2.             WEST TRANSITWAY EXTENSION – TRANSPORTATION CORRIDOR-SHARING AGREEMENT – MINISTRY OF TRANSPORTATION

 

PROLONGEMENT DU TRANSITWAY OUEST – ACCORD D’UTILISATION EN COMMUN DU COULOIR DE TRANSPORT – MINISTÈRE DES TRANSPORTS

 

 

 

COMMITTEE RECOMMENDATION

 

That Council delegate approval to the City Manager to negotiate, approve and execute a Transportation Corridor-Sharing Agreement with the Ministry of Transportation, based on principles outlined in this report, including a nominal consideration, for the use of lands owned by the Ministry of Transportation consisting of 50,080m2 (12.37 acres) shown hatched on Document “1” and as Parcels A, B and C on Document “2”, attached hereto, required for the construction of Phases 1A and 1B of the West Transitway Extension from Pinecrest Road westerly to Holly Acres Road.

 

 

 

Recommandation du Comité

 

Que le Conseil délègue l’approbation au directeur municipal afin qu’il négocie, approuve et signe un accord d’utilisation en commun du couloir de transport avec le ministère des Transports en fonction des principes présentés dans le présent rapport concernant l’utilisation des terrains appartenant au ministère des Transports et consistant en 50 080 m2 (12,37 acres), indiqués en hachurés dans le Document « 1 » et comme les parcelles A, B et C dans le Document « 2 », ci-joints, requis pour la construction des Phases 1A et 1B du prolongement du Transitway du chemin Pinecrest en direction du chemin Holly Acres pour une considération symbolique.

 

 

 

DOCUMENTATION

 

1.      City Manager’s report dated 11 February 2010 (ACS2010-CMR-REP-0007)

 


Transit Committee

Comité du transport en commun

 

and Council / et au Conseil

 

11 February 2010 / le 11 février 2010

 

Submitted by/Soumis par : Kent Kirkpatrick,
City Manager/Directeur des services municipaux

 

Contact Person/Personne ressource : Gordon MacNair, Director, Real Estate Partnerships and Development Office / Directeur, Bureau de développement et de partenariats immobiliers

(613) 580-2424 x 21217, Gordon.MacNair@ottawa.ca

 

Bay/Baie (7)

Ref N°: ACS2010-CMR-REP-0007

 

 

SUBJECT:

WEST TRANSITWAY EXTENSION – TRANSPORTATION CORRIDOR-SHARING AGREEMENT – MINISTRY OF TRANSPORTATION

 

 

OBJET :

PROLONGEMENT DU TRANSITWAY OUEST – ACCORD D’UTILISATION EN COMMUN DU COULOIR DE TRANSPORT – MINISTÈRE DES TRANSPORTS

 

 

REPORT RECOMMENDATIONS

 

That the Transit Committee recommend Council delegate approval to the City Manager to negotiate, approve and execute a Transportation Corridor-Sharing Agreement with the Ministry of Transportation, based on principles outlined in this report, including a nominal consideration, for the use of lands owned by the Ministry of Transportation consisting of 50,080m2 (12.37 acres) shown hatched on Document “1” and as Parcels A, B and C on Document “2”, attached hereto, required for the construction of Phases 1A and 1B of the West Transitway Extension from Pinecrest Road westerly to Holly Acres Road.

 

 

RECOMMANDATION DU RAPPORT

 

Que le Comité du transport en commun recommande au Conseil de déléguer l’approbation au directeur municipal afin qu’il négocie, approuve et signe un accord d’utilisation en commun du couloir de transport avec le ministère des Transports en fonction des principes présentés dans le présent rapport concernant l’utilisation des terrains appartenant au ministère des Transports et consistant en 50 080 m2 (12,37 acres), indiqués en hachurés dans le Document « 1 » et comme les parcelles A, B et C dans le Document « 2 », ci-joints, requis pour la construction des Phases 1A et 1B du prolongement du Transitway du chemin Pinecrest en direction du chemin Holly Acres pour une considération symbolique.

 

 

BACKGROUND

 

The West Transitway Extension resulted from an overall Environmental Assessment Report completed in March 1994 and approved by the Ministry of Environment on 4 April 1996.  This report dealt with a 3.7 kilometre extension of the Transitway System commencing at the Queensway Transitway Station at Woodroffe Avenue and proceeding westerly to Holly Acres Road.  In 1998 and under their approval system, the Regional Municipality of Ottawa-Carleton (RMOC) approved  Phase 1A, which involved the construction of the Bayshore Transit Station situated between Richmond Road and Holly Acres Road.  In the 2006 budget, City of Ottawa (City) Council approved funding to update the 1998 design assignments for Phase 1B of the West Transitway Extension from the Pinecrest Road interchange westerly to the Bayshore Transit Station and subsequently provided approval to call tenders for its construction as part of 2007 capital works program.  As part of the requirements for Phases 1A and 1B, it is necessary to obtain property from the Ministry of Transportation (MTO) more particularly shown hatched on Document “1” and as Parcels A, B, and C on Document “2”, attached hereto.

