4. CARDINAL CREEK STORMWATER FACILITY DEVELOPMENT CHARGE

REDEVANCE D’EXPLOITATION POUR L’INSTALLATION DE GESTION DES EAUX PLUVIALES DU RUISSEAU CARDINAL

 

 

Committee Recommendations

 

That Council:

 

1. Approve the City entering into a revised development charge front-ending agreement, based upon the principles set forth in this report, for the cost of the construction of a storm water management pond and trunk storm sewers with several of the developers within the Cardinal Creek watershed.

 

2. Refer to the 2004 Capital Budget Review the amendment of the funding for the capital project for this purpose from $18.01 million to $18.96 million.

 

3. Approve that the Cumberland Development Charge By-law be amended to reflect the participating and non-participating areas, to reflect the new project amount and new benefiting area and inclusion of all carrying costs of the project so that all costs continue to be recovered through the area specific development charge.

 

4. Approve that for the Phase 1A and the non-participating owners that the charge be payable upon the earlier of the registration of a plan of subdivision and the issuance of a building permit.

 

5. Adopt the background study prepared by C.N. Watson and Associates Ltd dated 11 September 2003 in respect of the Cardinal Creek Stormwater Facility.

 

 

Recommandations du comité

 

Que le Conseil municipal :

 

1. approuve que la Ville conclue avec plusieurs promoteurs du bassin hydrographique du ruisseau Cardinal une entente préliminaire sur les redevances d’exploitation révisées, selon les principes énoncés dans le présent rapport, pour défrayer les coûts de construction d’un bassin de rétention des eaux pluviales et de collecteurs d’égouts pluviaux;

 

2. soumette à l’étude du budget des immobilisations de 2004 la modification des fonds destinés au projet d’immobilisation aux fins de ces travaux, lesquels passeront de 18,01 à 18,96 millions de dollars.

 

 

 

3. approuve la modification du Règlement municipal sur les redevances d’exploitation de Cumberland en vue de tenir compte des secteurs participants et non participants, des nouveaux coûts du projet et les nouveaux secteurs qui en bénéficieront ainsi que de l’intégration de tous les coûts de détention du projet afin que tous les frais continuent de faire l’objet de mesures de recouvrement sous la forme d’une redevance d’exploitation spécifique au secteur.

 

4. approuve que, pour la phase 1A et pour les propriétaires non participants, la redevance soit payable dès la première inscription d’un plan de lotissement et la délivrance d’un permis de construire.

 

5. adopte l’étude préliminaire rédigée par C.N. Watson and Associates Ltd. en date du 11 septembre 2003 sur l’égout pluvial du ruisseau Cardinal.

 

 

 

 

 

Documentation

 

1. Development Services Department General Manager's report dated 14 October 2003 (ACS2003-DEV-APR-0234).

 

2. Extract of Draft Minutes, 21 October 2003.


 

 


Report to/Rapport au :

 

Corporate Services and Economic Development Committee

Comité des services organisationnels et du développement économique

 

and Council / et au Conseil

 

14 October 2003 / le 14 octobre 2003

 

Submitted by/Soumis par : Ned Lathrop, General Manager/Directeur général,

Development Services/Services d'aménagement 

 

Contact Person/Personne ressource : Larry Morrison, Manager, Infrastructure Approvals / Gestionnaire, Approbation des demandes d’infrastructure

(613) 580-2424 x27807, larry.morrison@ottawa.ca

 

Ref N°: ACS2003-DEV-APR-0234

 

 

SUBJECT:

CARDINAL CREEK STORMWATER FACILITY DEVELOPMENT CHARGE

 

 

OBJET :

REDEVANCE D'EXPLOITATION POUR L'INSTALLATION DE GESTION DES EAUX PLUVIALES DU RUISSEAU CARDINAL

 

 

REPORT RECOMMENDATIONS

 

That the Corporate Services and Economic Development Committee recommend Council:

 

1. Approve the City entering into a revised development charge front-ending agreement, based upon the principles set forth in this report, for the cost of the construction of a storm water management pond and trunk storm sewers with several of the developers within the Cardinal Creek watershed.

