisions for a median island, sidewalks and bike lanes/shoulders, plus two lanes in each direction; approximately 30% of this cost will be funded by the City

-          The bridge replacement will accommodate the proposed future Highway 417 improvements, including an independent ramp from Ottawa Road 174 to St. Laurent Boulevard;

-          This construction will:

·         Address the deteriorated condition of the existing structure

·         Support future widening on Highway 417 and Cyrville Road

·         Eliminate the need for future traffic and community impacts associated with the ultimate widening of that bridge if it was replaced with its’ existing width today

-          It is recommended that Cyrville Road be closed at the Highway 417 for up to 10 months in order to accommodate the replacement of the bridge for the following reasons:

·         It is more cost-effective rather than doing a staged construction

·         It will minimize cumulative traffic impacts on Cyrville and adjacent roadways over the duration of construction

·         It will improve safety for construction workers and motorists by eliminating traffic through the confined work zone

·         It will improve construction efficiency and will reduce the overall construction duration, i.e., a single year vs. a two-year construction schedule if only partially closed; reduced costs

-          Traffic; measures will need to be put in place to address the proximity and protection of the City’s watermain located in front of the Cyrville Road south abutment, below the existing Highway 417 outside eastbound traffic lane

-          As part of this work, the MTO looked at compatibility with other provincial and city projects currently underway, including:  ongoing MTO Highway 417 improvements; Interprovincial Crossing Study; the Downtown Ottawa Transit Tunnel; and, operational improvements to Cyrville and Ottawa Road 174

-          Detour strategies will be put in place to address the short term closure of Highway 417 and the long term closure of Cyrville Road

-          Access to residents and businesses in the vicinity of the work zone will be maintained at all times and shuttle service will be provided during the full closure of Cyrville Road to transport pedestrians; details are currently being developed with staff

-          There will be a public open house on May 12 at the Earl Armstrong Arena; notifications have been distributed

-          Construction will commence in February 2011 and is anticipated to be complete by October/November 2011.

 

A copy of their PowerPoint Presentation is held on file.

 

The Chair noted that the date for their public information centre coincides with a City Council date and she wondered if the MTO had worked with the ward councillor when determining this date.  Mr. Scale advised that they had presented the date to staff, but had not discussed it with Councillor Bellemare.  The Chair asked that the MTO consider communicating with the ward councillor for any future meetings, to ensure they are coordinated without additional scheduling conflict.

 

Councillor Bellemare was concerned about the proposed closure of the Queensway and Cyrville Road during the bridge replacement period and he urged provincial officials to work with staff to develop effective solutions to ensure mobility and public safety during this time.  While he understood the MTO wanted to avoid having to do the bridge replacement during peak hours in order to allow capacity, he was seeking a guarantee that it would maintain all day lane capacity instead of just during rush hour.  He wondered if the province could undertake to do that, even if it means building temporary lanes to maintain traffic capacity at the split.

 

Mr. Vanderlaan explained that the Ministry is very aware of the impacts that any lane closures have on traffic and would do everything possible to minimize that impact.  He explained that they have stringent guidelines their contractor has to follow with respect to the exact times they are able to close a lane to undertake work.  This construction project and the full closure of the highway will occur during the weekend night-time closure so the overall impact can be mitigated.  He added that the work to be done that requires lane closures on the Queensway are fairly minor and that once the bridge has been removed, there will have to be work done on the pier within the median, which will not impact traffic.

 

Councillor Bellemare was quite concerned that one of the slides in the MTO presentation referred to the long term closure of Highway 417.  Mr. Vanderlaan clarified that that was an error and advised that the slide should have reflected the long term closure of Cyrville Road, not Highway 417.  In response to a question posed by the councillor with regards to the impact this closure will have, he indicated that it will be discussed as part of the detour strategy before its long term full closure.  Traffic will be detoured on other major arterials and motorists familiar with the area will likely go on the Queensway to avoid the disruption caused by the Cyrville Road closure.

