10 June 03 File No G03-99-ROADDate

 

 

City of Ottawa

110 Laurier Street West, 5th Floor

Ottawa, Ontario

K1P 1J1

 

Attention:  Donna Mulvihill, Accessability Committee Co-ordinator

 

Re: Harmonization and Integration of City By-Laws

Road Activity By-law

 

The City of Ottawa is continuing with the process of harmonizing and integrating the various by-laws from the former municipalities. A public consultation notification was forwarded to stakeholders in April, at which time we had requested initial input into the review process. We are now initiating the second phase of the consultation process as defined in our earlier correspondence. Enclosed is a copy of the draft Road Activity By-law (former Road Cut By-law), this document has been formatted to allow comments to be entered or issues identified opposite particular clauses.

The Road Activity By-law regulates the entry on, the cutting of,  and the reinstatement of the road allowance, not only by the City, but also by all utilities, developers and their contractors. This by-law protects the City’s infrastructure and facilitates the safe and effective movement of traffic through construction or maintenance activity zones.

 

This By-law includes provisions related to permit applications notification related to activities, insurance and securities, reinstatement and warranty, and fees and charges. Also noted are peak hour restrictions and the conditions under which roads may be closed.

 

Changes from the current By-law include, but are not limited to:

·        the extension of notification requirements and peak hour restrictions to all work activities on Schedule B roads. For none excavation activities the requirement is for notification only, no permits will be required;

·        the move to reference City Standards, rather than include the Standards in the By-law;

·        and under consideration for recommendation but not included in the attached draft is the extension of the Pavement Degradation Fees to all City roads. The cost impact of Utility cuts on local roads is scheduled to be completed by the end of June, at which time this matter will be further considered.

 

If you have any comments or would like to provide input to the development of the new Road Activity By-Law, would you please forward your comments to Nancy Jean-Louis at 580-2424, ext 13637 or email at Nancy.Jean-Louis@ottawa.ca., by Monday, 23rd June 2003.  For specific comments on this project or content of the By-law, please contact Trevor Harris at 580-2424, ext 13764.

 

Sincerely yours,

 

 

Original Signed By Wade Clouthier

 

 

R. G. Hewitt, Director

Infrastructure Services Branch

Department of Transportation, Utilities and Public Works

 

RGH:njl