Sous-comité de la vérification
and / et
Finance
and Economic Development Committee
Comité des
finances et du développement économique
and Council / et au Conseil
19 May
2011 / le 19 mai 2011
Submitted by/Soumis par: Kent
Kirkpatrick, City Manager / Directeur municipal
Contact Person/Personne ressource : Steve Box, Manager, Policy
Coordination and Outreach/ Gestionnaire, Direction de la coordination des
politiques et du rayonnement
(613)
580-2424 x 24200, Steve.Box@ottawa.ca
Ref N°: ACS2011-CMR-OCM-0002 |
SUBJECT:
|
Quality Assessment Review - Office of the
auditor general (OAG) |
|
|
OBJET:
|
examen de l’évaluation de la qualité – Bureau du vérificateur général
(BVG) |
That the Audit Sub-Committee recommend that
the Finance and Economic Development Committee recommend Council approve the contract
amendments with Pricewaterhouse Coopers LLP to include a Quality Assessment Review of
the Office of the Auditor General as outlined in Document 1; and that
Pricewaterhouse Coopers LLP report back to the Audit Sub-Committee on the
review’s findings and recommendations for implementing the Institute of
Internal Auditors (IIA) standards.
Que le
Sous-comité de la vérification recommande au Comité des finances et du
développement économique de recommander à son tour au Conseil d’approuver des
modifications au contrat passé avec Privewaterhouse Coopers LLP, afin d’y
inclure un examen d’évaluation de la qualité du Bureau du vérificateur général
conforme à la description donnée au document 1, et que PricewaterhouseCoopers
LLP rende compte au Sous-comité de la vérification des conclusions et
recommandations de l’examen en vue de l’application des normes de l’Institut
des vérificateurs internes.
BACKGROUND
On 22 March 2011, the City Manager provided a
verbal update to the Audit Sub-Committee with respect to the status of the external
Quality Assessment Review of the Office of the Auditor General (OAG), further
to Council direction received on December 8, 2010. The City Manager received direction from the Audit
Sub-Committee (ASC) to recommend to the Finance and Economic Development
Committee (FEDCO) that the existing contract with Pricewaterhouse Coopers LLP
(PWC) be amended to conduct the review of the Auditor General’s Office.
The subsequent report to FEDCO on 5 April
2011 (ASC2011-CMR-OCM-0001) relayed this direction and specified that upon
Committee and Council approval, PWC would be asked to prepare a draft Terms of
Reference and criteria for ASC review and approval. In addition, to ensure impartiality and
independent analysis and reporting, PWC would be required to present its
findings and any recommendations arising from the review directly to the ASC as
its client.
On 13 April 2011, City Council approved the
ASC direction to the City Manager to amend the existing contract with PWC to
include a Quality Assessment Review of the Office of the Auditor General. This report provides a proposed Statement of
Work (Document 1) for committee approval.
The OAG currently operates in accordance with
the 2004 Council approved by-laws governing the Office. As such, it is most appropriate at this time
to undertake a review of the audit function against the existing framework. It
is further felt that implementing the Institute of Internal Auditors (IIA)
standards is appropriate at this time in the evolution of the audit
function.
After discussion, the Auditor General and
City Manager concurred that the most cost-effective manner in which to proceed
in order to achieve a Quality Assessment Review of the audit function was to
amend the existing contract the Office of the Auditor General (OAG) currently
has with Pricewaterhouse Coopers LLP (PWC).
Upon receiving direction from the City
Manager that City Council endorsed the abovementioned approach,
PWC prepared a draft Statement of Work for Audit Sub-Committee (ASC) review and
approval (Document 1).
The Statement of Work proposes that PWC
undertake an independent quality assessment review of the OAG and deliver
findings and recommendations to the ASC with regard to the following three
objectives:
Further to the timelines indicated in the
Statement of Work, it is expected that PWC will present its findings and
recommendations to the ASC in the fall of 2011.
There are no rural implications associated with this report.
As this is considered an internal administrative matter, no public
consultation was undertaken.
N/A
There are no legal/risk management impediments to implementing any of
the recommendations arising from this report.
The measures outlined in the report are in
keeping with the directions contained in the 2010-2014 Council Governance
Review report (ACS2011-CMR-CCB-0106) and strengthening the City’s overall
accountability framework.
N/A
Funds to conduct the Quality Assessment
Review outlined in this report are accommodated in the 2011 operating budget of
the Office of the Auditor General.
Document 1 - Pricewaterhouse
Coopers LLP - External Quality Assurance Review of the Office of the Auditor
General: Proposed Statement of Work for the Audit Sub-Committee (issued separately to all Members of Council
and held on file with the City Clerk)
Upon approval of the recommendation of this
report by Council, Pricewaterhouse Coopers LLP will proceed under the terms
outlined in the attached document.