1.             PEDESTRIAN CROSSWALK AT THE INTERSECTION OF KING EDWARD AVENUE AND CATHCART STREET

 

TRAVERSE PÉDESTRE À L’INTERSECTION DE L’AVENUE KING EDWARD ET DE LA RUE CATHCART

 

 

Committee recommendations as amended

 

That Council approve:

 

1. That a pedestrian operated traffic signal be installed at the intersection of King Edward Avenue and Cathcart Street, and that funds be allocated from the King Edward Capital Project.

 

2.                  That the following recommendation be referred to staff for cost estimates: That during the actual construction process, which has reduced the number of lanes on King Edward from 6 to 4, a feasibility study be undertaken to estimate the impact of permanently reducing the Avenue to four lanes.

 

 

Recommandations modifiées du Comité

 

Que le Conseil approuve :

 

1.         qu’un feu de circulation déclenché par les piétons soit installé à l’intersection de l’avenue King Edward et de la rue Cathcart et que les fonds qui y seront alloués proviennent du Projet d’immobilisations de l’avenue King Edward;

 

2.         que la recommandation suivante soit renvoyée au personnel en vue de l’estimation des coûts :

            que durant les travaux mêmes d’installation, qui obligent de réduire le nombre de voies sur l’avenue King Edward de six à quatre, une étude de faisabilité soit entreprise afin d’estimer l’incidence d’une réduction permanente de l’avenue à quatre voies.

 

 

 

Documentation

 

1.      Transportation Committee report (ACS2007-CCS-TRC-0002).

 

2.      Extract of Draft Minutes 7, Transportation Committee meeting of 16 May 2007.


Report to/Rapport au :

Transportation Committee

Comité de Transport

and Council/et au Conseil

Submitted by/Soumis par : Councillor/le conseiller Georges Bédard

Ward 12 Rideau-Vanier/Quartier 12, Rideau-Vanier

Contact Person/Personne-ressource : Councillor/conseiller Georges Bédard

(613) 580-2482, georges.bedard@ottawa.ca

Ward / Quartier 12 (Rideau-Vanier)

 

Ref N°/No de réf. : ACS2007-CCS-TRC-0002

 

 

 

 

SUBJECT:

Pedestrian Crosswalk at the Intersection of King Edward Avenue and Cathcart Street

 

 

OBJET :

TRAVERSE PÉDESTRE À L’INTERSECTION DE L’AVENUE KING EDWARD ET DE LA RUE CATHCART

 

 

REPORT RECOMMENDATIONS

 

That the Transportation Committee recommend Council approve:

 

1.                  That a pedestrian crosswalk be installed at the intersection of King Edward Avenue and Cathcart Street.

 

2.                  That during the actual construction process, which has reduced the number of lanes on King Edward from 6 to 4, a feasibility study be undertaken to estimate the impact of permanently reducing the Avenue to four lanes.

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité des transports recommande au Conseil d’approuver :

 

1.                  Qu’une traverse pédestre soit installé à l’intersection de l’avenue King Edward et de la rue Cathcart.

 

2.                  Qu’une étude soit tenue afin d’observer la possibilité de réduire le nombre de voies de 6 à 4.

 

 

BACKGROUND

 

All residents of Bruyère, Cathcart, Bolton, Boteler, Parent, Cumberland and Dalhousie Streets, located on the west side of King Edward and North of St. Andrew have no direct pedestrian access to the east side of King Edward, the closest access is the crosswalk at the intersection of St. Andrew and King Edward.

 

For many years now, residents of the community located at the west of King Edward have requested the installation of a crosswalk north of St. Andrew Street.  This as recently resurfaced with the ongoing renewal of the King Edward Avenue project.

 

In July 26, 2006, an RTS was initiated in order for staff to evaluate the possibility of adding a pedestrian crosswalk at the intersection.  On November 24th. 2006, reply was given to the request:

 

“For an IPS installation, the warrant system considers (i) the number and type (children, seniors, etc.) of pedestrians crossing the street, (ii) the traffic volume on the roadway, and  (iii) the time that pedestrians must wait (i.e. are delayed) for an appropriate gap in traffic on the roadway before starting to cross the street.   An eight-hour (07:30-09:30, 11:30-14:00, 14:30-18:00) pedestrian survey was undertaken on King Edward Ave. between Boteler St. and Bruyère St. on Wednesday 22 November 2006.  During the highest six hours of the survey, 49 pedestrians (10 youth and 39 adults) were observed crossing King Edward Ave.  Of these, 18 pedestrians waited 10 seconds or less before crossing the roadway.  Our analysis of this data shows that the conditions at this location meet 31% of the warrant for the installation of a pedestrian signal.  As the warrant conditions are not achieved, (100% required) we cannot recommend the installation of a pedestrian signal at this location at this time”

