2. DOWNTOWN
TRANSIT OPERATING STRATEGIES 2007-2010 STRATÉGIES D’EXPLOITATION DES TRANSPORTS EN COMMUN DANS LE
CENTRE-VILLE 2007-2010 |
Committee recommendation
That Council
receive this report for information.
Recommandation
du Comité
Que le Conseil reçoive le présent rapport à titre d’information.
Documentation
1.
Deputy City Manager's report Planning, Transit and the
Environment dated 1 May 2007 (ACS2007-PTE-TRA-0006).
2.
Extract
of Minutes 8, Transit Committee Meeting of 16 May 2007.
Report to/Rapport
au:
Transit Committee
Comité du
transport en commun
and Council/et au
Conseil
01 May
2007/le 01 mai 2007
Submitted
by/Soumis par: Nancy Schepers, Deputy City Manager/Directrice municipale
adjointe
Planning,
Transit and the Environment/Urbanisme,
Transport en commun et Environnement
Contact/Personne-ressource:
A. Mercier, Director/Directeur, Transit Services/Services
du transport en commun
613-842-3636 ext. 2271, alain.mercier@ottawa.ca
Ref N°: ACS2007-PTE-TRA-0006 |
SUBJECT: |
|
|
|
OBJET : |
STRATÉGIES
D’EXPLOITATION DES TRANSPORTS EN COMMUN DANS LE CENTRE-VILLE 2007-2010 |
REPORT
RECOMMENDATION
That the
Transit Committee recommend that Council receive this report for information.
RECOMMANDATION
DU RAPPORT
Que
le Comité du transport en commun recommande que le Conseil reçoive le présent
rapport à titre d’information.
EXECUTIVE SUMMARY
Assumptions and
Analysis
Transit ridership on the OC Transpo system continues
to grow by approximately three percent each year. The capacity of the Central Area Transitway bus-only lanes and
platforms on Albert and Slater Streets is limited, and the current level of
service on Slater Street in the afternoon is near the capacity of the
street. In its present configuration,
the street is capable of accommodating no more than 195 bus trips per hour, and
the scheduled level of service has been kept below 180 bus trips per hour since
2004 to maintain service reliability.
The key location that is the constraint on the system is the eastbound
platform on Slater Street east of Metcalfe Street.
In 2007, staff are pursuing three strategies to
reduce pressure on the capacity of Slater Street and to improve the flow of
buses and the reliability of service on Slater Street over the next few
years. These are:
1.
Improving
platforms to reduce boarding time;
2.
Increasing
the use of downtown bypass cross-town routes; and
3.
Using
more high-capacity articulated buses to accommodate ridership growth.
For the years beyond 2007 and until future rapid
transit projects are decided, other possible solutions are:
This table shows the number of eastbound bus trips
that are expected to be required in the afternoon peak period in each year from
2007 to 2010, the actions that staff plan to take to reduce that number, and
the number of bus trips that would be required after the actions are taken.
Year |
Number of Bus Trips Before
Actions |
Actions to be Taken |
Number of Bus Trips After
Actions Taken |
2006-07 |
173 |
-
Current situation |
173 |
2007-08 |
191 (From 2007 Transit Service
Plan) |
-
Improve Metcalfe platform -
Use articulated buses for growth |
182 |
2008-09 |
188 (182 plus 3 percent growth) |
-
Use articulated buses for growth -
More customers on bypass routes |
182 |
2009-10 |
188 (182 plus 3 percent growth) |
-
Use high-capacity buses for growth -
More customers on bypass routes -
Passenger information systems -
Smart card fare collection |
182 |
Beyond 2010 |
190+ |
-
Use high-capacity buses for growth -
Possible rapid transit projects - Consolidation of express routes |
|
On December 6, 2006, Council referred to Transit
Committee a motion that had been put forward to reinstate direct to downtown
service in the morning peak period on Routes 126, 148 and 149. This service was removed in 2006 because of
financial performance that was below the minimum standard established by
Council. Those changes were not related to Council’s decision to adopt a
hub-and-spoke route network in connection with the light rail project but were
made because the services were not used by enough customers to justify their
costs and because the operating resources are better used elsewhere in the
system where they could provide greater benefits for transit customers.