 

With regards to whether or not the MTO have looked at adding an extra lane, he explained that the intent is to widen the Queensway but in order to do that they need to lengthen the bridge.  The councillor was not reassured because any reduction in lanes would be equivalent to a reduction in capacity and therefore gridlock.  He maintained that that needs to be seriously looked at and did not believe the proposed detour strategy is sufficient.

 

Councillor Bellemare asked if access to the Cyrville Transitway Station would continue or whether it would be entirely suspended during construction.  Mr. Scale advised that the southerly access would be closed, but a shuttle service would be provided to bypass the work zone.  Details are currently being worked out with OC Transpo.  He explained that access to that Station from the north would be maintained and the station will be open and fully functioning.

 

Councillor Bellemare was concerned about the impact the closure of Cyrville Road would have on businesses and asked if the province was still soliciting feedback to ascertain whether or not the MTO might elect to choose the two-year option which, while being longer, would at least retain some use of that roadway.  Mr. Vanderlaan indicated that they were open to suggestions in any consultation with the public and part of the public open house next week would be to get feedback from those business owners.  He pointed out that as well as being a cost saving standpoint, the actual traffic impacts between the two alternatives (nine months vs. two years) are similar in that to get in and out as much as possible has a reduced impact when comparing the overall staging, which involves heavy traffic congestion on Cyrville Road for an extended period of time.

 

Mr. Scale added that as far as the daily delays to the system are concerned, there would be approximately 4-5% increase in total delay for the full closure as compared to the single lane closure.  He offered that the advantage is the duration, so when compared to the cumulative delay over a two-year period it would be twice the delay overall to the local network.  It is not only impacting Cyrville Road, but there is also some residual impact to the adjacent roadway network.  Mr. Scale further noted that that is part of the rationale why the MTO want to get in and get out.  It is also compatible with future improvements on Highway 417, which would be delayed by an additional year if the longer-term construction period was selected.  The Ministry is also aware of the City’s plans to expand the transitway and the shorter time period would coordinate with that work as well.  He believed the cumulative delay, even with the single lane alternating closure, would incur about a 5 minute delay through the work zone.  It is still a fairly significant impact to traffic on Cyrville Road, but overall, they feel that is the better scenario and minimizes impact not only to Cyrville Road but also the adjacent network.

 

Councillor Bellemare referred to their proposal for a rapid demolition of the Cyrville Road bridge during the nine month period, which would occur over the weekend during the night.  He had some concerns about noise therefore, and wanted to ensure this work would not impact residents when they are trying sleep.  At the same time, he wanted to ensure the MTO is taking advantage of the daytime in order to reduce the total length of construction on this bridge replacement.  Mr. Scale explained that they would be seeking a noise by-law exemption; there will be some work required for the demolition of the bridge (probably between 11:00 p.m. Saturday until 6:00 a.m. the next morning).  They envision that most of the other work required will be done during the day.  He added that the only work that really requires the scheduling of traffic on Highway 417 is for the median pier and at that point, the contractor will have a fairly good window during the afternoon and may elect to do some work later in the evening in order to expedite.

 

As a result of the complete closure of Cyrville Road, Councillor Bellemare inquired if staff anticipated any emergency response delays and John Manconi, General Manager of Public Works advised that staff is mobilizing the Traffic Incident Management Group which is representative of all emergency services and all departments in the organization.  The group will also be mobilized when the project is about to commence so everyone is connected and integrated, including OC Transpo.

 

When asked by the councillor if maintaining all day lane capacity on the Queensway is essential and feasible, Mr. Manconi could not speak to the feasibility of it, but understood there would be no lane reductions save and except some mobilization and de-mobilization.  He understood in the briefings he has received that there is a lot of room in the centre lanes for the pier and suggested that if that is critical to the councillor, a Motion or comment can be made during the consultation process.  Between the shorter or longer term closure of Cyrville Road, Mr. Manconi initially offered that his first preference would be the overnight replacement, but he recognized that that is not feasible, and he acknowledged that the MTO and their teams have pushed that very hard in terms of looking at that.  He explained that he has seen the vigour that has been put to this in terms of options and he liked the fact it is a date-specific project that gives the contractor the incentive to finish.  He believed the MTO were going down the right path and the public consultation is critical and so far staff has liked everything they have seen and there has been very receptive dialogue on the options and scenarios.  He looked to the Manager of Transit Service Design (Pat Scrimgeour) to ensure he was comfortable in terms of some of the strategies that have been put forward for transit users, but believed the public meetings would flush out some of those issues the councillor has raised.