 

Although staff response was not in favour of adding the crosswalk at the said intersection, it clearly demonstrated two major issues:

 

1.      Pedestrians and Cyclists are (rightfully) fearful of the consequences of crossing the Avenue without any lights

2.      Those who do cross the Avenue illegally subject themselves and automobilists to grave dangers  

 

The results of the staff monitoring also proved to be amputated; they were conducted on a November day.  The amount of pedestrians and cyclists flowing through King Edward in order to reach the Ottawa River Park and the Lowertown East Community is drastically down during this late – fall period.  Also construction on the renewal project was already underway, which is another factor reducing the number of pedestrians and cyclists using the Avenue.

 

The following is supporting documentation for the recommendation:

 

“Transportation and Transit Committee Extract from Wednesday, 17 July 2002 Minutes (#28)

Moved by E. Arnold

That the four lane option for King Edward Avenue be reviewed for the feasibility of implementation when each of the:

a. Transportation Master Plan;

b. The Rapid Transit Expansion Study;

c. The East End Interprovincial Bridge Study; and

d. The implementation of CN-CP proposal to twin freight lines between Ottawa and Toronto to carry inter-city truck traffic

are brought forward to Transportation and Transit Committee.

 

CARRIED”

 

 

DISCUSSION

 

Recommendation 1

 

The suggestion of implementing a pedestrian crosswalk at this intersection follows accordingly to the City of Ottawa’s official plan, section 1.8, Lowertown Street Environment:

Secure, inviting, pedestrian corridors (…), creating a sense of cohesiveness with neighbouring areas. In particular, efforts will focus on improving pedestrian safety and access across King Edward Avenue, thus reuniting the Lowertown community, along with significant enhancement of the street and reforestation along the boulevard”

And further, in section 1.8.3:

g.      Gateways and Distinctive Streets

City Council shall ensure the revitalization and enhancement of gateways and distinctive streets in Lowertown; in particular, Council shall ensure that:

King Edward Avenue

                                 i.            King Edward Avenue is developed as a boulevard and major gateway into the Central Area, with prominent streetscaping, secure and visible pedestrian crossings and strong visual links to Ottawa City Hall;

 

By adding this crosswalk, bicycling and walking would again be promoted to the citizens of the City, advertising at the same our great bike lanes all over the community. Also, a crosswalk would add to the overall safety of the avenue, by serving as a traffic calming measure on a corridor that sees many speed excesses.

 

Another viewpoint expressed by the community is the lack of interaction between the west and east sides of Lowertown since the building of the 6 lane arterial. Being separated by a heavily used boulevard does not create good community energy. By linking once more the community, by means of a pedestrian crosswalk, we create a corridor of activity beneficial for the community. The more access point between to the sides, the better it will be to strengthen the sense of community.

 

Finally, a new pedestrian link to the Bordeleau Park on the east side of King Edward would increase parks and recreation space to the residents of Lowertown west that presently suffers from a lack of parks.

 

Recommendation 2

 

Transportation Committee approved, on July 17th, 2002 a motion supporting the idea of studying the option of reducing King Edward Avenue from 6 to 4 lanes. The King Edward Avenue Task Force, Action Sandy Hill, the Rideau Street BIA, and a majority of the councillors also supported this motion.

 

As of January 2006, no report has been brought forward to Committee regarding this issue.  With the forced reduction of King Edward Avenue to 4 lanes during construction, it would be the ideal time to carry out the study.

 

 

CONSULTATION

 

Recommendation 1

During the process that lead to the approval of the King Edward Avenue Renewal, many public consultations where held.  One of the demands expressed by many citizens was the wish to have a crosswalk at King Edward and Cathcart.  Results of these consultations have clearly shown that Pedestrian Mobility & Safety was one of the most important aspects of the King Edward Renewal project.  Here are examples of raised issues:

a)      It is difficult to cross at lights

b)      Access to Rideau River is difficult

c)      Make roadway pedestrian / cyclist friendly.

The King Edward Avenue Renewal Planning and Environmental Study Report, published in 2002, has opened the door for this option as well.  Page 8 of section 9 (Assessment of the Preferred design) stated that there was “Potential for a signalized pedestrian crossing north of St. Patrick at Cathcart”.

