Report to/Rapport au :

 

Planning and Environment Committee/

Comité de l'urbanisme et de l'environnement

 

and Council / et au Conseil

 

10 June 2009 / le 10 juin 2009

 

Submitted by/Soumis par : Nancy Schepers, Deputy City Manager/

Directrice municipale adjointe,

Infrastructure Services and Community Sustainability/

Services d’infrastructure et Viabilité des collectivités 

 

Contact Person / Personne ressource: Dixon Weir, General Manager / Directeur général
Environmental Services / Services environnementaux

613-580-2424, x22002, Dixon.Weir@ottawa.ca

 

City-Wide / À l’échelle de la Ville

Ref N°: ACS2009-ICS-SWS-0003

 

 

SUBJECT:

Green Bin Program iMPLEMENTATION PLAN

 

 

OBJET :

Plan de mise en OEuvre du programme de Bac vert

 

 

REPORT RECOMMENDATIONS

 

That the Planning and Environment Committee recommend Council:

 

1.                  Receive this report for information; and

2.                  Direct staff to report back in early 2011 with results of the Green Bin Program along with recommendations to optimize the program in preparation for the 2012 collection contract tender.

 

 

RECOMMANDATIONS DU RAPPORT

 

Que le Comité de l'urbanisme et de l'environnement recommande au Conseil :

 

1.                  D’accueillir le présent rapport à titre informatif;

2.                  De demander au personnel de présenter un autre rapport au début de 2011, dans lequel seront présentés les résultats du programme du Bac vert, ainsi que des recommandations visant l’optimisation du programme en prévision des prochains appels d’offres pour les services de collecte en 2012.


EXECUTIVE SUMMARY

 

Assumptions and Analysis:

 

This report outlines the details of the implementation plan for Ottawa’s Green Bin Program. The primary focus of the report is to inform Committee and Council about the implementation schedule and the communication and outreach support to residents. 

 

Implementation of the program is comprised of three primary components:

·         Modification of collection service to include organics;

·         Provision of organics processing; and,

·         New service promotion and customer education.

 

Provision of the organics program will ultimately include all residents. The program will be rolled out in three distinct phases; Phase 1 will include single residential properties and low rise multi-unit residential properties, Phase 2 will include high-rise, multi-unit residential properties and Phase 3 will include the rural properties that were not included in the leaf and yard waste / organics collection in the last contract. Staff will report on implementation details for Phase 2 once the findings of the pilot on organics collection from high-rise buildings is complete. Phase 3 will be included in the level of service report (2011) for the consideration of Council in preparation for the next collection contract (2012).

 

Orgaworld Canada was awarded the contract to build and operate an organics processing facility for the City’s program. The facility is located at Rideau Road and Hawthorne Road and construction began in April of this year. The outside structure for the facility is well underway and the work on the interior is scheduled to commence in June.

 

Effective communication, education and promotion of the Green Bin Program to residents is one of the most important components of a successful organics initiative. Collection and processing are vital, but without an effective communications strategy, residents will not clearly understand how to participate in the program, thereby impacting contamination and diversion levels. 

 

The implementation plan described in this report, combined with effective communications and outreach, will result in a smooth transition to the new collection service and work towards the City’s diversion goals.

 

Financial Implications

 

This report has no financial implications as all costs associated with the Green Bin Program have been identified in previous reports and approved by Council.

 

Legal/Risk Management Implications

 

There are no legal/risk management impediments to receiving the information in this report and directing staff to report back in early 2011.

 


Public Consultation/Input

 

Extensive consultation on the Green Bin Program has been ongoing since 1997. The pilot program Compost Plus has tested the collection of organics in about 5,000 households. Nanos Research conducted a survey in the fall of 2008 on a wide range of solid waste issues and found that the majority of Ottawa residents are aware and supportive of the Green Bin Program. The Executive Summary of the survey findings is included as Document 4.

 

Background and Main Timelines

 

In May 2008, ACS2008-PWS-SWS-0002, Council approved the following level of service for solid waste, including the collection of green bins:

·         Continue with weekly garbage collection and alternate weekly blue box and black box through to 2012 under the existing contracts the City has with its service providers;

·         Bi-weekly organics collection from December to March; and

·         Weekly organics collection from April to November.

 

The collection of the green bin organics is scheduled to commence on January 4, 2010.

 

In March 2008, ACS2008-PWS-SWS-0004 Council awarded an organics processing contract to Orgaworld Canada Ltd.

 

In November 2008, contracts were awarded to Norseman Plastics and Ottawa Mouldcraft for the manufacture of organic collection carts and kitchen containers respectively. In April 2009, Fleishman-Hillard Canada was retained to develop and deliver an education and communications campaign for the implementation of the Green Bin Program.

 

Current Status:

·         Construction on the Orgaworld facility (building shell near completion);

·         Manufacture of approximately 50,000 green bins at a rate of 1,200 per day;

·         Green Bin Champions Pilot launched;

·         The manufacturing mould ready for production of the kitchen container; and,

·         The development of a communications plan.

 

Document 6 attached includes a previously distributed memorandum with respect to the purchaseof green bins.

 

 

RÉSUMÉ

 

Le présent rapport présente les détails du plan de mise en œuvre du programme de Bac vert de la Ville d’Ottawa.  Le rapport vise principalement à informer le Comité et le Conseil du calendrier de mise en œuvre et des moyens de communication et de sensibilisation utilisés à l’égard des résidents. 

 

La mise en œuvre du Programme comprend les trois principaux éléments suivants :

 

·         Modification du service de collecte des déchets afin d’y inclure les déchets organiques;

·         Prestation de services de traitement des déchets organiques;

·         Promotion du nouveau service et sensibilisation de la clientèle.