Financial Implications
The costs of the service plan for 2007 have been provided in the Transit Services 2007 operating budget. The capital costs to improve downtown stops this year will be funded by the Transitway Systems Improvement account. Operating and capital funding for initiatives occurring beyond 2007 will be requested in respective budget years.
Public Consultation/Input
No consultation was carried out in the preparation of this report. Any service changes which are proposed related to the matters described in this report would be subject to the normal consultation processes defined in the Transit Service and Fare Policies adopted by Council.
RÉSUMÉ
Hypothèses et analyse
Le
nombre d’utilisateurs du réseau de transports en commun OC Transpo continue
d’augmenter d’environ 3 % par année. La capacité des voies du Transitway
de la zone centrale réservées aux autobus et des quais des rues Albert et
Slater est restreinte, et le niveau actuel de service en après-midi sur la rue
Slater est pratiquement à capacité maximale. Dans sa configuration actuelle, la
rue peut accommoder un maximum de 180 trajets d’autobus à l’heure depuis 2004
afin de maintenir un service fiable. La principale contrainte du système est le
quai en direction est de la rue Slater à l’est de la rue Metcalfe.
En
2007, le personnel se penche sur trois stratégies visant à réduire la pression
exercée sur la capacité de la rue Slater et à améliorer la circulation des
autobus et la fiabilité du service sur la rue Slater au cours des prochaines
années. Ces stratégies portent sur :
1. l’amélioration des quais en vue de réduire le temps d’embarquement;
2. l’augmentation de l’utilisation des circuits de contournement;
3. le recours à des autobus articulés à grande capacité pouvant desservir
un plus grand nombre d’utilisateurs.
En
ce qui concerne les années ultérieures à 2007, et ce jusqu’à ce que des
décisions soient prises au sujet des futurs projets de transport en commun
rapide, d’autres solutions potentielles seraient :
Le
tableau ci-dessous montre le nombre de trajets d’autobus en direction est qui,
selon les attentes, seront nécessaires en période de pointe l’après-midi pour
chaque année de 2007 à 2010, les mesures que le personnel entend prendre pour
réduire ce nombre et le nombre de trajets d’autobus qui seront nécessaires une
fois que ces mesures auront été prises.
Année |
Nombre de trajets d’autobus avant la prise de mesures |
Mesures à prendre |
Nombre de trajets d’autobus après la prise de mesures |
2006-07 |
173 |
- Situation actuelle |
173 |
2007-08 |
191 (selon le plan des services en commun de 2007) |
- Amélioration du quai de Metcalfe - Utilisation d’autobus articulés pour
desservir plus d’utilisateurs |
182 |
2008-09 |
188 (182 plus une croissance de 3 %) |
- Utilisation d’autobus articulés pour
desservir plus d’utilisateurs - Plus de clients utilisant les circuits de
contournement |
182 |
2009-10 |
188 (182 plus une croissance de 3 %) |
- Utilisation d’autobus de plus grande
capacité pour desservir plus d’utilisateurs - Plus de clients utilisant les circuits de
contournement - Systèmes d’information des passagers - Mode de paiement par carte à puce |
182 |
Après
2010 |
190+ |
- Utilisation d’autobus de plus grande
capacité pour desservir plus d’utilisateurs
- Projets potentiels de transport rapide - Consolidation des lignes express
|
|
Le 6
décembre 2006, le Conseil a renvoyé au Comité du transport en commun une motion
ayant été déposée en vue d’instaurer à nouveau des circuits d'autobus directs à
destination du centre-ville pendant la période de pointe du matin sur les
circuits 126, 148 et 149. Ce service a été supprimé en 2006 parce que son
rendement financier était inférieur à la norme minimale établie par le Conseil.
Ces changements n’étaient pas liés à la décision du Conseil d’adopter un réseau
en étoile dans le cadre du projet de système léger sur rail, mais bien parce
que trop peu d’utilisateurs recourraient à ces services pour justifier leurs
coûts et parce que les ressources affectées à l’exploitation sont mieux utilisées
ailleurs dans le réseau là où elles procurent de plus grands avantages aux
clients.
