1.     Quarterly Report - Efficiency Savings Program  

 

Rapport trimestriel - Programme sur les économies d’efficience

 

 

 

Committee Recommendation

 

That Council receive this report for information.

 

 

 

Recommandation du Comité

 

Que le Conseil prenne connaissance de ce rapport.

 

 

 

Documentation

 

1.      City Manager’s report dated 12 May 2008 (ACS2008-CMR-OCM-0004).

 

2.      Extract of Draft Minutes, 20 May 2008.


Report to/Rapport au :

 

Corporate Services and Economic Development Committee

Comité des services organisationnels et du développement économique

 

and Council / et au Conseil

 

12 May 2008 / le 12 mai 2008

 

Kent Kirkpatrick, City Manager/Directeur des services municipaux

 

Contact Person/Personne ressource : Stephen Finnamore,
Executive Director/Directeur exécutif, Business Transformation Services/Services de transformation des activités apporteront des changements

(613) 580-2424 x28859, Stephen.Finnamore@ottawa.ca

 

City Wide/à l'échelle de la Ville

Ref N°: ACS2008-CMR-OCM-0004

 

 

SUBJECT:

Quarterly Report - Efficiency Savings Program

 

 

 

OBJET :

Rapport trimestriel - Programme sur les économies d’efficience

 

 

REPORT RECOMMENDATION

 

That the Corporate Services and Economic Development Committee and Council receive this report for information.

 

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des services organisationnels et du développement économique et le Conseil prennent connaissance du présent rapport.

 

 

BACKGROUND

 

In August 2007, the Long Range Financial Planning Sub-Committee approved potential management efficiency targets totalling $100 million over three years. These targets were subsequently approved by City Council in September 2007 and became part of the directions for building the 2008 tax-supported operating budget estimates, and were approved by Council as part of the 2008 budget. During the 2008 budget deliberations, Council passed a motion to reduce budget pressures for 2008 by advancing $2.5 million from 2009 and $2.5 million from 2010.

 

The efficiency targets were allocated as follows: $25 million in 2008, $29.5 million in 2009 and $45.5 million in 2010 (refer to table 1 for additional details), and are to be realized through productivity improvements, investments in technology, asset rationalization and procurement savings. As defined as follows:

 

Productivity Improvements – achieved through continuous process improvement initiatives to administration and service delivery operations.

 

Investment in Technology – the investment in technology, premised upon the completion of a business case analysis and approval of funding. Savings would be realized as a return on the investment over a period of time, normally within four to five years. 

 

Asset Rationalization – efficiencies realized through facility closures or consolidation, which would require investment in some instances. These initiatives would be brought before Council for consideration prior to implementation (savings would be realized over time).

 

Procurement modifications (subject to Council approval if required) to the way in which the City procures goods and services. Identification of savings potential to be established through a consultant facilitated analysis of corporate spending and associated procurement strategies.

 

Table 1 - Council Directed Efficiency Targets 2008 - 2010   ($000)

 

2008

2009

2010

Total

Productivity

    10,500

        10,750

       13,750

      35,000

Technology

            -  

         5,000

       10,000

      15,000

Asset Rationalization

2,000

5,000

8,000

15,000

Procurement               

    12,500

         8,750

       13,750

      35,000

Total

25,000

        29,500

       45,500

100,000

The table below shows the savings targets by year and their impact on the net City budget:

Impact of Savings Targets  ($000)

Net Budget Increase

2008

2009

2010

Total

Before Savings

91,021

114,686

119,495

325,202

After Savings

66,021   

85,186

73,995

225,202    

 

The Business Transformation Services department has been tasked with coordinating and reporting on the efficiency targets related to Technology Investment, Asset Rationalization (Leveraging Assets) and the Productivity efficiencies, while Financial Services will coordinate and report on savings from Procurement initiatives.  As per Council’s direction, progress against all of the efficiency targets will be reported to Council through: quarterly status reports; presentation of business cases for asset rationalization; and the reporting of amendments to the purchasing by-law, required to implement changes to procurement practices.

