2. van gaal Municipal Drain INSTALLATIONS MUNICIPALES DE DRAINAGE VAN GAAL |
That Council
give third reading to the Van Gaal Municipal Drain By-law.
Que le
Conseil municipal lise
une troisième fois le Règlement sur les
installations municipales de drainage Van Gaal.
For the information of Council
The Court of Revision approved the following
motion:
That the Agriculture and
Rural Affairs Committee, in its capacity as the Court of Revision approve the
assessments as outlined in the Engineer's Report.
pour la gouverne du conseil
Le
Tribunal de révision a approuvé la motion suivante :
Que le Comité chargé de
l'agriculture et des questions rurales, en sa qualité de Tribunal de révision
approuve les évaluations décrites dans le rapport de l'ingénieur.
Documentation
1.
General Manager, Transportation, Utilities and Public Works report dated 10 July 2003 (ACS2003-TUP-UTL-0015).
2. Extract
of Draft Minute, Agriculture and Rural Affairs Committee of 21 July 2003.
Report to / Rapport au:
Agriculture and Rural
Affairs Committee
Comité chargé de l’agriculture et des questions rurales
Sitting as the Court of
Revision under the Drainage Act, R.S.O. 1990, c.D.17
Siégeant à titre de tribunal de révision en vertu de la Loi sur le
drainage,
L.R.O. 1990, c.D-17
and Council / et au Conseil
10 July 2003 / le 10 juillet 2003
Submitted by / Soumis par: R.T.
Leclair, General Manager / Directrice générale
Transportation, Utilities and Public Works / Transports, services et
travaux publics
Contact / Personne-ressource: P. McNally, Director / Directeur
Utility Services Branch / Direction des services publics
e-mail / courriel: Patrick.McNally@ottawa.ca
|
|
Ref N:
ACS2003-TUP-UTL-0015 |
SUBJECT: |
VAN
GAAL Municipal Drain |
|
|
OBJET : |
INSTALLATIONS
MUNICIPALES DE DRAINAGE VAN GAAL |
REPORT
RECOMMENDATION
That the Agriculture and Rural Affairs Committee, in
its capacity as the Court of Revision:
1.
Approve the Assessments as outlined in the Engineer's Report; and
2.
Recommend Council give third reading to the Van Gaal Municipal Drain
By-law.
Que le Comité chargé de
l'agriculture et des questions rurales, en sa qualité de tribunal de révision:
1. approuve les évaluations décrites dans le
rapport de l'ingénieur:
2. recommande au Conseil municipal de lire une troisième fois le Règlement municipal sur les installations municipales de drainage Van Gaal.
According to its Terms of
Reference, the Agriculture and Rural Affairs Committee is the Court of Revision
for the Purposes of the Drainage Act.
According to section 52(1) of the Drainage Act:
Any owner of land assessed for the drainage works who complains that any land or road has been assessed too high or too low or that any land or road that should have been assessed has not been assessed, or that due consideration has not been given as to type of use of land, may personally, or by agent, appeal to the court of revision by giving notice in writing to the clerk of the initiating municipality setting out the grounds of the appeal, and the appeal shall be heard by the court of revision.
Thus, the purpose of the
Court of Revision for this sitting is to hear appeals from landowners affected
by the proposed maintenance and improvements of the Van Gaal Municipal
Drain. Those appeals, if any, concern the
Engineer’s Report, which was prepared in accordance with the Act and
which was adopted by Council on 25 June 2003, after Council gave first and
second reading to the “Van Gaal Drain By-law, 2003” (“provisional
by-law”). The Engineer’s Report was
initiated in 2001, at the request of the City of Ottawa to accommodate the
development of a subdivision in the village of Richmond in Goulbourn Ward.
The drain is located in the
City of Ottawa, Goulbourn Ward, as shown on the site plan contained in Attachment
A. The drain was last improved
under the report of A. J. Graham Engineering Consultant Ltd., dated 7 December
1971. The Drainage Act states
that the new City of Ottawa is responsible for municipal drains located within
its geographic boundaries. The
associated costs are being apportioned to developer and owner of the Cedarstone
Subdivision, Guycoki (Eastern) Ltd.
