Report to/Rapport au :
and Council / et au Conseil
25 February 2009 / le 25
février 2009
Steve Kanellakos, Deputy City Manager /
Directeur municipal adjoint
City Operations / Opérations
municipales
Contact Person/Personne ressource:
John Manconi, General Manager /directeur
générale, Public Works/Travaux Publics
(613)
580-2424, extension/poste 21110, John.Manconi@ottawa.ca
SUBJECT: |
CONROY Public Works Facility |
|
|
OBJET
: |
REPORT
RECOMMENDATIONS
That the Transportation
Committee recommends that Council approve:
1.
The increase of the capital authority for Heatherington
Building Replacement (Conroy Development Plan) from $4.64 M to $11.64 M to
allow for the construction of a Public Works facility at 3100 Conroy Road that
will replace the existing facility at 1770 Heatherington Road; and,
2.
The transfer of $7.0 M of tax supported debenture
financing from Capital Project Maple Grove Facility Works Operation to Capital
Project Heatherington Building Replacement (Conroy Development Plan).
RECOMMENDATIONS DU RAPPORT
Que le
Comité des transports recommandent au Conseil d’approuver:
1. L’augmentation de l’autorisation de
dépenses d’immobilisations pour le remplacement de l’édifice Heatherington
(plan d’aménagement de Conroy) de 4,64 M$ à 11,64 M$ afin de permettre
l’aménagement d’une installation pour Travaux publics au 3100, chemin Conroy
qui remplacera l’installation actuelle située au 1770, chemin Heatherington;
2. Le transfert de 7 M$ comme financement
sous forme de débentures soutenu par les taxes à partir du projet
d’immobilisations de l’installation de dépôt Maple Grove vers le projet
d’immobilisation du remplacement de l’édifice Heatherington (plan d’aménagement
de Conroy).
BACKGROUND
The Surface Operations
Branch has been actively reviewing operational practices and service delivery
models for the past several years.
Facility rationalization and consolidation has been an intricate
component of the Branch review. On 23 May 2007, Council approved a report
(ACS2007-PWS-SOP-0003) seeking approval of a long-range plan for Facility and
Property Rationalization & Consolidation.
Contained in the report was an outline for a project entitled
Heatherington Road Replacement. This
project involved the complete replacement of the Public Works facility at 1770
Heatherington Road. The project was originally estimated at $5.5 M, and was
approved in the 2007 Capital Budget with $4.64 M allotted to facilitate the
design and construction of a replacement facility.
Reduction in Capital
envelope, escalation in construction costs, inflation, requirement of site
servicing and amenities and the need to accommodate growth pressures has
impacted the original project estimate.
The revised project estimate to complete the new facility at 3100 Conroy
Road is $11.4 M. Increased authority of
$7.0 M is required to commence with the relocation of the works garage from
1770 Heatherington Road to 3100 Conroy Road.
Surface Operations
has an approved Capital Project (Ref.
No. ACS2007-BTS-RPN-0006) for the reconstruction and consolidation of a
facility located at 1655 Maple Grove Road.
The project authority is $10.8M for design and construction of the new
garage. Construction was expected to
start in 2009.
The 1655 Maple Grove
Road site is located within the boundaries of the Kanata West Development
Plan. Council has imposed a moratorium
on all planned construction within the Kanata West Development lands due to a
revised Ministry of Environment Assessment for review of the Carp River flood
plain. Given the delay of this project and
unknown restrictions that could result from a revised Environmental Assessment,
the Branch is proposing a transfer of $7M from the Maple Grove Project to the
Conroy Road construction plan. The Department will resubmit a budget request in
the 2010 Budget for the construction requirements of the Maple Grove facility.
CONSULTATION
Public consultation was conducted during the Zoning Amendment process required to facilitate construction at the 3100 Conroy Road site. Additional input will be obtained during the Site Plan Approval process for the building design and site layout for the new Works Yard at 3100 Conroy Road.
FINANCIAL IMPLICATIONS
With approval of the recommendation contained
in this report project authority in the amount of $7.0 M will be transferred
from capital project Maple Grove Facility to capital project Heatherington
Building Replacement..
Construction of the Maple Grove Facility will
be delayed until new authority is established. The request will be made in the
Draft 2010 Capital Budget.
LEGAL/RISK MANAGEMENT IMPLICATIONS
There are no legal/risk management impediments
to implementing the recommendations in this report.
Document 1 – Aerial Photograph of 1770 Heatherington
Document 2 - Aerial Photograph of 3100 Conroy Road
Document 3 – Aerial Photograph of 1655 Maple Grove Road
DISPOSITION
Following Council’s approval, Public Works staff will finalize the design and construction project for a Public Works facility at 3100 Conroy Road. Upon completion of the new facility, Public Works staff will disengage from the existing site at 1770 Heatherington and make the property available for disposal and redevelopment.
Public Works staff will review implications of the revised Ministry of Environment Assessment of the Carp River flood plain on the proposed redevelopment of 1655 Maple Grove Road Works Yard. Revised budget estimates will be submitted as part of the 2010 Capital Budget plan.