6.         Zoning – 20 -  50 Frank Nighbor Place

 

Zonage – 20 - 50, place Frank Nighbor

 

 

Committee Recommendation

 

That Council approve an amendment to the former City of Kanata Zoning By-law 138-93, to rezone 20–50 Frank Nighbor Place from M1C-2(H) and Hazard Zone – H to M1C-2(H)-f and Hazard Zone – H to add a Flood Fringe Zone and to alter the existing Hazard Zone.

 

 

Recommandation du comité

 

Que le Conseil approuve une modification au Règlement municipal sur le zonage 138-93 de l’ancienne Ville de Kanata, afin de faire passer le zonage du 20-50, place Frank Nighbor de M1C-2(H) et Zone à risque – H à M1C-2(H)-f et Zone à risque – H, de manière à ajouter une zone située dans un périmètre d’inondation et à modifier la zone à risque existante.

 

 

 

Documentation

 

1.         Development Services Department General Manager’s report dated 4 July 2002 is immediately attached (ACS-2002-APR-0128).

 

2.         An Extract of Draft Minutes, 25 July 2002, immediately follows the report and includes the voting record.


Report to/Rapport au:

Planning and Development Committee/

Comité de l’urbanisme de l’amenagement

 

and Council/et au Conseil

 

4 July 2002/le 4 juillet 2002

 

Submitted by/Soumis par:  Ned Lathrop, General Manager/Directeur général

Development Services Department / Services d’aménagement

 

Contact/Personne-ressource:  Grant Lindsay, Manager, Development Approvals/ Gestionnaire, Approbation des demandes d’aménagement

580-2424, ext 13242, Grant.Lindsay@ottawa.ca

 

 

 

 

Ref N°:   ACS2002-DEV-APR-0128

 

 

SUBJECT:     ZONING – 20-50 FRANK NIGHBOR PLACE

 

OBJET:          ZONAGE – 20-50, PLACE FRANK NIGHBOR

 

 

REPORT RECOMMENDATION

 

That the Planning and Development Committee recommend Council approve an amendment to the former City of Kanata Zoning By-law 138-93, to rezone 20–50 Frank Nighbor Place from M1C-2(H) and Hazard Zone – H to M1C-2(H)-f and Hazard Zone – H to add a Flood Fringe Zone and to alter the existing Hazard Zone.

 

RECOMMANDATION DU RAPPORT

 

Que le Comité de l’urbanisme et de l’aménagement recommande au Conseil d’approuver une modification au Règlement municipal sur le zonage 138-93 de l’ancienne Ville de Kanata, afin de faire passer le zonage du 20-50, place Frank Nighbor de M1C-2(H) et Zone à risque – H à M1C-2(H)-f et Zone à risque – H, de manière à ajouter une zone située dans un périmètre d’inondation et à modifier la zone à risque existante.

 

BACKGROUND

 

An application for a zoning by-law amendment was received by the City of Ottawa for 20-50 Frank Nighbor Place in June 2001.  The application proposed modifying the extent of the existing hazard land by applying a two-zone approach (incorporating a floodway and a flood fringe) that would permit development to encroach into floodplain of the Carp River as established by the original Zoning By-law.

 

During the design of both the Corel Centre lands and the Terry Fox Business Park, it was discovered that the elevations around the Carp River are lower than what is shown on the flood plain mapping.  As a result, an analysis of the Carp River was undertaken, resulting in a relocated boundary for the extent of the development and filling for both the Corel Centre lands and the Terry Fox Business Park.

 

Staff reviewed the application and determined that it was premature for the following reasons:

 

1.                  Further encroachment into the floodplain could jeopardize the findings and recommendations of the Subwatershed study as it pertains to the Carp River corridor;

2.                  The two-zone approach should be conducted by the City within the context of the subwatershed study for the entire reach of the river under urban pressure (Richardson Side Road to Hazeldean Road).

 

The Mississippi Valley Conservation Authority endorsed staff’s position.  In addition, the MVC requested that the City be the proponent of the analysis and zoning amendment, if supported, to ensure a complete and comprehensive approach was used.

 

The applicant agreed to a three-month delay in order to allow the City to conduct the required analysis through the Carp River Watershed/Subwatershed Study.

 

DISCUSSION

 

The Official Plan for the former City of Kanata sets out policies regarding the implementation of a two-zone flood plain.  It is recognized that within in some areas, the flood plain may be suitable for a two-zone approach.  This would result in a floodway, which is defined as the area within a flood plain where depths and velocities of flood waters make development unsafe and the flood fringe, which is defined as the area within a flood plain where depths and velocities of flood waters can be safely overcome and development may occur, subject to other policies in the plan.