 

With respect to the shuttle service to be provided, Mr. Scrimgeour explained that it would loop through that neighbourhood connecting the people who now walk to Cyrville Station and carrying them to St. Laurent Station instead.  While the details still have to be worked out, the expectation is that this would run all day long approximately every 20 minutes.  He recognized this option is not as good as the walk-in connection that currently exists, but it is fairly frequent and he anticipated transit users would schedule their time accordingly.  He agreed to send the councillor the details of that shuttle service route.

 

Councillor Bloess inquired of the overall improvements being recommended to Highway 417 and Mr. Vanderlaan explained that these will be a multi-year project as part of the Southern Ontario Highways Program.  The councillor noted that the chronology of those improvements (starting with the Cyrville Road bridge replacement) will be over many years and there will be impacts felt over the long run.  He preferred that a whole number of things happen at the same time as quickly as possible.  With regards to this particular project and the impact it will have on businesses, he posited that the timeframe was simply unacceptable and he maintained that there must be a better way of providing both the capacity on the Highway as well as for the use of the Cyrville Road bridge in a more expeditious way.  Mr. Vanderlaan recognized that rapid bridge replacements do go well and he would be the first to recommend doing that option on this bridge.  Unfortunately, this is a different bridge and the span is being lengthened, so in order to accommodate the extra span there is a need to close Cyrville Road.

 

The councillor noted there was $5M in Works in Progress in relation to this to improve Cyrville Road (Project 905024) and he asked staff to explain what will be done with that because there is another bridge over Highway 417 and the City will have to go through the same process twice.  Valerie Bouillant, Senior Project Engineer indicated that this funding was initially approved in the 2009 budget and reapproved in the 2010 budget.  The funding is was mainly for the cost-sharing for this project because the City has agreed to have a new bridge rebuilt to accommodate the future widening of Cyrville Road.  She confirmed that the funding will not be put towards the other crossing of Highway 417 further along Cyrville Road.

 

Councillor Bloess also commented on the preliminary work done to have cycling connections along Cyrville Road and over Highway 417.  Given that development has been allowed to occur, he wondered if the City had given up the right-of-way which could have been used for a future cycling facility?  Ms. Bouillant indicated she could get back to the councillor about this, but offered that the proposed bridge overpass will allow for cycling lanes.

 

When asked when the other bridge at Cyrville Road and the Queensway (situated further south) would be replaced, Mr. Vanderlaan explained that that bridge was constructed much later than the one being discussed today and the future work (which is many years out) would probably involve rehabilitation as opposed to actual replacement.  Councillor Bloess was concerned about taking a piecemeal approach to the work that has to be done.  He referred again to the southerly portion of Cyrville where it crosses Highway 417, noting that it is narrow and is a rural standard.  He commented that this is the cycling alternative to trying to get over the highway on Innes Road.  Ms. Boulliant explained that the widening of Cyrville Road just immediately south of the proposed MTO bridge reconstruction is not currently part of the Transportation Master Plan (TMP), last updated in 2008.  It was identified just beyond the threshold for the current planning horizon of 2031 and the next opportunity therefore would be when the TMP is updated again in 2013.

 

Following on the latter discussion, Councillor Legendre asked on what basis the City would partner with the province to make the bridge wider?  Ms. Bouillant explained that because of the life expectancy of the proposed bridge overpass (50+ years) it was viewed as a good investment to have the bridge deck to the ultimate configuration of four-lanes now, because the need for widening Cyrville Road immediately south of the bridge overpass is at the threshold (2031).  Based on this information therefore, the councillor did not believe staff had permission today from this Council to do that.  John Moser, General Manager of Planning and Growth Management offered that the $5M was approved by Council as part of the 2008 budget and again in 2009.  The councillor interjected however, that it was not in the TMP and therefore wondered why those dollars would have been approved.

