MEMO /
NOTE DE SERVICE
|
|
To /
Destinataire
|
OPL Board Facilities
Planning Committee |
|
cc: |
|
|
From / Expéditeur |
Richard Stark, Manager, Library Facilities Planning
and Development |
|
Subject / Objet
|
West District Library
Project Schedule Briefing Note |
Date: October 24, 2012 |
Background
$10,000,000
was approved in the growth portion of the 2009 capital budget to build the West
District Library facility. On November 15, 2010 the OPL Board approved the
selection of the existing Beaverbrook Branch site as the preferred location for
the new West District Library. On
October 17, 2011 the OPL Board awarded the professional architectural services
contract to Moriyama and Teshima Architects for this building project.
The site plan approval process began late in June 2012
and proceeded slower than anticipated. The
storm water management requirements have been quite challenging on this site
due to particularly high rock elevation in some areas and the necessity to
coordinate these needs with existing site services. Various options were
explored to store the water on site. This resulted in considerable dialogue
with City engineers to find a suitable and cost effective alternative. Changes to the site plan and original parking
lot layout preserves the treed lot area on the Mlacak site. The resulting
underground water retention system will be kept a safe distance from the
forested area to protect the trees.
Resolving these requirements resulted in the
parking lot construction being delayed until next spring with the full project going
to a single tender at that time. Initial
construction will be staged so that the parking lot will be completed prior to
the general contractor beginning significant work on the building
construction. This will minimize the
negative impact on available parking to the Mlacak Centre.
The estimated date for completion of this new
district branch is now Fall 2014. In response to
concerns raised at the October 15, 2012 OPL Board meeting, the proposed project
schedule has been revisited and updated.
Analysis
and Investigation
Philip
Piazza, Senior Project Manager, Architecture, from City Infrastructure Services
who has been working on the West District Library Project reviewed the proposed
schedule with Moriyama and Teshima to see if opportunities existed to improve
the proposed timelines. He also compared
this proposed schedule against the Greenboro District Library project which was
a new library construction added on to a community centre. The scale and scope of the Greenboro project
is similar to the West District.
Greenboro used many similar construction techniques as
those being employed in the West District project. It too was an addition to a community centre
and it was of similar size and had a nearly identical construction budget. Greenboro
was initially scheduled to take 15 months to build but ended up taking 18
months to complete. West District has two
additional factors which add to the project’s complexity:
1.
Requirement
to complete a new parking lot prior to
initiating the major part of the construction
2.
Potential
unknowns from major renovation and/or demolition of the existing Beaverbrook
Branch.
Board approval of the construction tender including
the parking lot is tentatively planned for the beginning of April 2013. Parking
lot construction cannot begin until April 2013 at the earliest, given the high
water table levels on this site. Too
early a start will impact the successful installation of the parking lot since
work would be undertaken on a less-than-firm soil base. This will create risks
and potential additional costs at the end of the project if portions of the
parking lot required remediation. One of the advantages to a spring start is
that the new building will be well under development so that it can be enclosed
before winter sets in Q4 of 2013.
Both
the Senior Project Manager and the Moriyama & Teshima team feel they have
addressed as many issues as possible to keep the schedule as compact and at the
same time as realistic, as possible. The
result is a 16 month construction schedule to the end of substantial completion.
Project Preliminary Schedule
Overview
1.
Design Development - Client/partner meetings
& review......................................... Completed
2.
Contract
Documents & detailed drawings commences..................................... October
11, 2012
3.
Contract Documents – Client review and
submissions .................................................. ongoing
·
Also Includes reviews of
security, furniture, equipment, civic art, signage, etc.
4.
Site Plan Application Approval .................................................................... November
30, 2012
5.
Cost Estimate 60% tender Class B.................................................................. December
6, 2012
6.
Cost Estimate 100% tender Class A .................................................................... January
7, 2012
7.
Building Permit Issued..................................................................................... January
17, 2013
8.
Contract
Documents completion...................................................................... January 23, 2012
9.
Tender and Review commences...................................................................... January
29, 2013
10.
Alternate
Service Delivery Plan completion by OPL Staff................................... January
31, 2013
11.
OPL Board approval of Beaverbrook closure................................................... February
11, 2013
12.
Beaverbrook
Depot opens ................................................................................ March
18, 2013
13.
Beaverbrook Branch closure and move out
commences..................................... March
19, 2013
14.
Tender closing and recommended contract award............................................. March
28, 2013
15.
OPL
Board approval of WD contract award (Special Meeting).................................. April 3, 2013
16.
Ground Breaking Ceremony................................................................................... April
5, 2013
17.
Construction commences (parking & building) 16 months duration.......................... April 8, 2013
18.
OPL Board approval of RFID equipment for West District................................ February
10, 2014
19.
Substantial Completion of building construction.................................................. August 1,
2014
20.
Deficiency Period and Final occupancy.............................................................. August
30, 2014
21.
OPL move in / furniture & equipment
installation commences.....................
September 2, 2014
22.
Open to public ............................................................................................... October
15, 2014
Philip Piazza will be in attendance at the Facilities Planning
Committee meeting to respond to any questions on the preliminary project
schedule.