 

2. Refer to the 2004 Capital Budget Review the amendment of the funding for the capital project for this purpose from $18.01 million to $18.96 million.

 

3. Approve that the Cumberland Development Charge By-law be amended to reflect the participating and non-participating areas, to reflect the new project amount and new benefiting area and inclusion of all carrying costs of the project so that all costs continue to be recovered through the area specific development charge.

 

4. Approve that for the Phase 1A and the non-participating owners that the charge be payable upon the earlier of the registration of a plan of subdivision and the issuance of a building permit.

 

5. Adopt the background study prepared by C.N. Watson and Associates Ltd dated 11 September 2003 in respect of the Cardinal Creek Stormwater Facility.

RECOMMENDATIONS DU RAPPORT

 

Que le Comité des services organisationnels et du développement économique recommande au Conseil municipal :

 

1. d'approuver que la Ville conclue avec plusieurs promoteurs du bassin hydrographique du ruisseau Cardinal une entente préliminaire sur les redevances d'exploitation révisées, selon les principes énoncés dans le présent rapport, pour défrayer les coûts de construction d'un bassin de rétention des eaux pluviales et de collecteurs d'égouts pluviaux;

 

2. de soumettre à l'étude du budget des immobilisations de 2004 la modification des fonds destinés au projet d'immobilisation aux fins de ces travaux, lesquels passeront de 18,01 à 18,96 millions de dollars.

 

3. d'approuver la modification du Règlement municipal sur les redevances d'exploitation de Cumberland en vue de tenir compte des secteurs participants et non participants, des nouveaux coûts du projet et les nouveaux secteurs qui en bénéficieront ainsi que de l'intégration de tous les coûts de détention du projet afin que tous les frais continuent de faire l'objet de mesures de recouvrement sous la forme d'une redevance d'exploitation spécifique au secteur.

 

4. d'approuver que, pour la phase 1A et pour les propriétaires non participants, la redevance soit payable dès la première inscription d'un plan de lotissement et la délivrance d'un permis de construire.

 

5. d'adopter l'étude préliminaire rédigée par C.N. Watson and Associates Ltd. en date du 11 septembre 2003 sur l'égout pluvial du ruisseau Cardinal.

 

BACKGROUND

 

Council adopted Planning and Development Committee Report 20, Item 18 on 9 January 2002 to provide for the financing of the Cardinal Creek Storm Water Management Facility and Related Trunk Storm Sewers.  Although consultation did take place with the interested parties and no comments were received by Committee when it considered the report, shortly after the adoption of the report, concerns were expressed by several developers with respect to the perceived inequity, discussed below, in the approach taken in the report.

 

The approach in Report 20, Item 18 involved the division of the landowners in the Cardinal Creek watershed into "participating" and "non-participating" owners.  The participating owners would pay for a portion of the cost of Stage 1 of the stormwater works based upon the expected yield of dwelling units from their land.  (Stage 1 of the Cardinal Creek Stormwater works is set forth in Document 2 with the exception of the Provence Sewer.  Stage 2 is the construction of the Provence Sewer.  The costs for Stage 2 are expected to be incurred in 2005.)  Letters of credit to secure construction of the Stage 1 works were filed with the City.

 

The City would front-end the portion of the cost of the stormwater works that represented the cost attributable to the expected dwelling unit yield from the non-participating owners lands.  As the participating owners pulled building permits, they would receive a partial credit on the stormwater component on the development charge, approximately 57%, with the balance being kept by the City to assist in the reimbursement of the City for front-ending the non-participating owner's share.  As the non-participating owners finally develop their lands, 57% of the stormwater component of the development charge paid by them would go to participating owners, according to their respective shares of the total number of dwelling units to fulfil their entitlement to credits and the balance to the City to complete the repayment to it.