DISCUSSION
The Drainage Act prescribes the process and
timelines that must be followed for any modification to a municipal drain. (The “Þ” below indicates the
current step in the process for the Van Gaal Municipal Drain.). In brief, the complete process includes:
·
Appoint
an Engineer to prepare the Engineer’s Report (Report completed November 2002);
·
Conduct an On-site Meeting with the landowners who will be affected to
review the proposed modifications (Completed 12 June 2001);
·
Conduct a Meeting to Consider - consideration by the Agriculture and
Rural Affairs Committee of the Engineer’s Report and the By-Law (Attachment
B) to adopt this report
(16 June 2003);
·
Council
approval of the Committee recommendation and first and second reading of the
By-law (25 June 2003);
·
Convene
a Court of Revision - a meeting of the Agriculture and Rural Affairs Committee,
where landowners may appeal their assessment.
The Court of Revision may direct the Engineer to revise the assessment
contained in the Report. All landowners
who are affected must then be advised of any revisions, and the Drainage Act
contains provisions for further appeal by landowners of their assessment;
·
Third
reading of the By-law at Council;
·
Construction
of the drainage works; and
·
Assessment
of the costs to benefiting landowners and road authorities.
The Drainage Act provides some guidance as to
how the Court of Revision is to proceed:
·
Section
55 states that in any appeal to the Court of Revision, if the engineer is called
upon to give evidence as to how an assessment was determined, the engineer must
give evidence before the appellant's case is presented.
·
Section 53 addresses those cases where the ground of appeal is
that lands or roads are assessed too high, and the Court of Revision is
satisfied that those assessments should be reduced. In such cases, where there is no evidence to indicate that the
amount of the reduction should be levied against lands or roads whose owners
are parties to the appeal, the court shall adjourn. The clerk must then notify such persons as the appellant may
specify, who are shown by the last revised assessment roll to be owners of land
affected. The notification must state
the date to which the hearing is adjourned.
At the renewed date, the Court must dispose of the matter and, where
appropriate, redistribute the assessments in such manner as appears just.
·
If the Court of Revision decides to change an assessment, section
56 states that notice of the change must be sent to affected owners and the
provisional by-law must be amended accordingly.
·
A party to an appeal to the Court of Revision may appeal from the
Court to the Agriculture,
Food and Rural Affairs Appeal Tribunal (section 54).
·
After the time for appeals to the Court of Revision has expired
and there are no appeals, or after the appeals have been decided, Council may
give third reading to the provisional by-law, thus authorizing construction of
the drainage works. The work may be
commenced ten days after the by-law is passed, if no notice of intention to
bring an application to quash it has been filed with the clerk [section 58(1)].
The Statutory Powers
Procedure Act, R.S.O. 1990, c.S.22 also applies to the Court of
Revision. This report requests that the
Agriculture and Rural Affairs Committee convene a Court of Revision as required
by the Drainage Act.
The Engineer’s Report
provides that the drain will be constructed incorporating design standards and
erosion control features to minimize the impacts of construction. The report has been distributed to the
Rideau Valley Conservation Authority for review.
Modifications to the Van
Gaal Drain will impact landowners in the watershed.
CONSULTATION
The On-Site Meeting, as
required under the Drainage Act, was held on 12 June 2001. All landowners in the watershed were
notified in advance of the meeting.
All landowners were notified
of the Meeting to Consider the Report and were provided with a copy of the
Engineer’s Report.
All landowners were provided
a copy of the provisional by-law and a notice of the time and location of the
first sitting of the Court of Revision.
The actual costs of the work
will be assessed to the developer of the Cedarstone Subdivision, Guycoki
(Eastern) Ltd. Future maintenance of
the drainage works will be assessed to the affected owners of lands in
accordance with the Schedule of Assessment “A” from the Engineer’s Report.