 

 


DISCUSSION

 

1. Productivity Improvements

 

The Productivity improvements have been incorporated into the 2008 operating budgets reducing the net budgets of these branches. The dollar amounts have been removed from the 2008 budget as described in supporting documentation attachment 1.

 

All Branch Management Teams have been directed to identify potential savings opportunities and complete multi-year plans to realize these savings. Department heads and the Executive Management Committee (EMC) are and will continue to review the achievements of these plans.

Measures to realize these efficiencies fall within three main categories: decreased expenditures, increased revenues and cost avoidance.

 

Decreased expenditures realized through reductions to input costs. These involve revisions to processes and service delivery procedures that result in a reduction in staffing levels and/or compensation expenditures (e.g. reducing overtime and/or shift premiums, restructuring etc.) and operating expenses (e.g. renegotiating savings through service agreements with external vendors, materials and supplies etc.). Some examples include: reducing the number of fleet vehicles and spares; or purchasing more efficient multi-purpose vehicles; or savings through the Water Loss Control program.

 

Increased revenues realized through volume and not price.  This will be achieved through initiatives that optimize program capacity and by enhancing communications to connect more effectively with citizen’s clients and customers. For example, increasing revenues in the areas of Right of Way permits and in the Large Water Meter Change Out program (e.g. increase sale of permits or registrations for recreation programs).

 

Cost avoidance measures that decrease future expenditures. This will be achieved through initiatives that optimize the efficiency of existing and future staffing levels. This involves a review of current staff deployment models as well as branch program and service reviews.

 

Actions to Date

 

As per Council’s direction, the productivity targets have been adjusted (refer to attachment 1) and all branches have commenced the identification of potential initiatives that will contribute to meeting productivity targets over the next three years. These plans have been reviewed by department heads and where necessary are undergoing revision to ensure that the initiatives are viable and do not affect programs or service levels. In support of this work several departments are using the Branch Process Review Program (BPRP) methodology or have developed efficiency review programs built upon that methodology. Several departments will be requiring all branches to complete a branch process review within the next three years.

 

This methodology will consists of five key deliverables: scope definition; internal organizational overview including information on mission, mandate, organizational structure and history, legislative framework, budget, human resources, core resources, Centres of Expertise (COE) relationships, and service delivery model; external benchmarking and best practices review; identification of areas of opportunity for improvement; and high-level business cases to support the implementation of the opportunity.

 

Activities for the Next Quarter

 

Subsequent to a final review by department heads, a detailed list of initiatives identified and/or being implemented to realize the 2008 productivity targets will be monitored through the will be provided to Council in the next quarterly status report. Subsequent status reports will be updated to include additional viable initiatives as they arise. The Executive Management Committee will be monitoring achievements against established branch productivity plans. 

 

2. Investments in Technology

 

To enable efficiencies through the investment in technology, Council approved $5 million as part of the 2008 budget, with recognition that additional funds will be required in subsequent years to achieve the efficiency target of $15 million in this area. The IT Investment Fund is administered by IT Services branch, based on a framework approved by EMC.  The primary objective is to leverage the fund to achieve the maximum possible permanent savings over the shortest possible time.

 

Technology-enabled savings may be achieved from:

 

 

The Fund is to be used for direct investment costs (hardware, software, implementation services).

 

Information Technology Investment Fund Framework

 

Since the Information Technology (IT) investment fund was designed to focus strictly on bottom line savings starting in 2009, the Value Management tools were enhanced to make a clear distinction between realizable budget savings and re-deployable savings.

 

The IT Services branch, based on a framework approved by EMC, administers the IT investment fund.  The primary objective is to leverage the fund to achieve optimize permanent savings over the shortest realizable time.

 

Technology-enabled savings may be achieved from:

 

 

The IT investment fund is to be used for direct investment costs (hardware, software, implementation services). Permanent savings that are confirmed through the Value Management process will be identified in the appropriate budget year as an expenditure reduction within the office of the branch Director.  Planned savings not achieved in the target year will be carried forward to the next year. Savings initiated in the current year, but not realized until future years, will be credited when realized.

