How Ottawa's airport upgrade got off the ground

Undeterred by problems in the aviation industry, the new terminal is opening early -- and under budget. Kristin Goff reports.

 

Kristin Goff

 

The Ottawa Citizen


Saturday, October 04, 2003

CREDIT: Bruno Schlumberger, The Ottawa Citizen

 

Richard Brisbin is the architect of the Ottawa's new airport terminal. The new three-storey terminal building is double the size of the old one, with 14 new airplane gates and more for space for passengers.

 

 

After manoeuvring through the most turbulent period in modern airline history, Ottawa's airport expansion project is coming in for a smooth landing -- six months early and likely under its $310-million budget.

The expansion at the Ottawa Macdonald-Cartier International Airport opens to the public Oct. 12.

Says the airport authority's chief executive, Paul Benoit: "Users are going to find this the most phenomenal, fantastic airport. And that's a promise."

Among its new facilities are:

- A three-storey terminal building, double the size of the old one, with 14 new airplane gates, more space for passengers, and more restaurants and shops, many of them locally owned.

- A parking garage with 1,700 vehicle spaces in addition to 800 ground level spots outside. Outside parking at the old terminal will become long-term parking.

- A host of other upgrades, including a new fire station, new de-icing facilities and wider aprons to ease bottlenecks for arriving and departing airplanes.

Ironically, the new airport facilities are opening in a radically different economic environment than when the plans were finalized in 2000.

At the time, the 40-year-old Ottawa airport, which had its most recent upgrades almost 20 years ago, was under pressure from a booming technology industry, a healthy leisure market and growth in passenger traffic that had reached double-digit levels.

Four years later, problems in the technology industry, the shocks of the Sept. 11, 2001 terrorist attacks, a drop in business and leisure travel, and a life-and-death struggle for some airlines have taken a toll. This year there will be fewer passengers traveling through the airport than the 3.4 million in 2000. There are also fewer flights and no direct links between Ottawa and U.S. technology centres such as San Jose, California, and Raleigh-Durham, North Carolina.

Those flights were cancelled early in 2001 as companies such as Nortel began cutting their travel budgets. Air Canada has had to do even more paring of flights, as its financial troubles deepened.

Still, Mr. Benoit says he expects this year to show an increase of two to three per cent in passenger traffic from last year's 3.2 million travellers. Smaller carriers such as Westjet, Canjet and Jetsgo have recently added several dozen flights to their schedules. That increase in scheduled flights, in turn, caused the airport authority to make some last-minute adjustments to the new airport project as recently as August, he said.

At one point, during the worst of the airline industry problems, the airport authority had considered tearing the old terminal down, he said.

But just two months ago, officials reverted to their original plan, which was to keep several gates in the old terminal for departures during peak travel times. A link from the new building provides access to four gates in the old terminal and more could be used, if needed.

For now, flexibility is the watchword. Based on current projections, the new facility might serve travellers for a decade or more before a planned second and third phase of expansion are begun, Mr. Benoit said during an interview.

But much of the timing for that is beyond the airport's control.

"An airport, itself, does not generate new traffic. Nobody flies to Ottawa because there is a new airport," says Mr. Benoit. But the new facility can accommodate growth when conditions are right.

"Ottawa-Gatineau will be positioned now, for the next 10 to 20 years, to respond to the needs of the community. You won't have to go through Montreal or Toronto, because if there is demand for a flight here, it will be served. The airlines will be able to come in."

Given the wild fluctuations in the industry during the time the project was underway, it's all the more remarkable that it has been finished six months earlier than planned and probably under budget.

The project is being largely financed through a $15 per passenger airport improvement fee, which is already in place. Mr. Benoit takes pains to point out that the private airport authority, which has a long term lease to run the federally owned airport, didn't get "one cent from government."

Nearly 85 per cent of work on the project was done by local companies from Ottawa-Gatineau. Being able to finish months early saved money as did keeping an eagle eye on costs, he said.

Mr. Benoit thinks the project will come in under $310 million but even if it doesn't, he says the airport authority still got more bang for its buck than planned because it was able to include pre-building of some infrastructure for future expansions into the current project.

There is relatively little talk of what economic spinoffs the new airport terminal will bring immediately, at least in specific dollar terms.

"I don't know if that is measurable," says Jeffrey Dale, president of the Ottawa Centre for Research and Innovation. "But it is certainly a huge, huge benefit to have that kind of facility here."

Part of that, he says, is in the image the new airport will project to visiting business, government and leisure travellers, who get their first impression of the region as they step off their planes.

Because of that, the airport authority has taken steps to make sure everything from the region's heritage to its high tech industry are show-cased at the terminal, says Mr. Dale, who also sits on the Airport Authority board.

Jacques Burelle, president of the Ottawa Tourism and Convention Authority, agrees.

"I think it is going to be another post card for us, in terms of (showing) the quality of life that we have here," Mr. Burelle says.

© Copyright 2003 The Ottawa Citizen