3.             Patio Operations During the Reconstruction of Preston Street

 

EXPLOITATION DES TERRASSES PENDANT LA RÉFECTION DE LA RUE PRESTON

 

 

Committee recommendations

 

That Council approve:

 

1.         That the permit holders within the construction limits during the Preston Street Reconstruction Project be permitted to operate patios on the right-of-way (ROW) at no charge, where and when the approved boundaries of their patio are available and as permitted by the contractor; and

 

2.         That the permit holders on Preston Street outside of the construction limits be offered the opportunity to open their patios while being charged the lower 'Boulevard' as opposed to the 'Sidewalk' rate.

 

 

recommandations du comi

 

Que le Conseil approuve :

 

1.                  que les titulaires de permis de la zone visée par le projet de réfection de la rue Preston soient autorisés à exploiter gratuitement une terrasse sur l’emprise routière, si le périmètre devant être occupé par leur terrasse est accessible et si l’entrepreneur le permet; et

 

2.         que les titulaires de permis de la rue Preston non situés dans la zone visée par le projet se voient offrir la possibilité d’exploiter leur terrasse tout en ne payant que le tarif des terrasses situées sur une emprise plutôt que celui des terrasses situées sur le trottoir.

 

 

 

 

Documentation

 

1.      Councillor Diane Holmes’ report dated 8 April 2008 (ACS2008-CCS-TRC-0007).

 


Report to / Rapport au :

 

Transportation Committee /

Comité des transports

 

and Council / et au Conseil

 

8 April 2008 / le 8 avril 2008

 

Submitted by / Soumis par :

Councillor / Conseillère Diane Holmes, Somerset Ward

 

Contact Person/Personne ressource : Councillor / Conseillère Diane Holmes, Quartier Somerset Ward

(613) 580-2484 / Diane.Holmes@ottawa.ca

 

Somerset (14)

Ref. N°: ACS2008-CCS-TRC-0007

 

 

 

SUBJECT:

Patio Operations During the Reconstruction of Preston Street

 

 

OBJET :

EXPLOITATION DES TERRASSES PENDANT LA RÉFECTION DE LA RUE PRESTON

 

 

REPORT RECOMMENDATIONS

 

That the Transportation Committee recommend Council approve the following:

 

1.         That the permit holders within the construction limits during the Preston Street Reconstruction Project be permitted to operate patios on the right-of-way (ROW) at no charge, where and when the approved boundaries of their patio are available and as permitted by the contractor; and

 

2.         That the permit holders on Preston Street outside of the construction limits be offered the opportunity to open their patios while being charged the lower ‘Boulevard’ as opposed to the ‘Sidewalk’ rate.

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité des transports recommande au Conseil d’approuver ce qui suit :

 

1.         Que les titulaires de permis de la zone visée par le projet de réfection de la rue Preston soient autorisés à exploiter gratuitement une terrasse sur l’emprise routière, si le périmètre devant être occupé par leur terrasse est accessible et si l’entrepreneur le permet; et

2.         Que les titulaires de permis de la rue Preston non situés dans la zone visée par le projet se voient offrir la possibilité d’exploiter leur terrasse tout en ne payant que le tarif des terrasses situées sur une emprise plutôt que celui des terrasses situées sur le trottoir.

 

 

BACKGROUND

 

The following motion is being placed on the agenda for the consideration of the Transportation Committee as requested by Councillor Diane Holmes:

 

Whereas the Preston Street Reconstruction project is in the detailed design stage with construction commencing in the spring of 2008;

 

And whereas there is a strong interest in recognizing and building on the vibrant pedestrian atmosphere;

 

And whereas roadway construction is a very difficult time for businesses and Preston Street is expected to take 3 years to complete;

 

And whereas patios will maintain pedestrian activity on the street;

 

And whereas only 6 restaurants within the Preston Street BIA currently have patios operating on the ROW (357 Preston St. pending);

 

Therefore be it resolved that the permit holders within the construction limits be permitted to operate patios on the ROW at no charge, where and when the approved boundaries of their patio are available and as permitted by the contractor;

 

Further be it resolved that the permit holders on Preston Street, but outside of the construction limits, be offered the opportunity to open their patios while being charged the lower 'Boulevard' as opposed to the 'Sidewalk' rate.

 

 

CONSULTATION

 

This item will be advertised in the local dailies as part of the Public Meeting Advertisement on Friday preceding the Transportation Committee Meeting.

 

The Preston BIA supports these recommendations.

 

Public Works and Services Comments:

 

PWS staff do not have delegated authority to waive temporary outdoor patio encroachment fees.  Non-refundable fees are calculated for the number of days from the permit start date to September 30, in accordance with Section 63(2) of the City of Ottawa Encroachment By-law 2003-447.

 

Staff have no concern with the proposal for the reduction in the permit encroachment rate within the active construction zone along Preston Street, but we do have concern with respect to the part of the proposal that relates to outside the active construction zone.  This sets a precedent for this project, and others within the City, and has financial impacts over an undetermined time frame.

 

 

FINANCIAL IMPLICATIONS

 

Public Works and Services, Traffic and Parking Operations Branch, has advised the waiving and/or reduction in permit encroachment rates as per the report’s recommendation would have a total estimated impact on 2008 revenue in the amount of $15,102.36 based on the establishments that normally are issued permits in the affected construction area.

 

There is one location that exists outside of the construction area.  If this location is removed from consideration (as per staff’s concerns), the revenue impact becomes $12,132.12.

 

 

DISPOSITION

 

The Public Works and Services Department.