 

Since 2004, Information Technology Services (ITS) has used an industry best-practice process called Value Management to assess potentially significant technology investment opportunities and ensure that information technology is aligned with business objectives and strategies.  Value Management also ensures that discretionary technology investments are transparent, equitable, and based on a sound business case that respects a triple-bottom line perspective and is aligned with the City’s priorities and strategic directions.

 

A full range of business benefits, including cost savings, cost avoidance, new revenues, improved productivity and/or enhanced services, form a baseline against which the success of the investment can be measured and reported.  The Integrated Business Solutions (IBS) project, for example, enabled to the City to realize sustainable, annual efficiencies of approximately $8 million when it was completed in 2005/06.  Between 2005 and 2007, 23 other projects delivered over $3 million of bottom line efficiencies, cost avoidance savings, and additional revenues and indications are that more efficiency could be achieved by expanding the IT investment fund.

 

The Value Management process was updated in 2007, with process changes and evaluation criteria approved by EMC in November 2007.  The revised process expands the assessment to include all new technology projects. To ensure transparency and accountability for the costs and any benefits, a panel of Directors representing every City department evaluates project proposals. This Value Assessment Panel (VAP) identifies which projects should proceed and their relative priority, ensures that risks are identified and managed as appropriate, and that the sponsoring department is accountable for the resulting benefits. The value assessment is based on a 5-year analysis of both non-financial and financial measures (e.g., Net Present Value, payback, etcetera), as well as future operating budget impacts, to assist in decision-making.

 

The VAP will be utilized to review and select projects and their priority, and ensure that all feasible cross-Branch and Departmental opportunities to realize savings and other benefits are assessed. Subsequent to the detailed planning and design of any new technology funded through the IT investment fund, and immediately prior to implementation, the projected costs and benefits will be reviewed and the decision to fund the investment confirmed by the VAP.

 

Actions to Date

 

A communications and marketing plan was developed to inform clients about the IT investment fund.  . A conscious effort was made to rapidly disseminate information regarding the program throughout the corporation.  Specifically this included:

 

 

 

 

 

The ITS branch has received four viable applications (two of which are proceeding at this time) to the IT investment fund. These include:

 

1.                  Automated Invoice Payments (Financial Services): Replacement of the current manual processing of invoices across the City with an automated solution that will streamline the authorization process, manage payments to vendors in a timely and cost effective manner, enhance internal controls, and ensure that the delegated spending authority levels for each employee are observed.

 

2.                  Council Agenda Building Tool (City Clerk's Office): Replacement of the current manual preparation of agendas for standing committees and Council meetings with an automated solution that will result in less effort and time to create, publish and distribute agendas.

 

3.                  RPA/OPCA automation (Employee Services): Automation of the existing Request for Personnel Action (RPA) and Organization and Position Change Approval (OPCA) forms and processes to enable direct entry into SAP via Ozone, resulting in less data entry, reduction in errors, faster processing of transactions and the realization of other administrative efficiencies.

 

4.                  Transit Fleet Tire Tracking (Fleet Services): Implement a solution to monitor pressure and temperature on tires on over 900 Transit buses that is expected to reduce vehicle operating costs, increase success of tire warranty claims and improve vehicle performance and reliability.

 

At the time of this report, the RPA/OPCA automation and Transit Fleet Tire Tracking projects have been able to identify substantive bottom line budget savings.  While other projects did identify significant benefits (productivity improvements, service improvements, etc.), they did not contribute to achieving the fund objectives.

 

Results were compiled and reviewed on April 30, 2008 by the Value Assessment Panel (VAP).

 


 

Table 2  - New Technology Investment Initiatives Summary

Project

Department/Branch

Capital Requirement

Net Base Budget Savings

RPA/OPCA Automation

BTS/Employee Services

$1,260,000

$380,000

Transit Fleet Tire Tracking

PWS/Fleet Services

$1,700,000

$495,000

 

The number of submissions received was moderate due to a number of factors including: a tight submission deadline; the challenge of meeting the eligibility criteria; the short timeframe to realize the payback; and, the immediate priority for branches to meet 2008 productivity targets. It is anticipated that the number of submissions will increase as this new initiative becomes more established.