 

Following on the comments made by staff with regards to the shuttle service to be provided, Councillor Legendre wondered when staff intended to advise the Committee about the circuit and whether or not it is adequate.  Mr. Scrimgeour confirmed that OC Transpo staff have worked out an initial concept of what that route would be and this had been discussed in general details with the ward councillor.  He confirmed that as they learn more about the MTO’s construction plans and how they plan to stage their work, staff would be able to develop the particulars of the route more precisely and convey that information to the ward councillor and any others interested.  When asked about the 20-minute frequency for the shuttle, Mr. Scrimgeour acknowledged that it does increase people’s travel time because it puts an additional transfer and a wait into the trip that does not currently exist.  Given that the MTO is paying for the shuttle, Councillor Legendre suggested staff could argue the need for better service with an additional shuttle if required.  Mr. Scrimgeour agreed this could be discussed with the MTO if that is the will of the Committee through recommendation to Council.  The councillor indicated he would seek the guidance of the ward councillor in this regard.

 

Following on a previous point with regards to costs, Councillor Desroches believed the all-in costs of this project would include the incremental transit costs required in order to accommodate residents.  He felt that any resources the City would have to engage whether it is the police for traffic or any signs needed for detours, et cetera, would include a comprehensive public relations and public information tool at the City’s disposal, and which would be covered by the province.  Mr. Manconi indicated that the MTO have been very supportive of all those costs and are paying for upgrades to the City’s camera system for mobility logistics, signage, et cetera.

 

Councillor Jellett was concerned about the downstream effects on OR 174 during construction of the bridge.  He asked how many days of lane reductions there would be at the split and at OR 174.  Mr. Scale advised that the lane closures on Ottawa Road 174 are strictly for construction of the median pier and that all the work on the abutments and the overhead spans can be done without impacting that roadway.  At this time, he estimated one or two months impact of having one lane closed.

 

When asked by the councillor what staff were doing to mitigate the traffic problems that will occur every morning as a result of this (i.e., back-ups all the way to Rockland), Mr. Manconi clarified that the lane closures would occur during off-peak periods and understood that the impacts to OR 174 would be minimal.  Mr. Scale confirmed this, adding that the actual closure will be on the median lane westbound on Highway 417 so there will in effect be two lanes on OR 174 being maintained, which will merge with a single lane from Highway 417, which is currently two lanes.  The councillor remarked that if there is a reduction of those lanes on Highway 417, it will slow traffic down, thereby impacting the two lanes from OR 174 merging onto the highway.  Mr. Scale agreed there would be some impact, but posited that the actual conversion would happen before the two actually converge; therefore, that reduction would primarily be on Highway 417 itself.  He recognized there would be some impact as people are passing through, but confirmed there would be no lane closures envisioned for OR 174.

 

Councillor Jellett then referenced the work the City is doing to build a third lane from Blair Road to the split westbound and if that would have any impact on OR 174.  Greg Kent, Manager, Engineering Technical Services advised that there would be some construction impacts, but the work would be minimal and would be done during off-peak periods as much as possible.  The councillor wanted to ensure that the EA work for the third lane from Montreal Road to Jeanne d’Arc would be done at the same time the MTO is expending the capacity on their section.  Mr. Moser confirmed this would be the case.

 

Following on the aforementioned comments about the third lane, Councillor Bloess wanted to know if staff had looked at different ways of accommodating the backed up traffic that would occur.  With respect to the westbound lane from Blair to OR 174 for example, he wondered if any thought was given to hook that into the Aviation Parkway in order to relieve some of the pressure during construction.  Mr. Manconi indicated that while this was not something staff had thought about, they would give it some consideration to see whether or not it could be feasible.