 

 

DISCUSSIONS

 

The subject properties are part of the MTO's controlled-access Highway 417 from the Pinecrest Road interchange westerly to the Holly Acres Road interchange.  As part of the proposal to construct the West Transitway Extension, it is necessary to acquire the subject properties containing an area of 50,080m2 (12.37 acres) shown hatched on Document “1” and as Parcels A, B and C on Document “2”.

 

The City’s “Corporate Policy-Acquistion of Real Property” requires that the City pay market value for the acquisition of land for such projects.  The MTO had indicated that although their lands are dedicated as public road in the provincial system, it could declare the lands under Documents 1 and 2, surplus to their needs. 

 

Negotiations commenced with the MTO in 1998 by the initiation of the appraisal process to estimate market value of the lands required for Phase 1A (construction of the Bayshore Transit Station – Document 1). Compensation was agreed upon on the basis of an appraisal report completed at that time however, the agreement process was never finalized.  Construction of this Phase took place in 2000 as the MTO issued an encroachment permit allowing the work to proceed.  This outstanding matter forms part of this report.

 

Negotiations for Phase 1B (Document 2), commenced in 2006 with the City requesting that the MTO transfer title to the City for its requirements.  However, since the parties were unable to reach a monetary settlement by the time construction scheduling took place, the MTO granted an encroachment permit so that construction could proceed.  Construction is now completed and Phases 1A and 1B are open for operation.

 

A resolution to the appraisal process for the lands has not been forthcoming due to differences in fundamental appraisal principles.  The MTO estimates market value of the requirements at approximately $4M while the City estimates the market value at approximately $2.6M.  Both parties have remained steadfast in their positions since August 2007.

 


The MTO developed its policy of obtaining market value for lands dedicated as public road to address compensation for the loss of an asset.  However, the construction of a mass transitway system and the movement of vehicular traffic are a benefit to the future movement of traffic along any provincially-owned and controlled-access highway serving the same vehicular traffic movement.  Accordingly, the City’s transitway system benefits the MTO.  As such, and due to the fact that the MTO has just completed a redesign of this portion of Highway 417, the MTO’s senior management is receptive to alternative Tranportation Corridor-Sharing options in this specific circumstance.

 

This alternative option would permit the City to construct and maintain its infrastructure on the MTO’s public road under a Transportation Corridor-Sharing process, and this is not without precedent.  Examples in the Ottawa area and along Highway 417 are:

 

 

City staff are recommending that Council delegate approval to the City Manager to negotiate, approve and execute a Transportation Corridor-Sharing Agreement with the Ministry of Transportation based on principles outlined in this report, thereby allowing the City and the MTO staff to work together to develop an appropriate agreement that will satisfy both parties.  Should Council approve the principles, the intent is to apply this concept in similar situations such as the next phase of this project.

 

The agreement will be developed by the MTO’s Legal Services Branch, involving full consultation with the City’s Legal Services Branch and the Real Estate Partnerships and Development Office, and will address and define all areas of mutual concern including (but not limited to):

 

1.      Land/Corridor:

-  the term of the agreement, including cancellation / termination provisions

-  appropriate compensation in the event the MTO requires the City to remove / relocate infrastructure in the future

-  protection to the City in the event of the MTO’s privatization of Highway 417

-  protection to the City in the event of a change in the City’s mass transportation use

 

2.      Construction:

- shared responsibility for construction costs

- approval of contract drawings

- encroachment/building/land use/lane closure permits

- letters of Credit

 

3.      Post Construction Maintenance:

- areas of responsibility for maintenance of infrastructure, winter maintenance

- appropriate protocols to address responsibility for Emergency Management

- process for dealing with conflict, including mediation processes

- appropriate liability and indemnification protection for both parties

- responsibility for damage to property or infrastructure of either party

 

 

ENVIRONMENTAL IMPLICATIONS

 

The City’s requirements from the MTO have been reviewed through the Historical Land Use Inventory and no environmental concerns were indicated.

 

 

CONSULTATION

 

Public consultation of the City’s requirements for this project was part of the Municipal Class Environmental Assessment process and included open houses.

 

OC Transpo, Legal and Construction Services – Development Division have been consulted regarding the proposed Transportation Corridor-Sharing Agreement.

 

The Ward Councillor has been made aware of the property requirements and the proposed Transportation Corridor-Sharing Agreement.

 

 

LEGAL/RISK MANAGEMENT IMPLICATIONS:

 

There are no legal/risk management impediments to the implementation of the recommendation in this report. The risk which arises from constructing the Transitway on lands not owned by the City, will be dealt with in the Transportation Corridor-Sharing Agreement by requiring that appropriate compensation or mitigation be negotiated with the City should the MTO at some future time require a relocation of the Transitway, a change of use, or a sale of Highway 417. In addition, past experience with shared transportation corridors suggests that the City's risks of relocation or removal are minimal.

 

 

FINANCIAL IMPLICATIONS

 

The Transportation Corridor-Sharing Agreements with the MTO will negate payment of market value for the City’s requirements.

 

 

SUPPORTING DOCUMENTATION

 

Attached, as Documents “1” and “2” are property sketches showing the City’s requirements from the MTO’s - Highway 417.

 

 

DISPOSITION

 

Following Council’s approval, Real Estate Partnerships and Development Office and Legal Services Branch will finalize the Transportation Corridor-Sharing Agreement.


 

DOCUMENT “1”

 

DOCUMENT “2”