 

The VAP has recommended that $1.26 million from the IT investment fund be reserved for RPA/OPCA Automation, resulting in net base budget savings of $190,000 in 2009 and an additional $190,000 in 2010 with a pay back over four (4) years. This work will be merged with Time/Leave Automation, a related project approved by Council in 2008.  Together, these initiatives will deliver substantial savings, productivity improvements, and cost avoidance benefits within a 3-year timeframe.  Detailed planning work is underway to launch these projects as quickly as possible.

 

The VAP has also assessed the Transit Fleet Tire Tracking project, and recommended that it not proceed at this time, pending completion of a pilot project currently underway in Fleet Services branch to confirm the reliability of the technology.  A final decision is expected in the third quarter of this year (2008).

 

Activities for the Next Quarter

 

Although it is relatively early in the IT investment fund program, there have been several other promising opportunities identified to leverage technology that could result in further bottom-line efficiency savings. Despite the moderate number of proposals received to date, ITS will continue to encourage and seek proposals from branches for the fund.  A second call for submissions will be announced by the ITS branch, in preparation for a second project evaluation cycle to be held in the fourth quarter of 2008.

 

The identified IT investment fund projects will continue in 2008. The work underway will contribute to the identified savings targets for 2009 and 2010.  Although it is probable that the IT investment fund will be substantially committed to approved projects this year, there will likely be a carry-over of unspent funds to 2009 as part of the Works in Progress (WIP) budget, to enable projects identified in the later part of 2008 to be completed in 2009. 

 

Other Initiatives and Activities

 

Through the normal business planning cycle, other IT initiatives are in-progress or are being planned that will result in further efficiencies, some of which will be used to meet departmental efficiency targets, and others that may be able to leverage IT investment fund to help reach the corporate technology efficiency target.

 

The Mayor’s e-Government Task Force will be reporting shortly on its findings and recommendations. The ITS branch has worked actively and collaboratively with the Mayor’s e-Government Task Force since February, and is awaiting the report recommendations that could result in new projects financed through the IT investment fund.

 

By the end of the second quarter of 2008 the ITS branch will have completed a review of opportunities to further expand or leverage the City’s significant SAP investment.  There is a strong probability that further automation of manual processes will be identified with commensurate opportunities for further permanent cost savings.

 

3.  Asset Rationalization

 

The Leveraging Assets Initiative is focused on ensuring that the buildings, facilities and capital infrastructure deployed by various branches in support of client department programs and services are put to optimum use. It is also focused on examining how City property holdings and vacant lands may be re-deployed to generate permanent revenues and cost reductions. Real Property & Asset Management (RPAM) has been tasked to lead and pursue this initiative in recognition of its role in conducting strategic asset management, asset rationalization exercises and property disposition in addition to condition reviews and capital re-investment forecasting.

 

Subsequent to a review by EMC the Direct to Disposition strategy has been adopted for the Leveraging Assets initiative as described below.

 

Direct To Disposition

 

This strategy recognizes that one option to achieve permanent cost savings is to reduce the asset and property inventory and dispose of assets that have exceeded or are approaching the end of their life, have a poor condition rating, are limited in their capacity to support program delivery (especially in relation to contemporary service requirements), and/or may present an unacceptable level of economic or operational risk. The candidate facilities are not typically considered suitable for re-development or alternative use.

 

In addition to direct operating cost savings, it is recognized that the disposition of aged infrastructure will lead to a reduced requirement for deferred lifecycle investment. Any proposed disposition of developed property and the potential accompanying program delivery adjustments will be brought before Council for consideration and approval prior to implementation.

 

The Direct to Disposition strategy also recognizes efforts by the municipality to sell vacant, undeveloped property as a means of generating permanent revenues. Since 2001, RPAM has successfully rationalized and disposed of a significant volume of property, which, in turn, has generated tax revenue that would have otherwise likely been unrealized.

 

Although the bulk of vacant property has been affected by this effort, this strategy proposes a detailed review of current vacant property holdings with the intent of seeking further tax revenue possibilities. Based on a preliminary analysis a significant number of vacant properties in the inventory are being held for future program purposes. Under this strategy, RPAM will host discussions with client departments to confirm if the property hold should remain in the City’s inventory. Vacant properties that are deemed to be surplus to the City’s requirements are being marketed for sale.