Répercussions
financières
Les
coûts du plan de service pour 2007 ont été fournis dans le budget de
fonctionnement des services de transport en commun pour 2007. Les coûts d’immobilisations pour améliorer
les arrêts du centre-ville seront imputés au compte d'amélioration du réseau du
Transitway. Les fonds de fonctionnement
et d’immobilisations pour les initiatives mises en place après 2007 seront
demandés dans les budgets des années respectives.
Consultation
publique/commentaires
Aucune consultation n’a été menée dans le cadre
de la préparation du présent rapport. Tout changement de service proposé
concernant les sujets décrits dans le présent rapport serait soumis au
processus normal de consultation défini dans les politiques sur le service du
transport en commun et sur les tarifs adoptées par le Conseil.
BACKGROUND
General
Transit ridership on the OC Transpo system continues
to grow by approximately three percent each year. This continuing growth requires that the capacity of the system
to carry customers also be increased each year. The capacity of Albert and Slater Streets to accommodate bus
operations is limited, and the currently scheduled level of service eastbound
on Slater Street in the afternoon peak hour is near the physical capacity limit
of the street. As it will take several
years to implement any rapid transit plan on which Council may decide, it is
necessary that a strategy be in place to accommodate the continuing growth of
ridership on the transit system without exceeding the physical capacity of the
street network. This report presents
for the information of Council the strategies that staff are using to manage
the growth of the transit system over the next several years.
Motions
At its meeting of December 6, 2006, Council
considered the following motion and referred it to the Transit Committee:
MOTION NO. 2/6
Moved by Councillor M.
Bellemare
Seconded by Councillor P.
Hume
WHEREAS in 2005 City Council
approved resolutions aimed at addressing concerns regarding the proposed
integration of both light rail transit and bus rapid transit on Albert and
Slater Streets;
AND WHEREAS the resolutions
included a direction to ensure that a minimum of 30 percent of bus traffic be
removed from Albert and Slater Streets by the end of 2009;
THEREFORE BE IT RESOLVED
that, in the light of the amended North-South Light Rail Transit Project, the
direction be set aside, and that the removal of downtown trips on Routes 126,
140, 148 and 149, implemented in 2006, be reversed, and that staff report to
Transit Committee each year on the operating conditions on Albert and Slater
Streets.
MOTION NO.
2/7
Moved by
Councillor R. Chiarelli
Seconded by
Councillor D. Deans
That Motion No. 2/6 be
referred to the Transit Committee.
REFERRAL CARRIED
2005 Directions by
Council
The approved environmental assessment for the
proposed North-South Light Rail line called for the trains to operate in the
same transit lane as the buses on Albert and Slater Streets. To support this operation and to address
concerns raised by downtown businesses, Council directed staff to reduce bus
operation on Albert and Slater Streets once the light rail line was open. This reduction would have been based on a
larger reorganization of the transit route network. In the “hybrid hub and spoke network,” there would have been
fewer direct-to-downtown routes, but those that remained would have run more
frequently. There would also have been
improved cross-town routes bypassing downtown via Carling and Baseline/Heron,
to carry customers who previously travelled through downtown but were not
travelling to or from points in downtown.
And, the light rail line itself would have carried many customers who
would otherwise need to ride buses.
The opening of the light rail line and the change to
the “hybrid hub and spoke network” would have reduced the number of bus trips
by 29 percent eastbound on Slater in the afternoon and westbound on Albert in
the morning, by 12 percent westbound on Albert in the afternoon, and by two
percent eastbound on Slater in the morning.
With the cancellation of the light rail project in
December 2006, the “hybrid hub and spoke network” can no longer be implemented
as approved. While current planning
processes for the future of rapid transit are underway, there are elements of
the revised network plan that are valuable and which are incorporated into the
strategies described in this report.
DISCUSSION
Capacity
Limits
Experience since 2003
The most congested corridor on the entire transit system is eastbound service on Slater Street and the Mackenzie King Bridge in the afternoon peak period. The most congested point on Slater Street is the bus stop on Slater east of Metcalfe Street.