 

The Official Plan requires that a site specific Zoning By-law amendment is required where there has been an interest in creating a two-zone flood plain and where the approach is deemed acceptable to the City and the Conservation Authority.  The site-specific zoning by-law amendment shall only be passed if:

a)      sufficient information is provided to demonstrate that the proposed development and its occupants will be protected from the effects of a 100 year flood;

b)      the potential upstream and downstream impacts of the proposal will not significantly alter the hydrology or hydraulics of the flood plain;

c)      the underlying designation on Schedule “A” or “B” permits the proposed development;

d)      vehicles and people have a safe way of entering and exiting the site during times of flooding.

 

The current zoning for the subject lands east of the Carp River is shown on the Location Plan (Document No. 1).  The two-zone flood plain will impact the Light Industrial, Mixed Exception Holding Zone {M1C-2(H)} and the Hazard Zone (H).  The creation of the two zone flood plain will result in an increase in the size Hazard Zone, which is reflected on the proposed Zoning Schedule "A"(Document 3).  The Hazard Zone will be comprised of the floodway component of the two zone floodplain.  The portion of the flood plain to be affected by this change is shown on the Flood Plain map (Document 2).

 

The holding zone associated with the Light Industrial Mixed area shall only be lifted upon receipt by the City of the following documentation: a traffic study; a market study; a complete site plan application and any other information required by the City.  This zone permits industrial uses, business office and big box retail outlets.

 

ANALYSIS

 

Carp River Corridor

 

The most degraded section of the Carp River is south of Richardson Side Road to its terminus at the Glen Cairn stormwater facility.  This section of the river is characterized as degraded warm water fisheries.  Channelization of the river, past (agriculture and urbanization) and present land use activities have caused excessive sediment build-up along the bottom of the channel.  Accumulated sediment contributes to degraded water quality and degraded fish habitat.  An ultimate stable channel form must be achieved under existing and future land use scenarios.

 

Based on the findings of the Carp River Subwatershed Study, the most feasible solution appears to be the establishment of a riverine wetland environment along most of the channel’s length.  A corridor width of 100 metres is recommended to accommodate the riverine wetland, a low flow channel, recreational pathways, and appropriate buffer zones.

 

In terms of 20 and 50 Frank Nighbor Place, a corridor width of approximately 88-100 metres is achievable.  Development (Corel Centre) exists along the western portion of this corridor that only provides a 30-metre setback from the river rather than the desired 50 metres.

 

Zoning By-law

 

A comprehensive analysis of the Carp River system and the potential for a two zone for the reach from Richardson Side Road to the Glen Cairn Detention Pond has been conducted.  The findings indicate that a two-zone approach can be applied to the subject lands.  As a result, the City is now the proponent of this application, with the support of the property owners affected.  Application of the two-zone approach along this reach of the Carp River will be done in phases, with the area shown on the Location Map (Document 1) being the first to be implemented.  The remaining development parcels along this reach of the River will be pursued through a separate process, as part of the Kanata West Concept Plan and the Carp River Watershed/Subwatershed Study.

 

The zoning by-law amendment for 20-50 Frank Nighbor Place will contain the following provisions, which will define the two-zone flood plain and provide the framework to permit the development within the flood fringe:

 

·        Where a zone symbol is followed by a dash and an “f” (for example M1C-f), this denotes a special zone.  The permitted uses and the zone provisions for the flood fringe zone shall be according to the zone represented by the zone symbol as well as the following general provisions:

 

(a)                All permitted uses shall be flood proofed in accordance with the following provisions:

(i)                  any building and related major building services such as mechanical or electrical services, shall be located at least 0.3 metres above the regulatory flood level.

(ii)        all non-residential uses shall be flood proofed to the regulatory flood level.

 

(b)               All alterations or additions to existing non-conforming buildings or structures shall be flood proofed in accordance with the following provisions:

(i)                  Alterations or additions which expand the existing building or structure shall be protected to 0.3 metres above the regulatory flood level.

 

In addition to the above-mentioned provisions, the five definitions listed below will be added to Zoning By-law 138-93:

 

“Flood fringe” means the outer portion of the flood plain between the floodway and the limit of the regulatory flood.  Flood depths and velocities are generally less severe in the flood fringe than those experienced in the floodway.  The flood fringe is the area where development and site alteration may be permitted.