 

The Direct to Disposition strategy is expected to demonstrate new permanent tax revenues associated with the sale of vacant property. A report on tax revenues earned in 2008 from vacant land dispositions is forthcoming in the third quarter of this year. The savings opportunities to be accessed from the Direct to Disposition strategy are also premised on the City’s commitment toward a reduction in the size of the asset inventory. Effective program rationalization may identify co-location options that lead to permanent operational cost savings; however, care will be applied to limit the requirement for major capital funding requirements to achieve this enhanced asset deployment.

 

It should be noted that, based on a building operating cost average of $7.80/square foot (in 2007 dollars), the City will need to reduce the size of its building inventory by approximately 11 % in order to achieve a $10 M reduction in operating costs. Clearly not all of the three-year $15 million target can be achieved through the elimination of inventory. The remaining savings will be realized by a corresponding reduction in pay-as-you-go contributions to capital and through incremental tax revenue increases.

 

Actions to Date

 

The Comprehensive Asset Management (CAM) division has undertaken the following work during the first quarter:

 

·        An Asset Profile and Leveraging Assessment summary sheet has been developed. This summary sheet succinctly captures all of the primary facility details, financial and condition data. The eligible annual savings estimates as well as the 5-year cost avoidance figures are highlighted in the data. Service impact statements as well as mitigation strategies are tendered by the client department(s) and RPAM. A risk assessment profile is included. CAM will include the depreciated value of the asset in future releases of this summary sheet as part of the Tangible Capital Asset reporting obligation.

 

 

 

 

 

 

Activities for the Next Quarter

 

A)                Populate the Asset Profile and Leveraging Assessment sheets for the recommended list of candidate facilities and continue to do so for buildings above 10,000 square feet.

B)                 Host meetings with affected client departments to assess the potential disposition of aged facilities and held properties and complete impact statements and mitigation strategies. Preliminary estimate of potential savings, tax revenues and cost avoidance to be described.

C)                Discussions with those branches that may be affected will be hosted during the next quarter. Discussions will center on the potential opportunities and impacts related to a disposition alternatives for an existing City asset or vacant property. Once completed staff input will be communicated to the Ward Councillor(s). Subject to the results of this initial assessment, public consultation may be required.

D)                RPAM is researching additional energy conservation opportunities and intends to submit a detailed report to Council this fall that will examine the operating cost savings achievable via a more aggressive energy conservation program.

 

4. Procurement Savings

 

As per Council direction, a spend analysis has been undertaken by an independent consultant and the findings are coming back to Corporate Services and Economic Development Committee (CSEDC) and Council for consideration under a separate report.

 

 

CONSULTATION

 

The purpose of this report is for information only therefore no public consultation is required.  All Departments were consulted in the preparation of this report.

 

 

FINANCIAL IMPLICATIONS

 

As per Council direction, the 2008 branch operating budgets have been reduced by the productivity target amounts identified in the 2008 draft budget estimates. The status of the achievement of the efficiency targets will be ongoing and included as part of the regular reporting on the financial status of the operating and capital budgets.

 

 


SUPPORTING DOCUMENTATION

 

DOCUMENT 1 -  $35 million Productivity Allocation by Branch 2008, 2009 and 2010.

 

 

DISPOSITION

 

Subsequent to City Council’s review of this status report, staff will pursue each of the three strategies as described herein, with special emphasis on the Direct to Disposition strategy.

