CONFIRMATION OF MINUTES

That the Transportation Committee confirm the Minutes of the Meeting of DAY MONTH YEAR.

INQUIRIES

PAGE

PUBLIC HEARINGS

PRESENTATIONS

REGULAR ITEMS

1. ISLAND PARK DRIVE, KIRKWOOD, CHURCHILL AREA TRAFFIC CALMING PILOT STUDY - PUBLIC HEARING

- Co-ordinator, Transportation Committee report dated 25 August 1998 01

That Transportation Committee recommend Council approve the construction of traffic calming measures for Kirkwood Avenue, Churchill Avenue, Scott Street and Merivale Road identified in Annex A.

2. LYON STREET TRAFFIC CALMING PILOT STUDY

- Co-ordinator, Transportation Committee report dated 25 August 1998 10

AS AMENDED That Transportation Committee recommend Council approve the construction of calming measures for Lyon Street, identified in Annex A, including the addition of a speed hump between Somerset Street and Maclaren Street as part of the Lyon Street Traffic Calming Pilot Study.

3. TRAFFIC CONTROL SIGNALS AND ROADWAY MODIFICATIONS AT ALBION ROAD AND RIDEAU ROAD AND AT TRIM ROAD AND WATTERS ROAD - PUBLIC HEARING

- Co-ordinator, Transportation Committee report dated 25 August 1998 17

 

That the Transportation Committee recommend Council approve:

 

1.the installation of a traffic control signal at the following two intersections in conjunction with the proposed roadway modifications for each intersection;

a.Albion Road (Regional Road 25) and Rideau Road;

and;

b.Trim Road (Regional Road 57) and Watters Road;

2.the roadway modifications for the above two intersections as shown in Annex F (pages 2-4) and Annex G (pages 2-3).

 

 

4. MARCH ROAD AT THE ACCESS TO THE GATEWAY MALL - PROPOSED NORTHBOUND LEFT-TURN LANE AND ACCESS TO 365 MARCH ROAD - PUBLIC HEARING

- Co-ordinator, Transportation Committee report dated 25 August 1998 50

 

That Transportation Committee recommend Council approve the modifications to the traffic control signals at March Road and Gateway Mall and the construction of associated changes to the roadway along March Road as described in the report and illustrated in Annex C, subject to the owner of 151516 Canada Incorporated:

 

a) funding the total cost of the traffic signal modifications and the proposed road works;

b) executing a legal agreement with respect to the above.

 

5. PROPOSED INTERSECTION MODIFICATIONS TO KIRKWOOD AVENUE AND HAMPTON PARK PLAZA/SWITZER AVENUE - HAMPTON PARK PLAZA REDEVELOPMENT - PUBLIC HEARING

- Co-ordinator, Transportation Committee report dated 25 August 1998 59

 

That the Transportation Committee recommend Council approve the modifications to the traffic control signals at Kirkwood Avenue and Hampton Park Plaza/Switzer Avenue and the construction of associated changes to the roadway along Kirkwood Avenue as described in the report and illustrated in Annex C, subject to the owners, London Life Insurance Company and Devan Properties Limited:

 

a) funding the total cost of the traffic signal modifications and the proposed road works;

b) executing a legal agreement with respect to the above.

 

6. FALLOWFIELD ROAD FROM WOODROFFE AVENUE TO A POINT 155 M WEST OF WOODROFFE AVENUE - PROPOSED MEDIAN - PUBLIC HEARING

- Co-ordinator, Transportation Committee report dated 25 August 1998 68

 

7. LIGHT RAIL PILOT PROJECT: RECOMMENDED SERVICE CONCEPT AND COST ANALYSIS

- Planning and Development Approvals Commissioner report dated 18 August 1998 88

 

That the Transportation Committee recommend Council approve:

 

1. The selection of the Canadian Pacific Railway Ellwood Subdivision, from the West Transitway at Bayview to the Southeast Transitway at Greenboro as shown in Annex C, as the preferred route for a light rail pilot project using diesel-powered low-floor light rail vehicles;

2. Timely examination of possible light rail extensions that are not identified in the Official Plan and Transportation Master Plan (e.g., to downtown Hull, downtown Ottawa, Ottawa Macdonald-Cartier International Airport and Barrhaven) so that they may be implemented, if and when they are warranted, subject to availability of funds as well as Official Plan amendment and Environmental Assessment approvals;

3. The negotiation with Canadian Pacific Railway and/or appropriate partners, for approval by Council, of a public-private partnership agreement for light rail pilot project implementation and operation, based on the principles contained in Annex D, with capital costs not exceeding a present value of $16 million, and with annual operating costs not exceeding system-wide average operating costs for equivalent ridership levels;

4. The Light Rail Pilot Project Environmental Assessment Terms of Reference, issued separately as Annex F and as modified by a supplemental Annex G (to be issued separately if required), to be submitted to the Ontario Ministry of the Environment for approval.

 

8. RICHMOND ROAD (REGIONAL ROAD 36) AND STAFFORD CENTRE ACCESS - PROPOSED CONNECTION TO NORTHSIDE ROAD

- Director Mobility Services and Corporate Fleet Services Environment and Transportation Department report dated 12 August 1998 119

 

That the Transportation Committee recommend Council approve:

 

1. The modification to the traffic control signals at Richmond Road and Stafford Centre Shopping Mall and the construction of associated changes on Richmond Road to provide a new road link to Northside Road as described in the report and illustrated in Annex B, subject to the City of Nepean funding the total cost of the traffic signal modifications and the proposed road works;

2. The initiation of the public hearing process as required by Sections 297 and 300 of the Ontario Municipal Act.

 

9. COMMUNITY FACILITY/BAYSHORE TRANSIT STATION INQUIRY FROM COUNCILLOR BYRNE - 17 JUNE 1998

- Director Engineering Division Environment and Transportation Department report dated 19 August 1998 127

That the Transportation Committee receive this report for information.

10. TRANSPORTATION COMMITTEE MEETING - 6 MAY 98 - MOTION TC-1-98 - NON-POLICE TRAFFIC ENFORCEMENT

- Regional Solicitor report dated 21 July 1998 129

That Transportation Committee receive this report for information.

11. RESPONSE TO OUTSTANDING INQUIRY TC-7-98 TRANSPORTATION COMMITTEE MEETING - 17 JUNE 1998 COMPLETING THE WEST TRANSITWAY - PHASE 1B

- Director Engineering Division Environment and Transportation Department report dated 19 August 1998 132

That Transportation Committee receive this report for information.

 

INFORMATION PREVIOUSLY DISTRIBUTED

OTHER BUSINESS

ADJOURNMENT