During the year 2003-04, continuing growth in transit ridership and the resulting required growth in the level of service provided on the transit system led to congestion eastbound on Slater and particularly at Metcalfe exceeding the capacity of the road system. The result was severe delays to eastbound service, affecting not only customers heading east at that time but also customers across the entire transit system as buses were delayed on their eastbound trips from downtown and also on their subsequent trips in other places.
Following the severe delays to service in 2003-04, eastbound services in the afternoon peak period were changed in September 2004. Routes which are not used to travel to points along the Transitway were moved from Slater Street to Queen Street – this affected Routes 3, 221, 231, 232, and commuter services to points outside Ottawa. Routes with the lowest ridership from downtown were cut back to start at Hurdman Station – this affected Routes 124, 126, 140, 148, and 149. These changes reduced the number of buses operating eastbound on Slater in the busiest hour from over 200 to fewer than 180.
As a result of these modest changes, reliability
improved markedly. It has become clear
from experience that, with the current conditions, the number of bus trips
scheduled to run east on Slater Street in the afternoon should not exceed 15 in
five minutes or 180 in an hour. Beyond
that number, reliability declines quickly, travel time increases quickly, and
operating costs will in turn increase as time is added to the schedules to
allow for this extra delay. (Note that
the same limit of 180 bus trips per hour does not apply in the morning when
passenger service time at the platforms is shorter. There will be a limit to capacity in the morning, but it has not
yet been reached.)
The following table shows how average travel times
through downtown were high in 2003-04 when too many bus trips were scheduled
and how times reduced after 2004 when the number of bus trips was reduced.
Years |
Number of Scheduled Bus
Trips |
Average Travel Time in
Peak Hour, LeBreton Station to Campus
Station |
2003-04 |
203 |
23 minutes |
2004-05 |
170 |
16 minutes |
2005-06 |
170 |
15 minutes |
2006-07 |
173 |
16 minutes |
The table shows that average travel time on Slater Street in the afternoon peak hour reached 23 minutes in 2003-04 and that it declined to 16 minutes after the service changes in September 2004. Note that the table shows the average travel time for all bus trips over an eight-month period; on particular days with bad weather or other causes, the average travel times were much higher.
Since 2004, ridership growth east from downtown in the afternoon peak period has been managed by the careful assignment of high-capacity articulated buses and the careful scheduling of trips at this critical time. Improvements to cross-town routes that bypass downtown have allowed and encouraged some customers to avoid travelling through downtown. Travel times on the Central Area Transitway are monitored daily, and weekly reports are examined internally to ensure that problems are identified as they arise.
Road Capacity for Buses and Platform Capacity for Passengers – General Comments
The critical time of day for bus operating capacity
on downtown streets is the afternoon peak period, and the critical direction is
eastbound on Slater Street.
The morning is less of a restriction than the
afternoon because in the morning most passengers are stepping off buses by all
doors, paying no fares, and walking directly away from the bus stop toward
their destinations. In the afternoon,
most passengers are arriving at the platforms, joining the group of customers
already there, waiting for a bus on a particular route, boarding mostly by the
front door of buses (boarding by the rear door by pass-holders is allowed on
articulated buses), and paying a fare or showing a pass.
The number of buses is greater heading west on
Albert in the morning and east on Slater in the afternoon than in the other
directions because the number of customers is 25 percent higher travelling from
and to the east of downtown than from and to the west. This is largely due to the connection of the
Southeast Transitway to the East Transitway east of downtown at Hurdman
Station.
Most of the traffic signals along Albert and Slater
streets are set to change on a 55-second cycle. This is the interval that Traffic and Parking Operations Branch
has found over time provides the best balance between the east-west needs of
the heavy transit operation and the north-south needs of auto traffic. This interval also corresponds closely to
the length of time that is required for buses to go through a green light, stop
at the next bus platform, drop off and pick up customers, and move off from the
stop, ready to go through the next green light.
