2. Hunt
Club Extension – Phase II Prolongement
du chemin Hunt Club – Mise à jour sur la phase II |
That Council approves the following:
1. Direct staff to
not award the contract for Phase I, pending receipt of the Minister's
confirmation; and
2. that if the Minister does not provide this
confirmation by October 1, 2009 that this issue be brought back to
Transportation Committee for consideration.
Que le Conseil
approuve ce qui suit:
1. De donner instruction au personnel de
ne pas attribuer le contrat pour la phase 1 avant d’avoir reçu la confirmation
du Ministre;
2. D’exiger que cette question soit soumise de
nouveau à l’étude du Comité du transport si, au 1er octobre 2009, le
Ministre n’a pas donné cette confirmation.
Documentation
1. Transportation Committee report, dated
27 August 2009 (ACS2009-CCS-TRC-0015).
Report to/Rapport au :
Comité des transports
and Council / et au Conseil
27 August 2009 / le 27 août 2009
Submitted
by/Soumis par : Councillor Rainer Bloess
SUBJECT: |
Hunt Club Extension – Phase II |
|
|
OBJET : |
Prolongement du
chemin Hunt Club – Mise à jour sur la phase II |
That the Transportation Committee recommend to Council :
1. That
staff be directed to not award the
contract for Phase I, pending receipt of the Minister's confirmation; and
2. that if the Minister does not provide this confirmation by October 1,
2009 that this issue be brought back to Transportation Committee for
consideration.
RECOMMANDATIONS DU RAPPORT
Que le Comité du transport recommande au Conseil :
1. De
donner instruction au personnel de ne pas attribuer le contrat pour la phase 1
avant d’avoir reçu la confirmation du Ministre;
2. D’exiger que
cette question soit soumise de nouveau à l’étude du Comité du transport si, au
1er octobre 2009, le Ministre n’a pas donné cette confirmation.
BACKGROUND
The Hunt Club Extension is a priority in the
City’s Transportation Master Plan and has been contemplated in the former
Region's Official Plan since 1983. The
Ontario Minister of Transportation has agreed to communicate with the City
regarding his position about funding 50% of construction of the 417 interchange
by early October 2009.
Phase I (Hawthorne to Russell) of the project will be materially complete
by March 31, 2011 and will be placed into service upon completion of Phase II
(Russell to Highway 417 including the interchange). Funding for the latter is subject to a
cost sharing agreement between the City and the MTO.
CONSULTATION
Staff will implement Council’s direction accordingly.
There are no legal/risk management
impediments to implementing the recommendations in this report.
FINANCIAL IMPLICATIONS
Council has approved the City share for both Phase 1 and 2 for this project and is subject to partnership funding.
Document 1 – Deputy City Manager’s memo dated 13 August 2009
DISPOSITION
City staff to write a letter to the Minister advising of Council’s decision.
Document
1
M E M O /
N O T E D E S E R V I C E
|
|
To /
Destinataire |
Mayor and Members of
Council |
File/N° de
fichier: ACS2009-ICS-DCM-0004
IPD |
From /
Expéditeur |
Deputy City Manager |
|
Subject / Objet |
Hunt Club
Extension – Phase II Update / Prolongement du chemin Hunt Club – Mise à jour
sur la phase II |
Date : 13
August 2009 |
Pursuant to the email sent on Friday July 24,
2009, I have received the attached correspondence from the Ministry of Transportation.
As you know, the Hunt Club
Road extension will provide arterial access to the provincial highway system in
an area of potential industrial growth and address congestion and delay in the
Walkley/Hawthorne corridor. It is identified in the Transportation Master Plan
and addresses Council’s direction to ensure that City infrastructure is built
or improved as needed to serve new growth.
As per the Provincial
Stimulus Funding timeframe, the project required a two-phase approach to
qualify for funding. Phase I of the project is comprised of a new four-lane
road between Hawthorne Road and Russell Road. Phase II would see completion of
the roadway by providing an interchange link to the 417.
The Infrastructure Stimulus Fund application was
specific in its request for early funding to ensure the completion of Phase I
by March 31, 2011 and timely transition of Phase II. The following excerpt is
extracted from the project description in our application:
“Phase I will be materially complete by March 31, 2011 and will be placed into service upon completion of Phase II of the project between Russell Road and Highway 417. Phase II is subject to a cost sharing agreement between the City and MTO.”
The Provincial and Federal Governments approved
this project as described, recognizing the need to complete both Phases to
achieve its full functionality. In our most recent letters to the Province you
were sent on July 24, 2009, we requested matching funding support to align with
the Phase I timetable and move ahead with Phase II as planned.
In the attached letter, the Province did not provide a financial commitment for the Phase II construction.
The Province did however re-confirm it’s verbal commitment for the $1.4M needed
for the design and property acquisition elements. In
response to our request for a firm commitment we received the following:
“As you know, the province’s capital budget is approved on an annual basis. Future funding for the ministry’s share of the construction of the Hunt Club interchange will be pursued through the budgetary process.”
Given the lack of firm commitment to cost share
Phase II beyond the design and property acquisition, staff do not have
authority to proceed to construction for Phase I. While the timing for future
Provincial funding for Phase II is unknown, Phase I still remains shovel ready.
Tender for Phase I construction had been anticipated for fall in order to have
advanced on the Federal and Provincial Stimulus Funding support.
It is hoped the Province will recognize the need to contribute to this project in its ensuing capital budget and commit to its remaining share for the conclusion of this important link. I will be following up with the Province to provide any information that supports the Provincial interest in this project.
As always, should you have any questions on this
please do not hesitate to contact my office. For inquiries on the design and
delivery of the project, please contact Wayne Newell.
Thank you,
Original signed by:
Nancy Schepers
Deputy City Manager
Infrastructure Services and Community Sustainability