 

Councillor Bloess referred to the extension of Hunt Club Road to Highway 417 and the fact the City is waiting for the province to commit funding to build the interchange.  He wondered if there was money in the provincial budget this year that could accelerate that link, which would in turn provide some relief during the closure of Cyrville Road.  Mr. Vanderlaan was unable to comment on that particular project, but explained that he would get back to the councillor with the appropriate contact person who could speak to that.  The councillor explained that the reason he was bringing that up was because people will try to avoid the bottleneck as they head up Highway 417 and given the already congested ramp at Walkley, which will only get worse, there is a need for that interchange to provide relief and also to provide a direct link to the industrial and business parks.

 

Following on the councillor’s remarks re the Hunt Club Road interchange, Nancy Schepers, Deputy City Manager, Infrastructure Services and Community Sustainability advised that the City is proceeding with the extension under the Stimulus Funds and the design of the interchange is underway and should be finished for potentially award of a contract in 2011.  She confirmed staff are in active discussions with the MTO and there is a 50/50 cost sharing, as was stipulated as part of the City’s application under the Stimulus Funds.  She added that staff is working with the MTO to obtain confirmation of their funding commitment for the interchange.

 

Questions arose on what contact information would be listed on the MTO signage during the Cyrville Road bridge replacement and Mr. Vanderlaan indicated that the phone number would be that of the contractor administrator, who would then direct people to the appropriate contact at the MTO.  Should councillors receive any complaints or questions, they should be directed to the MTO.

 

The Chair asked that staff consider it direction from this Committee that the MTO will have their phone numbers on the signage and they are responsible for making that information clear.  She wanted to ensure that staff monitor those signs when they are installed.

 

Councillor Legendre referred to the MTO slide presentation and the details that referred to the third span accommodating an independent OR 174 to the St. Laurent ramp.  He knew that the northbound ramp at St. Laurent is very close to the split, which has always been a problem, and asked if what is proposed will accommodate that extra lane?  Mr. Vanderlaan explained that the previous project that was done for the overall Queensway eliminates the move from Highway 417 westbound to St. Laurent and in place of that, there will be a ramp from OR 174 to St. Laurent; they will eliminate the off-ramp and provide another one.  He agreed to provide the councillor with additional information on that particular aspect of the project.

 

Councillor Legendre also referred to the link between what is proposed in the MTO’s presentation and the Interprovincial Crossing Study and Mr. Scale explained that originally, the proposed change to Highway 417 was to eliminate the existing weave westbound as motorists try to exit at St. Laurent.  Today there are three through lanes under St. Laurent Boulevard and as part of the future expansion there will be four lanes, which will increase the weaving distance.  To avoid that, the MTO propose to have a ramp come off of OR 174 in the proximity of the Aviation inner loop ramp, that will be independent of OR 174 as it passes under Cyrville and will go under the Cyrville Road third span and will access St. Laurent Boulevard, the existing ramp further on.  But there will be no access from Highway 417 westbound to St. Laurent Boulevard.  As part of the proposed interprovincial work, that St. Laurent exit ramp would actually be eliminated and replaced with an on-ramp from the Aviation Parkway onto 417 westbound.  The MTO wanted to ensure accommodation of movement with the Highway 417 changes, as well as leaving it open to implementing the interprovincial border crossing recommendations.  Mr. Vanderlaan added that all they were doing with the third span was keeping the options open and not precluding anything that may arise as a result of the interprovincial bridge study.

 

With regards to the DOTT (Downtown Ottawa Transit Tunnel), Councillor Legendre noted that the construction timing would be coordinated with DOTT improvements and in view of the fact the City has to change the transitway to rail, the buses will have to come off the transitway in this area and move onto the Queensway.  He wondered how this coordination was going to work.  Dennis Gratton, A/Manager, Planning explained that the planning and construction program for the Cyrville Bridge will be well ahead of the DOTT construction program for this portion of the transitway system when it is being converted to light rail.  Therefore, their work should be complete by the time the City is in the conversion process and there will be no interference.

 

In addition to the comments made previously about the MTO scheduling their public information centre on the same date as a Council meeting, Councillor Legendre expressed disdain for the MTO making such a scheduling conflict as he believed it reflects a lack of respect to Committee and Council.