 

“Flood plain” means the area, usually low lands, adjoining a watercourse which has been or may be covered by floodwater.

 

“Floodway” means the channel of a watercourse and the inner portion of the flood plain where flood depths and velocities are generally higher than those experienced in the flood fringe.  The floodway represents that area required for the safe passage of flood flow and/or that area where flood depths and/or velocities are considered to be such that they pose a potential threat to life and/or property damage.

 

“Two-Zone Concept” means the approach whereby certain areas of the flood plain are considered to be less hazardous than others such that development potentially could safely occur.  The flood fringe defines that portion of the flood plain where development may be permitted subject to the appropriate flood proofing.  The floodway defines that portion of the flood plain wherein development is prohibited or restricted.

 

“Flood Proofed” means those established technical measures for buildings, structures or properties prone to flooding which are implemented to reduce or eliminate flood damage.  Flood proofed non-residential uses and alterations to existing non-conforming uses my incorporate wet passive measures.

 

The addition of the two-zone flood plain, whereby part of each affected property will fall within the flood fringe, will not impact on the permitted uses or the development provisions for the MIC zone.  Any development that will encroach into the flood fringe of these sites will require flood proofing and approvals from Mississippi Valley Conservation for fill permits prior to any approvals being granted by the City.  The onus is therefore on the landowners to ensure that all requirements from Mississippi Valley Conservation are met or development may not proceed or may be delayed. 

 

The amendment to Zoning By-law 138-93 to incorporate the two-zone flood plain along the Carp River will include the revised Hazard and the revised floodway, as indicated on the proposed flood plain mapping and zoning schedule (Documents 2 and 3).

 

ENVIRONMENTAL IMPLICATIONS

 

The zoning amendment respects the recommendations forthcoming from the Carp River Watershed/Subwatershed Study.  The hazard area was defined based on both technical (two zone analysis) and environmental considerations.  The ecological attributes of the Carp River corridor are preserved within the dedicated hazard area.  The protection of the Carp Corridor will allow for the future restoration works to occur that will enhance the environmental features and functions of the river corridor.

 

CONSULTATION

 

The affected landowners have been involved with the process of implementing the two-zone flood plain along this portion of the Carp River.

 

Mississippi Valley Conservation has been involved with the preparation of this report and has reviewed the two-zone analysis.

 

The Ward Councillor is aware of the application.

 

FINANCIAL IMPLICATIONS

 

N/A

 

APPLICATION PROCESS TIMELINE STATUS

 

The application was not processed within the timelines established by the Department of Development Services.  The application was deemed premature by staff as it was submitted during the preliminary stages of the Carp River Subwatershed Study that is being undertaken by the City of Ottawa.  This application was put on hold until such time as the study was well underway and some conclusions could be determined with regards to allowing a two-zone flood plain to be permitted along the reach of the Carp River from Richardson Side Road to the Glen Cairn detention pond.

 

ATTACHMENTS

 

Document 1 – Location Map

Document 2 – Flood Fringe/Floodway Map

Document 3 – Proposed Schedule A for Zoning By-law Amendment

 

DISPOSITION

 

Development Services and Legal Services to co-ordinate the finalization of the Zoning By-law for adoption by Council and execution by the Mayor and Clerk.


Location Map                                                                                                                    Document 1

 


Flood Fringe/Floodway Map                                                                                              Document 2

 


Proposed Schedule A for Zoning By-law Amendment                                                         Document 3

 


ZONING – 20 AND 50 FRANK NIGHBOR PLACE

ZONAGE – 20-50, PLACE FRANK NIGHBOR

ACS-2002-APR-0128

 

Chair Hunter began by reading a statement required under the Planning Act, which advised that anyone who intended to appeal this proposed Zoning By-law Amendment to the Ontario Municipal Board (OMB), must either voice their objections at the public meeting, or submit their comments in writing prior to the amendment being adopted by City Council.  Failure to do so could result in refusal/dismissal of the appeal by the OMB.

 

Craig Winters, Novatech Engineering for The Regional Group, was present in support of the recommendation contained in departmental report dated 4 July 2002.

 

Moved by Councillor J. Harder:

 

That the Planning and Development Committee recommend Council approve an amendment to the former City of Kanata Zoning By-law 138-93, to rezone 20–50 Frank Nighbor Place from M1C-2(H) and Hazard Zone – H to M1C-2(H)-f and Hazard Zone – H to add a Flood Fringe Zone and to alter the existing Hazard Zone.

 

CARRIED, with Councillors Munter and Stavinga dissenting.