Each bus platform along Albert and Slater Streets is approximately 55 metres long, and has room for either three 60-foot (18-metre) articulated buses or four standard 40-foot (12-metre) buses. As many articulated buses are required to carry the volume of customers on the busiest routes, there are rarely four 40-foot buses in a row, and the service is planned to have no more than three buses move through each green light. At three buses every 55 seconds and with 55-metre platforms, the maximum number of buses that can move through downtown in an hour is 195. Any delay of more than a very few seconds, which could result from such things as weather, a delivery truck in the bus lane, or a bus stopping twice at one platform, takes away capacity which can never be regained until the service levels diminish later on in the afternoon.
During the afternoon peak period, when transit
ridership is the highest (and when as a result the number of bus trips required
is the highest) and when queuing and boarding time the longest, it has become
clear from experience that there is a critical maximum number of buses that can
be accommodated reliably on Slater Street.
During the year 2003-04, the scheduled number of bus trips running east
on Slater Street during the afternoon peak hour was so high that operation
became unreliable. Long queues of buses
developed on Slater Street west from the platform at Metcalfe Street, the
busiest stop in downtown and the stop with the worst location and
configuration. As a result, the travel
time increased for all customers, especially for those travelling late in or
after the busiest hour.
Delay resulting from congestion causes inconvenience
for customers by increasing their travel time and also by increasing the
variability of travel time, making on-time reliability worse at stops along the
route after the zone of congestion. The
cost to allow for delay in the schedules of bus routes is very high. Each minute of delay on Slater Street in the
busiest hour of the afternoon rush hour requires three more buses to be in
service, at a capital cost of approximately $1.5 million and an operating
cost of approximately $260,000 per year.
Key Problem Locations
The busiest bus stop along Albert and Slater streets
is the eastbound platform at Metcalfe Street.
This stop is used by 5,000 customer-trips each day boarding buses and
4,400 customer-trips alighting from buses.
The platform is poorly located, in three ways:
More information about the poor location and poor
arrangement of the eastbound Metcalfe platform is provided in Document 1, from
a report prepared for the City by consulting engineers in 2005.
Other downtown platforms which have poor configurations that are secondary sources of delay are:
Actions Being Taken in 2007
1. Improving Platforms
Staff are making improvements this year to the most
significant bottleneck on the transit system, the eastbound platform on Slater
Street just east of Metcalfe Street.
Building on the understanding reached between the City and Hydro Ottawa
during the planning for the light rail project, the plans are to move the
platform further east so that it is nearer the centre of the block, to
straighten the curb so that customers have a better view of the second and
third buses approaching the platform, and to make the platform deeper to reduce
conflicts among transit customers and with other pedestrians.
Also in 2007, improved passenger waiting facilities
and an improved southbound platform will open at Laurier Station, as part of a
new building under construction by the University of Ottawa, and staff will
make small improvements to the configuration of the eastbound platform on
Slater Street at Kent Street, by adjusting the location of the bus stop marker
slightly and by installing additional railings to guide waiting customers and
bus operations.
Other improvements may be possible to the eastbound
platform on Slater Street at Bank Street as part of an adjacent development,
and to the westbound platforms on Albert Street at Metcalfe Street and at Bay
Street by reconfiguring the platforms, sidewalks, and bus stop and shelter
locations.
2. Downtown Bypass Routes
Between five and ten percent of all customers who travel on buses through downtown are travelling between points that are not within downtown (e.g., Orléans to Algonquin College), and could be accommodated on bus routes that bypass downtown if the travel times were more attractive. To encourage these customers to shift to bypass routes, improvements were made in 2006 and are being made in 2007.
In 2006, the frequency of service on cross-town
Routes 101/102 was improved and a new link was introduced between Orléans and
Tunney’s Pasture via Carling Avenue and Holland Avenue.
Following the 2007 Transit Service Plan and as part
of the 2007 City operating budget, Council has approved funding for the
extension of Route 118 to provide cross-town service from Orléans to Baseline
Station via Heron and Baseline during peak periods and for the extension of
most trips on Route 101 (Orléans-Blair-Bayshore-Kanata) to Orléans. The improvements to Route 101 began in
April 2007 and the extension of Route 118 will be in place from September 2007.
