Budget Adjustments Requiring Council Approval DOCUMENT 1
Description Increase / (Decrease) in Authority  Revenue  Rate Supported  Development Charges  Debt Explanation
Departmental Requests:            
             
904737  Trenchless Rehabilitation - Water             (1,750,000)              100,000               1,650,000 Water Services - A total of $3.0M authority is available under 904737.  Realignment of the Southwest Transitway between Baseline and Norice in conjunction with the Algonquin College Pedestrian overpass and redevelopment is a major undertaking that received Council approvals to proceed as part of the 2009 capital budget process.  In order to accommodate the works, relocation of an existing large diameter watermain is necessary to protect major water transmission infrastructure.  The combination of size, soils and preferred re-alignment through Woodfroffe Avenue all contribute to higher than anticipated preliminary estimated costs.  Transfer of $1.75M is required for the realignment.
904217  SW Transitway (Baseline to Norice)               1,750,000             (100,000)           (1,650,000)
900712  Kemp Park Local Improve. (WW Component)                (399,000)              399,000     Integrated Roads, Water & Wastewater Services
Water Services
Wastewater Services
Reduced authority requirements
903811  Infrastructure Management                (413,000)            380,000                33,000
904581  R-O-W / Easement Adjustments                (206,000)            206,000
902328  Craig/Fifth/Lyon Rehabilitation                (207,000)            207,000
904010  Balsam St (Dead End to Preston)                  (18,000)              18,000
904231  Dumaurier Ave (Boys /Girls Club)                  (26,000)              26,000
903528  Perth St (45mW Queen Charlotte-Shea)                  (17,000)              17,000
903530  Parkdale Ave (Carling - Gladstone)                (340,000)            340,000
903807  R-O-W / Easement Adjustments 2006                (206,000)            206,000
903812  Kilborn/KilbornPl/Blossom/Begonia/Dahlia                (155,000)            155,000
903850  Rehab/Replacement Misc Structures                (260,000)            260,000
903707  IT Revenue Div- New Water Billing Sys                  (83,000)              83,000
902857  Glen Cairn Flooding Event                (296,000)              296,000    
Total  Departmental Requests             (2,626,000)                         -           2,593,000                33,000                         -  
 
Administrative Changes:
             
901183  Trim Road / St Joseph Watermains                           -                365,000             (365,000)   Water Services -Refinance to level of eligible DC funding
903095  ROPEC Plant Digester Expansion                           -                (2,500,000)             2,500,000 Wastewater Services - Refinance to eligible DC funding.  This project will be refinanced over several years as development charge revenues are collected.
Total Administrative Changes                           -                           -              365,000          (2,865,000)             2,500,000
Total Funding Requirements             (2,626,000)                          -           2,958,000          (2,832,000)             2,500,000