ATTACHMENTS
Attachment A - Van Gaal Municipal Drain Site
Plan
Attachment B - Van Gaal Municipal Drain
By-law
Attachment C - Notices of Appeal
Attachment D - Engineer’s Report (Held on file with the City Clerk)
DISPOSITION
Staff shall implement the decisions of the Court of Revision. A separate report shall be forwarded to Council concerning the outcome of the Court of Revision and, if appropriate, it will be recommended that Council give third reading to the provisional by-law.
ATTACHMENT A
Van Gaal Municipal Drain Site Plan
Attachment B
Van Gaal Municipal Drain
By-Law
BY-LAW NO. 2003 -
A by-law of the City
of Ottawa to provide for the improvement of drainage works in the City of
Ottawa – Van Gaal Municipal Drain.
WHEREAS the Van Gaal
Municipal Drain By-law, being By-law Number 12-72 of the Township of Goulbourn
was passed pursuant to the Drainage Act (now R.S.O. 1990, c.D.17);
AND WHEREAS the lands
referred to in By-law Number 12-72 of the Township of Goulbourn is now included
in the City of Ottawa by virtue of the City of Ottawa Act, 1999, S.O.
1999, c.14, Sch.E;
AND WHEREAS every by-law
of the Township of Goulbourn is deemed to be a by-law of the City of Ottawa
pursuant to Section 5(6) of the said City of Ottawa Act, 1999;
AND WHEREAS an
engineer was appointed by the City of Ottawa pursuant to section 78(1) of the Drainage
Act, and a report has been procured, made by Robinson Consultants Inc., and
the report is on file with the City clerk;
AND WHEREAS the Van
Gaal Municipal Drain, after it is modified pursuant to this by-law will drain
the following roads and lands:
City of Ottawa, formerly the geographic Township of
Goulbourn, more specifically:
Lots 17, 18, 19, 20, 21, 22, 23 Concession IV;
Lots 15, 16, 17, 18, 19, 20, 21, 22, 23, 24
Concession V;
AND WHEREAS the
entire costs of the required drainage work shall be borne by the owners of
“Block No. 1” lands as described in Schedule “A” of the Robinson Consultants
Inc. Report dated November 2002;
AND WHEREAS the
owner of “Block No. 1” lands as described in Schedule “A” of the Robinson
Consultants Inc. Report dated November 2002, as of the date of this Bylaw is
Guycoki (Eastern) Limited;
AND WHEREAS Council
of the City of Ottawa is of the opinion that the drainage of the area is
desirable;
AND WHEREAS Council
of the City of Ottawa considers it desirable to give this by-law 1st
and 2nd Reading on June 25, 2003 so that it is provisionally adopted
pursuant to section 45 of the Drainage Act,
THEREFORE the Council of the
City of Ottawa enacts as follows:
1. The report dated
November 2002, filed with the City clerk, is hereby adopted and the drainage
works as therein indicated and set forth is hereby authorized and shall be
completed in accordance therewith.
2. Guycoki (Eastern)
Limited shall pay the entire cost of the drainage work, as set out in the
report dated November 2002 referred to in Section 1.
3. This by-law comes
into force on the passing thereof and may be cited as the “Van Gaal Municipal
Drain By-law, 2003”.
ENACTED AND PASSED
THIS day of , 2003
CITY CLERK MAYOR
Attachment C
Notices of Appeal
None received as of 21 July
2003.
VAN GAAL MUNICIPAL DRAIN
INSTALLATIONS MUNICIPALES DE DRAINAGE VAN GAAL
ACS2003-TUP-UTL-0015
Mr. D. Ryan, Project Manager,
Municipal Drainage, advised that the meeting to consider the Engineer’s Report
was held on 16 June 2003 in accordance with the Drainage Act. Mr. Ryan confirmed that the drainage works
are being paid for by the developer of the Cedarstone Subdivision.
Moved by J. Stavinga
That the Agriculture and Rural Affairs Committee, in its capacity as
the Court of Revision:
1. Approve the Assessments as outlined in the Engineer’s Report, and
2. Recommend Council give third reading
to the Van Gaal Municipal Drain By-law.
CARRIED