 

Subsequent to the adoption of the report by Council, certain of the participating landowners noted that they felt that the proposed scheme imposed an inequitable burden upon them.  The non-participating owners would only be called upon to make their payment towards the stormwater component at the time of registration of their plans of subdivision, in ordinary course a limited time before funds are obtained from the purchaser.  The participating owners on the other hand must front end a portion of the cost of the works and only receive their full credit when the last plan of subdivision is registered by the non-participating landowners.  While the stormwater component would be indexed in accordance with standard practice and interest would be paid on the outstanding credits to the participating landowners, it is acknowledged that the cash flow impact of the scheme proposed in January, 2002 was much greater upon the participating owners.

 

Further, development has proceeded much more quickly than anticipated in the Cardinal Creek Drainage Area.  Certain of the lands that fell within the non-participating area with development expected in the latter half of this decade are now ready to proceed.

 

Finally, as staff were discussing the means to deal with the question of inequity, it also became apparent that the cost of the Cardinal Creek Stormwater System would be greater than that anticipated.  As part of the 2001 budget deliberations, $11 million authority was approved for the Cardinal Creek Storm Water Management Facility and Sewers. The funding for the project was to be 100% front end financing by the developers (owners).  After extensive negotiations, the participating owners requested that the project limits be extended, adding approximately 900 meters of additional trunk storm sewers.  The additional length of storm sewer added $7 million to the overall project cost and this additional amount was subsequently included in the 2002 Capital Budget   With the receipt of tenders and the construction that has taken place to date, and taking into account the outstanding claims for property acquisition by the City, it is presently estimated that the cost of the Cardinal Creek Storm Water Management Facility is $18.96 million.

 

Staff agreed to pursue a means of dealing with the inequity on the understanding that for any building permit issued after 9 January 2002, the date of the original Council approval, the stormwater component of the development charge payable would be that which reflected the increased cost of the works.

 

 

DISCUSSION

 

The revised proposal is premised on there being three area specific charges rather than one.  Three areas would be identified for the Cardinal Creek watershed, one each respectively for the geographical areas of the original participating owners, one for the owners, originally non-participating but now ready to proceed with development (the Phase 1A owners) and one for the remaining non-participating owners.  The participating landowners would continue to be responsible for paying up front to the City their proportionate share of the Phase 1 works.  However, they would receive a 100% credit back against the revised stormwater component of the development charges.

 

For the Phase 1A owners, it is proposed that the base charge applicable to them be approximately 8.4% higher than that applicable to the participating owners.  This reflects the fact that the participating owners have paid the charge for building permits issued over the past several years and that they have posted letters of credit since 2002.

 

The development charge applicable to the non-participating owners would be the charge applicable to the Phase 1A owners, with a phased-in increase of 6% per year in the case of the former.  This amount reflects the estimated financing cost to the City of the infrastructure.  It continues to be recommended that, for both the Phase 1A and non-participating owners such charge be collected at the time of the registration of a plan of subdivision (or at the issuance of a building permit if there is no plan of subdivision).  Should, through the lifting of part lot control or otherwise the number of units on the plan exceed that anticipated at registration, payment of the stormwater development charge will be required for the additional units.

 

CONSULTATION

 

Staff have met with landowners on a number of occasions.  In accordance with the Development Charges Act, notice of the public meeting was provided in the Ottawa Citizen and Le Droit on 1 October 2003.

 

FINANCIAL IMPLICATIONS

 

As set out in Document 2, the estimated cost of the Cardinal Creek Stormwater Works is estimated to be $18.956 million.  It is further estimated that approximately 98% of the development in the drainage area will be residential and 2% commercial.  Deducted from the cost of the system is the amount of $2.05 million, being the available reserve funds for this project as of 9 January 2002.

 

With respect to residential development, 4,452 single-detached equivalent units are anticipated to be located with the drainage area, post 2001.  The division between the participating, Phase 1A (Additional Participating Development) and non-participating area is set forth in Document 3.  The resulting charge attributable to the participating owners for a single detached dwelling will be $3,625, to a Phase 1A owner will be $3,928 and that initially to a non-participating owner, assuming development in 2004, $4,164.

 

To the extent that the monies are received sooner or later than expected, there will be an opportunity to revisit the charge, including with the comprehensive review of all City development charges to take place in 2004.