3. High-Capacity Articulated Buses
Customers can be carried on fewer buses when more customers are carried on each bus. The OC Transpo system now has 227 60-foot articulated buses. These have 54 seats (as compared with 41 seats on a standard 40-foot bus) and normally carry 70 customers (as compared with 45 on a standard 40-foot bus).
In September 2007, ridership growth on frequent
east-end express and direct-to-downtown routes will be accommodated by
converting trips to use 60-foot articulated buses rather than by adding more
trips using standard 40-foot buses.
Routes 20, 22, 24, 29, 31, 33, 35 and 94 are expected to require service
increases in September 2007 because of growing ridership, and this growth will
be accommodated by converting trips during the busiest hour to use articulated
buses instead of 40-foot buses. This will provide the required increase in
capacity without increasing the number of bus trips scheduled eastbound on
Slater Street in the afternoon peak period. (Service increases are also
expected to be required on Routes 95 and 97, but as these routes already use
articulated buses, the growth will be accommodated by adding more trips.)
Another advantage of increasing the use of articulated buses is that boarding
time is reduced as all-door boarding is allowed for pass-holders on articulated
buses.
The articulated buses will be made available by
converting trips elsewhere in the system to use 40-foot buses instead of
articulated buses and by adding trips so that the capacity remains the same or
is increased appropriately to accommodate the expected growth. This change is expected to affect Routes 61,
66, 70, 71, 76 and 118, and may also affect Routes 4 and 180.
Fifty-seven new 60-foot articulated buses are being
acquired for delivery in 2008. With a small internal reconfiguration, the new
buses are expected to have 55 seats, one more than the current articulated
buses. These additional articulated buses will allow capacity to continue to be
increased on busy routes without increasing the number of trips required.
Other Possible Future Solutions
1.
Use of Other Streets in Downtown
Transit Services staff and
Traffic and Parking Operations staff have worked together to identify other
streets within downtown that could accommodate some of the bus operations that
are now on Albert and Slater Streets.
It is possible to add up to 25 bus trips per hour in
the afternoon peak period to operate east on Wellington Street or Queen Street,
south on Elgin Street and east on the Mackenzie King Bridge. Buses from Gatineau could reach this route
from the Portage Bridge and buses from the west could reach this route via Bay
or Kent Street, as Routes 3, 15, 16 and 18 do now. It is also possible to move some trips in the morning peak period
to operate west via Queen Street to be consistent with the afternoon routing.
Currently, Transit Services staff are working to
evaluate whether any routes should be changed to use Wellington and Queen
Streets in 2007 or 2008. One
possibility is to move the routes crossing the Portage Bridge from Gatineau –
Routes 27 and 40 and a possible new Transitway route from Gatineau to Orleans –
to use Wellington Street or Queen Street on their eastbound trips. Any proposed route changes would be
described to Transit Committee in a subsequent report and would be subject to
the normal consultation processes defined in the Transit Service and Fare Policies
approved by Council.
The advantage of moving routes to use Wellington and
Queen Streets is that fewer trips would operate on Albert and Slater Streets,
both reducing congestion and allowing road capacity for growth. However, the benefit of a consistent set of
bus stops for customers to board buses heading east and south would be
diminished, and the travel time for customers may be longer on the other
streets than it is on the bus-only lanes on Albert Street and Slater Street.
Moving routes to other streets west of the Rideau Canal will also not address
congestion at Mackenzie King Station and Laurier Station, and those stations
could develop into bottlenecks after the congestion on Slater Street at
Metcalfe Street is addressed.
2. High-Capacity Double-Decker
Buses
Staff are continuing the evaluation of the suitability of double-decker buses in the OC Transpo bus fleet. The demonstrator double-decker bus passed its in-service tests in the summer of 2006 and the winter of 2007, and has passed its specific winter tests for heating and on-road handling. During the spring of 2007, staff are estimating the costs that would be required to configure a bus maintenance and storage facility to handle double-decker buses, estimating the costs to make changes to on-road infrastructure to increase the clearance height for double-decker buses, and assessing the impact that the use of double-decker buses would have on the pavement of City streets and the Transitway. Based on the outcome of these evaluations and on the benefits that double-decker buses would have for customers and for operations, a recommendation will be developed by mid-2007.