 

 

 

 

 

 

 

 


DOCUMENT 1

 

Breakdown of 2008 - 2010 Operating Budget Productivity Assignments

 REVISED PRODUCTIVITY ASSIGNMENT

 

2008

2009

2010

 Total

 Department / Branches

 $ 000

 $ 000

 $ 000

 $ 000

 

 

 

 

 

Elected Officials

            -

            -

             -

            -

 

 

 

 

 

City Manager

 

 

 

 

City Manager's Office

          70

          55

             -

        125

Financial Services

        220

        160

             -

        380

City Clerk's Branch

        370

        285

             -

        655

Legal Services

          30

          35

             -

          65

City Manager Total

        690

        535

             -

     1,225

 

 

 

 

 

Office of the Auditor General

            -

            -

             -

            -

 

 

 

 

 

Community and Protective Services

 

 

 

 

CPS DCM

            -

            -

             -

            -

Paramedic Service

        146

        155

        219

        520

Fire Services

     1,017

     1,070

      1,553

     3,640

By-law Services

          75

          86

        119

        280

Office of Emergency Management

          13

          17

          25

          55

Housing

        219

        233

        343

        795

Public Health

        109

        112

        154

        375

Employment & Financial Assistance

        170

        181

        269

        620

Parks & Recreation

        341

        362

        522

     1,225

Child Care

        255

        267

        393

        915

Long Term Care

        122

        129

        199

        450

Cultural Services & Community Funding

          62

          69

          99

        230

CPS Total

     2,529

     2,681

      3,895

     9,105

 

 

 

 

 

Library

        242

        250

        368

        860

 

 

 

 

 

Public Works and Services

 

 

 

 

PWS DCM

            -

            -

             -

            -

Solid Waste - Tax

        269

        283

        413

        964

Solid Waste - Rate and Non Dept

        323

        339

        495

     1,157

Surface Operations

     1,009

     1,061

      1,547

     3,617

Traffic & Parking Operations

        416

        437

        638

     1,490

Infrastructure Services

          85

          90

        131

        306

Fleet Services (Expenditures)

     1,595

     1,679

      2,449

     5,724

Fleet Fuels

        464

        487

        711

     1,662

Fleet Services (Recoveries)

   (2,059)

   (2,167)

    (3,160)

    (7,386)

PWS Total

     2,102

     2,209

      3,223

     7,534

 

 

 

 

 

Planning, Transit and the Environment

 

 

 

 

PTE DCM

            -

            -

             -

            -

Transit Services

     3,290

     3,466

      5,053

    11,810

Building Code Services - Ontario Building Code

        127

        134

        196

        457

Building Code Services - Other Permits

           5

           5

            8

          18

Planning Branch

          88

          92

        134

        314

Economic & Environmental Sustainability

          23

          25

          36

          84

PTE Total

     3,533

     3,722

      5,427

    12,683

 

 

 

 

 

Business Transformation Services

 

 

 

 

BTS Exec Director's Office

            -

            -

             -

            -

Real Property Asset Management

        120

        121

        179

        420

RPAM Facility Cost

        267

        285

        413

        965

RPAM Hydro and Heating

        146

        155

        229

        530

Information Technology

        520

        380

             -

        900

Employee Services

        100

          85

             -

        185

Corporate Planning & Performance Reporting

          20

           5

             -

          25

Corporate Communications

          20

          10

             -

          30

Client Services & Public Information

        220

        165

             -

        385

BTS Total

     1,413

     1,206

        821

     3,440

 

 

 

 

 

Total

   10,509

   10,604

    13,733

    34,847

 

 

 

 


            Quarterly Report - Efficiency Savings Program  

Rapport trimestriel - Programme sur les économies d’efficience

ACS2008-CMR-OCM-0004            city-wide / À l’Échelle de la ville

 

Responding to questions from Councillor Wilkinson, Mr. S. Finnamore, Executive Director of Business Transformation Services, explained this was the first quarterly report, which was intended to give Council a notion of the direction being taken with the efficiency savings program; the productivity targets themselves and what has been done in terms of allocating the targets amongst the various departments and branches.  He noted that in order to achieve their targets, some of the branches would be undertaking program reviews.  He submitted that by the second and third quarterly reports, Council should have a good idea of how and where the efficiencies would be achieved and he was confident that they would be on target. 

 

In response to a request from Councillor El-Chantiry, Mr. Finnamore confirmed that, in order to give members of Council the ability to make comparisons and to see the progression from one quarter to the next, future reports could include, as an annex, a summary of previous reports.  

 

Following these exchanges, Committee voted to receive the report.

 

That the Corporate Services and Economic Development Committee and Council receive this report for information.

 

            RECEIVED