 

INDEXING

 

As the participating owners have contributed already in accordance with their proportionate share to the cost of the Cardinal Creek Stormwater Works, as well as providing letters of credit, the charge payable in respect of their lands will not be indexed.  As noted above, the charge to the Phase 1A and non-participating owners reflects a phase-in charge of 6% per year to reflect the financing cost to the City.  No indexing will take place beyond the phase-in.

 

 

SUPPORTING DOCUMENTATION

 

Document 1 - Cardinal Creek Storm Drainage Area Benefiting Development (Map)

Document 2 - Cardinal Creek Storm Drainage Project Cost Estimates

Document 3 - Cardinal Creek Storm Drainage Area Benefiting Development (Table)

Document 4 - Cardinal Creek Stormwater Facility - C.N. Watson and Associates (On file with City Clerk)

 

 

DISPOSITION

 

Legal Services, in cooperation with Development Services, will submit the necessary by-law amendments and revise the front-ending agreements.

 

 


Document 1

 


Document 2

 


Document 3

 



CARDINAL CREEK STORMWATER
FACILITY DEVELOPMENT
CHARGE

REDEVANCE D’EXPLOITATION POUR L’INSTALLATION DE

GESTION DES EAUX PLUVIALES DU RUISSEAU CARDINAL

ACS2003-DEV-APR-0234

 

Mr. T. Marc, Solicitor, appeared before the Committee on this item.

 

Mark Labrosse, Vice and Hunter, Barristers and Solicitors, spoke on behalf of Legault Builders, a residential home builder primarily in the east end of the City.  He referenced Document 3 of the report, specifically the allocation of capacity set out between participating and non-participating developers.  He stated that his client has requested information from staff respecting the evolution of the allocation over various drafts of this report, and had concerns, not having received the requested information.  He stated their understanding of the ongoing climate of intensification, however given the area’s location in Orléans, highrise development does not follow the pattern in the area.  He further indicated that his client has been assured that development charges will proceed in accordance with development, however his client is not ready to put forward a draft plan of subdivision at this time and is concerned that non-participating developers may, at some date in the future, be required to pay more than the current indexing amount.  With respect to the location of stormwater in Orléans, he noted that his client will meet with the Regional Group to resolve their differences.

 

Mr. Marc indicated that this matter was originally before Council in 2002 and that thereafter, developers in the area expressed some concerns which staff indicated would be revisited.  Staff are thus bringing the report back, having taken the approach to divide the storm drainage area into three, being the original participating developers in January 2002 at a cost of $3,625; those who were not participating in 2002 but are ready to come on board now at a cost of $3,928; and the non-participating developers which include Legault Builders and the Regional Group at a cost of $3,928, increasing by six per cent per year to account for the lost opportunity cost to the City of the funds invested in the system.  The respective three implementing by-laws were included in the background study distributed separately to Committee.  Mr. Marc stated that staff were recommending approval of the report with the related by-laws for original and new participating developers scheduled for enactment at the November 19th Council meeting.  Discussions will continue to be held with Legault Builders and the Regional Group, and should a resolution be reached, the third by-law will be enacted on November 19th, otherwise enactment will be carried into 2004.

 

 

That the Corporate Services and Economic Development Committee recommend Council:

 

1. Approve the City entering into a revised development charge front-ending agreement, based upon the principles set forth in this report, for the cost of the construction of a storm water management pond and trunk storm sewers with several of the developers within the Cardinal Creek watershed;

2. Refer to the 2004 Capital Budget Review the amendment of the funding for the capital project for this purpose from $18.01 million to $18.96 million.

3. Approve that the Cumberland Development Charge By-law be amended to reflect the participating and non-participating areas, to reflect the new project amount and new benefiting area and inclusion of all carrying costs of the project so that all costs continue to be recovered through the area specific development charge.

4. Approve that for the Phase 1A and the non-participating owners that the charge be payable upon the earlier of the registration of a plan of subdivision and the issuance of a building permit.

5. Adopt the background study prepared by C.N. Watson and Associates Ltd dated 11 September 2003 in respect of the Cardinal Creek Stormwater Facility.

 

CARRIED