The model of double-decker bus that has been tested would have 84 seats (as compared with 54 on the current articulated buses) and would normally carry approximately 100 customers (as compared with 70 on an articulated bus). If double-decker buses were found to be suitable for use in Ottawa, they would allow capacity to be further increased on busy routes beyond what is possible with articulated buses without increasing the number of trips required.
3. Real-time Signage
In the longer term, electronic real-time bus arrival signs are planned for installation at the downtown platforms. Information about the order of bus arrivals would enable customers to organize themselves better at the platform. The electronic signs would need to be planned and budgeted for installation in a future year. The continuing installation of “SmartBus” GPS location systems and “Discus” transponders on board all buses is essential to allow the presentation of precise information on the order of buses arriving at the platforms and on the time until the arrival of the next trip on each route. Real-time information will reduce boarding time at the downtown platforms.
4. O-Train Improvement/Expansion
The current O-Train service contributes toward
reducing the need for additional service eastbound on Slater in the afternoon
peak period. Some customers leaving
downtown for southern areas such as Greenboro use routes that run west on
Albert Street and transfer to the O‑Train at Bayview Station. Others travel between points such as
Tunney’s Pasture and Greenboro and use the O-Train in preference to riding
buses through downtown and around via Hurdman Station.
Any future extension of the O-Train service, such as
to Leitrim, would further contribute to reducing the capacity problem on Slater
Street. The more customers who travel
from downtown to southern points such as Greenboro, Leitrim, and Riverside South
who ride buses west out of downtown and transfer to the O-Train at Bayview
Station, the more capacity on Slater Street will remain open for customers who
must travel east.
Staff will also evaluate whether changes should be
made to bus routes in places such as Riverside South, Leitrim, Greenboro, Hunt
Club, Uplands, and Alta Vista that would improve service for customers and
address the imbalance of demand within downtown by encouraging customers to use
the O-Train and travel in and out of downtown via Bayview Station rather than
via Hurdman Station. Any service changes would be subject to the normal
consultation processes defined in the Transit Service and Fare Policies adopted
by Council. If any physical changes
were recommended at O-Train stations, they would be planned and budgeted for
installation in a future year.
The plan for the next three years is to manage
service in the central area through:
·
Use
of high capacity buses;
·
Improvements
of platforms;
·
Moving
some service onto other streets; and,
·
Attracting
customers to cross-town bypass routes.
However, as growth continues, there will come a time
when improved use of the available capacity will need to be forced by operating
fewer individual bus routes and thus offering customers reduced choice. The timing of this will depend on Council’s
decisions on rapid transit.
Currently, Transitway routes, express routes, and
direct-to-downtown routes provide direct service from downtown to almost all
bus stops east of Blair Road or south of Walkley Road, in addition to most
stops inside those points. The
provision of direct services certainly has contributed over the years to the
high ridership on the OC Transpo system, but as the eastbound capacity on
Slater Street is gradually exhausted, it will not be possible to retain all of
those direct services. The
disadvantages of removing the direct services will at some point be less than
the benefit of operating reliable service for all customers.
The consolidation of express routes into fewer
express routes was a major characteristic of the “hybrid hub and spoke network”
that Council adopted in 2005. In
Orléans, for example, 14 express routes would have been replaced by five
express routes. The consolidated
express routes would have operated more frequently than the current express
routes, could have been frequent enough to support high-capacity buses, would
have been aligned along arterial roads and major collectors and would have
required customers to walk further to points away from these primary
roads. (Local bus routes would have
continued to provide service on minor collectors and local roads.) By operating fewer express routes, the frequency
of each would be higher. By operating
more frequent services, the waiting times at downtown stops would be reduced
and the number of customers waiting at any particular time would be reduced as
a result.
It may be necessary in the longer term beyond 2010
to start to consolidate express routes in the east and south. The first would likely be pairs or groups of
routes that operate near each other to serve adjacent areas, or routes with
very low ridership and thus low frequency.
Any proposed route changes of this type would be presented to customers
for comment, following the normal consultation processes defined in the Transit
Service and Fare Policies approved by Council, and would be described to
Transit Committee in a report at that time.