Comments from the Public Works & Services Department

Following receipt of the draft version of this report, authored by Councillor Bédard and circulated for staff comment, detailed analysis was undertaken to ensure that if the proposed pedestrian signal were installed at King Edward and Cathcart, it would operate safely.  That analysis revealed that this location is not suitable for a pedestrian signal as the new alignment of King Edward north of that point, does not provide sufficient sight distance for operators of large southbound trucks with conventional braking systems, to see, react and stop in time to avoid collisions with queued vehicles, backed up from the Cathcart intersection. 

 

That finding was immediately conveyed to and discussed with Councillor Bédard by phone.  In light of that finding, he asked that staff attend the annual general meeting of the Lowertown West Community Association on March 19, 2007, to provide that information and to respond to related questions.

 

At that meeting, a construction drawing was used to illustrate the changes currently underway to the road and sidewalk network at the north end of King Edward.  Those changes will provide direct sidewalk connections from both sides of King Edward in the vicinity of Cathcart Street, to destinations and areas to the north such as Sussex Drive, Minto Bridges, the former Ottawa City Hall, the Lester B. Pearson Building and the parklands adjacent to the Rideau River. 

 

The need for direct pedestrian access to those destinations – replacing the current need for pedestrians on the west side of King Edward to first cross that roadway to access the sidewalk on the east side before proceeding north - was a key design consideration on which the re-alignment of King Edward between Sussex Drive and Boteler Street was premised.  That objective could only be met by grade separating King Edward Avenue from the northbound and southbound ramps to/from the Macdonald-Cartier Bridge.

 

It was then explained that if a pedestrian signal were installed at Cathcart Street, the width of the east-west crossing of King Edward Avenue would be 32 metres and the corresponding duration of the red indication facing north-south traffic would be 30 seconds.  The duration of red indication is based upon a “walking speed” of 1.07 metres per second for seniors and children.  During that 30 second red interval, pedestrians would be provided with a 7 second “walk” indication (to leave the curb and start their crossing) followed by a 17 second “flashing don’t walk” and a 6 second “solid don’t walk” indication (to complete their crossing). 

 

The geometry of the southbound approach to that intersection and more specifically, to the ramp that carries inter-provincial traffic from the Macdonald-Cartier Bridge to King Edward Avenue, was then discussed.  That ramp consists of a west to east segment, a right-hand curve that connects that segment with King Edward Avenue and, the most northerly two blocks of King Edward Avenue between Boteler Street and Cathcart Street.  It was stressed that each of those southbound ramp segments that connect the Macdonald-Cartier Bridge to the intersection of King Edward and Cathcart, is only two-lanes wide.

 

During weekday morning rush hours, that two-lane southbound ramp typically carries 3,000 vehicles per hour, 5 % of which are heavy trucks.  Computer modelling using Synchronic Analysis, shows that queues would quickly develop over 30 second red intervals and extend from the Cathcart into or beyond the curve - depending on the exact percentage of trucks. 

 

The apex of that curve is some 250 metres from Cathcart and while drivers of most automobiles approaching the curve would have ample opportunity to see, react and stop safely in time to avoid collisions with vehicles stopped at the end of that queue, operators of heavy trucks would not be able to do so.  This is because the stopping distance requirement for cars and light trucks travelling at 50 km/h under wet conditions is 60-65 metres, whereas the stopping requirement for heavy trucks with conventional braking systems under similar conditions is 85-110 metres.

 

This is not a safety issue with the existing signal at King Edward Avenue and St. Andrew Street, two blocks or 160 m south of Cathcart Street, as King Edward Avenue widens to three lanes at Cathcart and its storage capacity between St. Andrew and the curve is adequate to safely accommodate queued traffic from that signal.

 

A member of the audience suggested that because trucks are much higher than cars, operators of those vehicles should be able to see hazards much further ahead and that this should compensate for their stopping distance requirements.  Staff responded that while this would certainly be a consideration in many situations, it cannot be applied in this instance because of the curve, the visibility obstruction created by a large building on the southwest corner at Boteler Street (that restricts the view across the inside of the curve) and, the concrete barrier walls that line both sides of the ramp in the area of its grade separation above the King Edward (southbound) roadway from Sussex Drive.  Sight distance standards are based on the need for approaching drivers, regardless of the type of vehicle they are operating, to see the taillights of stopped passenger vehicles at a height of 38 cm (or 18”) above the road surface.  The barrier walls are 110 cm (or 44”) high.

 

Another suggestion was that in conjunction with the proposed installation of a pedestrian signal at Cathcart Street, flashing beacons could be installed upstream of the curve to forewarn drivers that the signal at Cathcart had been activated.  Again, it was agreed that ordinarily, that would be a viable option.  However, in this instance, upstream flashers are already in place to forewarn drivers of the curve ahead and the need to reduce their speed to safely negotiate it.  As those beacons will still be required when construction of the re-aligned southbound ramp is complete, this is not an acceptable solution.  Flashing beacon installation must conform to provisions set out in Ontario Traffic Manual and two sets of beacons cannot be installed in such close proximity to one another. 