 

Councillor Bellemare reiterated the critical need to maintain capacity on the Queensway during the bridge replacement and felt the Committee should support a Motion that would seek to request that the province do everything it can to maintain lane capacity.  He proposed that the Committee recommend that Council urge the Province to maintain all-day lane capacity in both directions on the Queensway during the reconstruction.  Councillor Legendre indicated he would be putting that Motion forward on behalf of the ward councillor.  Mr. Manconi indicated he was fully supportive of the Motion.

 

Councillor Bellemare acknowledged the comments made about the need to have a widened Cyrville Road Bridge.  He argued that it is critical given that it will be a 75-year structure and from a cost perspective it makes more sense to ensure a widened deck to accommodate four lanes, cycling lanes in both directions and sidewalks at this point in time.  Cyrville Road will be expanded to four lanes in the future and therefore it is necessary to widen the bridge and he was glad that funding is included in the budget to accommodate that at this time.  He recognized that the City has already increased capacity from Highway 417 to the Blair Road interchange by adding a third westbound lane and this summer there will be a third east bound lane added to OR 174.  He recognized that this bridge reconstruction is required in order to add a third span as part of the overall widening of Highway 417 from downtown to the split.  With continued growth in the east end of Ottawa, this added capacity is necessary.  And, when the City converts the transitway to light rail from Tunney’s Pasture to the Blair Transitway Station, there will be a need for this capacity on the Queensway for the buses to pick up the slack and ensure mobility for transit riders going east/west.

 

The councillor recognized that this bridge replacement needs to happen in order to ensure the City is modernizing its’ transportation network in this particular location to an adequate degree, in order to meet existing and future demand.  He appreciated that staff would be coordinating all efforts to ensure that all issues involved in such a massive and complex project are addressed.

 

Chair McRae thanked the MTO and their consultants for their presentation and staff for working on this important matter.  She hoped there would be a communications plan and that they would undertake to meet with the affected ward councillors.

 

            Moved by J. Legendre

 

That the Transportation Committee recommend that Council approve that the City urges the Province to maintain all-day lane capacity in both directions on the Queensway during the reconstruction of the Cyrville Road Bridge.

 

                                                                                                            CARRIED

 

Klaus Beltzner failed to see why the existing bridge could not be maintained while a second bridge is constructed right next to it.  He explained that this is what occurred on the Bronson Avenue and Bank Street bridges and wondered why that was not considered to be done in this particular case.  With respect to the detour strategy that will be put in place, he did not hear a detour which goes along the Aviation Parkway from Highway 417 and then left on Ogilvie Road.  He heard the detour would go further east of Blair and then to Ogilvie Road and the Committee should take into consideration the opportunity for a detour on the Aviation Parkway.  He acknowledged that there would be disruption and lane closures and the opportunity is to take some of the traffic off OR 174 by providing more transit.  He believed transit capacity can be improved during this construction period, with the addition of service being offered from the Trim and Millennium park and ride lots.  Also, there are methods that will allow the City to increase capacity through the downtown area for this duration and will improve the modal split.  Further details of this are contained in his e-mail to Committee dated 4 May 2010 and reflected in the photographs attached to that e-mail.  A copy of his submission is held on file.

 

Following on this presentation, Councillor Leadman wondered whether Transit Services staff would take into consideration the option provided by the delegation in terms of looking at this project overall and the potential in improving the support services for the residents and to bring some relief through the OR 174 split.  Mr. Scrimgeour explained that as they learn more about the MTO’s detailed construction plans, they will be able to deduce from that what impacts they would have on general mobility.  He offered that there may be the possibility of building elements of this into the overall traffic management plan that staff referred to previously.  And, if staff knows early enough what additional resources would be required, they may be considered as part of the 2011 budget, but such information would have to be determined before the fall.  The councillor suggested to the MTO representatives and their consultants that if there is an opportunity where there can be some funds allocated to support transit options in order to minimize the impact of this project, she believed it would work in both favours.  Mr. Vanderlaan indicated that they were open to any discussions.

 

That the Transportation Committee receive this presentation for information

 

                                                                                                RECEIVED