6. Smartcard Fare System
The Smartcard Electronic Fare Collection system will
reduce boarding times at the downtown platforms by reducing the number of
people who need to pause at the front entrance of buses to pay their
fares. Funding for the Smartcard fare
system was approved by Council in the 2007 budget and, if the implementation
plan is approved, installation could begin in 2008 and be completed by
2009.
Evaluation of Council
Motion
Motion No. 2/6 of December 6, 2006, that was
referred by Council to the Transit Committee (see the background section of
this report) asks that morning peak period trips on Routes 126, 140, 148 and
149 be extended to downtown as they were before 2006.
While the removal of the downtown extensions of
these three routes was consistent with the then-current Council direction to
adopt a hybrid hub-and-spoke network, this was not the reason that the changes
were made. The 2006 service changes on these routes did not affect the
reliability of service on Slater Street in the afternoon peak period, because
the changes in 2006 affected only the morning trips to downtown. The afternoon trips from downtown on these
three routes had already been removed in 2004.
All sections of all routes are evaluated each year
to determine their financial performance and to find whether the financial
performance meets the minimum standard set by Council. The downtown extensions
of Routes 126, 140, 148, and 149 in the morning peak period had financial
performance measures that were worse than the minimum standard. This meant that each service was not used by
enough customers that the benefit of the service justified the cost to provide
it, and that operating resources were better used elsewhere in the system where
they could provide greater benefits for transit customers.
The morning trips to downtown should not be
reintroduced, because the benefit that they would provide does not justify the
cost required to operate them.
CONSULTATION/PUBLIC NOTIFICATION
No consultation was carried out in the preparation of this report. Any service changes which are proposed related to the matters described in this report would be subject to the normal consultation processes defined in the Transit Service and Fare Policies adopted by Council.
TRANSPORTATION MASTER PLAN
Section 7.2 of the Transportation Master Plan lays out the City’s primary principles for the delivery of a high-quality transit service. The policies in this section were supplemented by the Transit System Management Policies approved by Council in 2005. Among the priorities in the TMP and the policy document are the provision of reliable service, expansion of the service to serve increasing numbers of customers, and the need for a balance between convenience for individual groups of customers and overall benefits for the greater number of customers.
FINANCIAL IMPLICATIONS
The costs of the service plan for 2007 have been provided in the Transit Services 2007 operating budget. The capital costs to improve downtown stops this year will be funded by the Transitway Systems Improvement account. Operating and capital funding for initiatives occurring beyond 2007 will be requested in respective budget years.
SUPPORTING DOCUMENTATION
EXCERPTS FROM
CENTRAL AREA TRANSITWAY SYSTEM MANAGEMENT STUDY (DILLON CONSULTING FOR
CITY OF OTTAWA, MARCH 2005) DOCUMENT 1
SLATER AT METCALFE
Excerpts from Central Area Transitway System Management Study
(Dillon Consulting for City of Ottawa, March 2005)
Metcalfe Station (Slater Street) is
considered to be the critical station within the Central Area Transitway. A
number of existing conditions at the station contribute to poor operations,
delay, and lost capacity.
1.
Buses are sometimes unable to pass through the intersection on their
first opportunity because the previous platoon is not clear of the station,
causing a cycle failure and wasting the green time; and
2.
The average process time per platoon is increased due to an increase in
the “enter/exit station” component (i.e., the buses are stored further from the
station and require more time to enter the station).
Observations of the corridor show that
Metcalfe Station (eastbound) is a significant bottleneck within the Slater
Street corridor. It processes the highest number of PM peak period boardings of
all stations in the Central Area Transitway, and is behind only the Mackenzie
King Stations (eastbound and westbound) for total passenger activity. Given the
current design of the platform, which is narrow and recessed at its west side,
there is little room for passenger or pedestrian flow. The angle of approaching
buses also makes it difficult to see their route number, leading to longer bus
recognition times, dwell times, and, therefore, process times.
Metcalfe Station (Slater Street) is also the only “far side” stop in the Central Area Transitway system. Traffic signal operations play a more significant (and detrimental) role in the operation of Metcalfe Station (eastbound) and station capacity is lost due to cycle failures.