 

Another suggestion was that speed humps be installed to physically limit the approach speed of vehicles, thereby ensuring that trucks could stop in time to assure safe operation of the proposed pedestrian signal.  Many in the audience openly disagreed with that notion, noting that the resultant noise from large trucks decelerating in advance of and in traversing the speed hump, especially overnight, would not be an acceptable trade-off.

 

The discussion then focused on traffic and pedestrian conditions at the intersection of King Edward and Cathcart.  As noted by Councillor Bédard in the report, conditions based on a survey completed last November only satisfied 31% of the Council-approved installation warrants for a pedestrian signal and no seniors or children crossed at that point.  Staff therefore asked why, exactly, people wish to cross at Cathcart when there are no major pedestrian-trip generators immediately east or west of that point.  The answer was that people want to cross the road for a variety of reasons, including their desire to directly access the park and recreational areas alongside the Rideau River.

 

Staff therefore indicated that because the timing of the November survey is a point of contention, it would certainly be repeated following construction, once everything returns to normal.  Further, it was stressed that like many other locations, this site could be monitored on a regular (annual) basis.  If conditions change over time and are found to meet the warrants, then action must be taken to protect those pedestrians.  This can only be done in two ways, either by separating the conflicting vehicle and pedestrian streams through time, or, by separating those streams through distance.  The former is done through traffic signals that alternate the right-of-way between the opposing streams and the latter is done through physical separation using a pedestrian overpass or tunnel.  In this instance, because a pedestrian signal is not an option, a grade-separated crossing would have to be devised.

 

As a final note, attendees at the meeting expressed frustration and felt misled, as they had been informed through the Environmental Assessment Study process that underground ducting would be installed at this site during construction to facilitate the installation of a pedestrian signal when required.  This implied to them that such an installation was technically possible.  Staff conceded that this was understandable as it clearly states in two areas of the report entitled “King Edward Renewal” approved by Council in 2003 (Ref: ACS2002-TUP-INF-0016) that the recommended design provides for:

 

“the installation of underground traffic plant at the King Edward/Cathcart intersection to accommodate possible future pedestrian-activated traffic signals at this location if/when warranted, or determined appropriate.”

 

However, staff also pointed out that in fairness to those involved in that study, this is a very complex environment.  A combination of the geometry of the southbound ramp, the height of its barrier walls, the makeup of the traffic using it, visibility conditions on the inside of the curve, the pedestrian crossing time requirements, the vehicle storage capacity of the King Edward north of Cathcart, the need to retain advance warning flashers at the curve, and a number of other factors, ultimately led to dismissing what appeared to be a standard and straightforward solution during the conceptual and function planning stages of this project.  There was no deliberate attempt to mislead anyone and at the end of the detailed design process, public safety cannot be compromised and staff analysis simply “is what it is”.  A pedestrian signal simply will not operate safely at King Edward and Cathcart.

 

 

Recommendation 2

The idea of studying the option of reducing King Edward from 6 to 4 lanes was previously approved by Transportation Committee in 2002.

 

Comments from the Public Works & Services Department:

This motion was addressed in The Planning and Environmental Study Report for the King Edward Avenue Renewal project, dated September 2002, which evaluated different roadway cross-section options.  The conclusion of this evaluation was that a six-lane cross-section is recommended, primarily due to considerations of traffic congestion, until measures are in place to significantly reduce traffic volumes on King Edward Avenue, and particularly the volume of truck traffic.  Possible measures to reduce traffic volumes are discussed in the report, and include construction of a new inter-provincial bridge. The 6-lane roadway, has been designed to be reduced to 4 lanes if traffic is significantly reduced in the future.

 

It is recommended that a study of traffic operations on King Edward Avenue be conducted following implementation of the measures to reduce traffic volumes as described in the Planning and Environmental Study Report, to determine whether a reduction to four lanes is recommended at that time.

 

 

FINANCIAL IMPLICATIONS

 

The installation of the underground ductwork for the pedestrian crossing at this location is part of the larger contract for King Edward Avenue Renewal-Phase 2, which is presently under construction.  This should reduce the overall cost of the installation of pedestrian signals and allow for the installation of above ground plant at any time in the future without further inconvenience to vehicular traffic on King Edward Avenue.

 

Comments from Financial Services

 

There is no funding identified in the 2007 Capital Budget for the requested Intersection Pedestrian Signal installation at the intersection of King Edward Avenue and Cathcart Street or the requested studies.