Les services de collecte des déchets organiques seront éventuellement offerts à tous les résidents.  Le programme sera mis en œuvre en trois phases distinctes. La première phase visera les résidences individuelles et les petits immeubles à logements multiples, la deuxième phase comprendra les tours d’habitation à logements multiples et la troisième phase visera les propriétés rurales qui n’étaient pas inclus dans la collecte des feuilles et résidus de jardinage et des déchets organiques aux termes du dernier contrat. Le personnel présentera un rapport sur la mise en œuvre de la deuxième phase lorsque les conclusions du projet pilote de collecte de déchets organiques pour les tours d’habitation à logements multiples auront été élaborées.  Les résultats de la troisième phase seront inclus dans le rapport sur les niveaux de service (2011) dont le Conseil tiendra compte pour le prochain contrat de service de collecte (2012).

 

La Ville a accordé à l’entreprise Orgaworld Canada le contrat de construire et d’exploiter une installation de traitement des déchets organiques pour le programme de la Ville.  L’installation est située au coin du chemin Rideau et du chemin Hawthorne; les travaux de construction ont commencé en avril 2009.  La construction de la structure externe de l’installation va bon train et les travaux internes devraient commencer en juin.

 

La communication efficace avec les résidents, la sensibilisation de ces derniers et la promotion du programme constituent les éléments les plus importants pour assurer le succès de l’initiative de collecte des déchets organiques.  La collecte et le traitement des déchets sont très importants, mais sans une stratégie de communication efficace, les résidents ne comprendront pas bien comment ils peuvent participer à ce programme, ce qui aura une incidence sur les niveaux de contamination et de réacheminement. 

 

Le plan de mise en œuvre présenté dans le présent rapport, ainsi que les communications efficaces et la sensibilisation permettront une transition facile vers le nouveau service de collecte et l’atteinte des objectifs de la Ville en matière de réacheminement des déchets.

 

Incidences financières

 

Le présent rapport ne fait état d’aucune incidence financière, car tous les coûts associés au programme de Bac vert ont été fournis dans les rapports précédents et approuvés par le Conseil.

 

Incidences juridiques et en matière de gestion du risque

 

Il n’existe aucune entrave d’ordre juridique ou en matière de gestion du risque à recevoir le présent rapport ou à demander au personnel de fournir un rapport au début de l’année 2011.

 


Consultation publique/commentaires des résidents

 

Depuis 1997, on mène une consultation approfondie en ce qui concerne le programme de Bac vert.  Le projet pilote Compost Plus a permis de tester le service de collecte de déchets organiques auprès d’environ 5 000 ménages. Nanos Research a mené un sondage à l’automne 2008 sur une large gamme d’enjeux relatifs aux déchets solides, et, selon les conclusions, la majorité des résidents d’Ottawa connaissent le programme de Bac vert et l’appuient. Le résumé des conclusions du sondage est présenté à l’annexe 4.

 

Contexte et avancement du projet

 

En mai 2008, ACS2008-PWS-SWS-0002, le Conseil a approuvé les niveaux de service suivants pour la collecte des déchets solides, y compris la collecte des bacs verts :

·         poursuivre jusqu’en 2012 la collecte hebdomadaire des déchets et l’alternance de la collecte hebdomadaire des bacs bleus et des bacs noirs, en vertu des contrats en vigueur avec les fournisseurs de services de la Ville;

·         recueillir les déchets organiques aux deux semaines de décembre à mars;

·         recueillir les déchets organiques chaque semaine d’avril à novembre.

 

La collecte des déchets organiques des bacs verts devrait commencer le 4 janvier 2010.

 

En mars 2008, ACS2008-PWS-SWS-0004, le Conseil a accordé à l’entreprise Orgaworld Canada Ltd. le contrat de construire et d’exploiter une installation de traitement des déchets organiques.

 

En novembre 2008, les entreprises Norseman Plastics et Ottawa Mouldcraft ont décroché des contrats pour la fabrication des grands bacs à déchets organiques et des petits bacs pour la cuisine, respectivement.  En avril 2009, l’entreprise Fleishman-Hillard Canada a reçu le mandat d’orchestrer une campagne de communication et de sensibilisation dans le cadre du programme de Bac vert.

 

Avancement du projet :

·         La construction de l’installation de traitement d’Orgaworld se poursuit (la structure extérieure est presque terminée).

·         Environ 50 000 bacs verts sont fabriqués à raison de 1 200 bacs par jour.

·         Le Projet pilote des champions des bacs verts a été lancé.

·         Le moule pour la fabrication des bacs pour la cuisine est prêt.

·         Un plan de communication est en cours d’élaboration.

 

L’annexe 6 présente une note de service envoyée précédemment au sujet de l’achat des bacs verts.

 

 


DISCUSSION

 

1.                  Details on Collection Program Modification

 

In preparation for the changes to the collection program, an implementation plan has been developed, which involves the delivery of the green bin, kitchen container, promotion / information package and preparation for collection (i.e., purchase of collection vehicles). The success of this plan is critically important to the ongoing success of the Green Bin Program. Experience in other municipalities has shown that problems with the roll-out can affect participation in the program.  The plan has been developed to ensure that:

 

·         Delivery is properly scheduled and routed and any missed or other delivery issues are corrected right away;

·         Outreach officers accompany each delivery team to provide personal one-on-one support to residents;

·         Communications are clear so that residents understand the start-up dates and how to participate in the program; and

·         Councillors’ offices, the 311 call centre, delivery crews and Solid Waste staff are in constant contact to resolve issues as they arise.

 

Delivery of Carts

 

The cart vendor, Norseman Plastics, will manage the storage, assembly, packaging and delivery of containers for the first phase of the roll-out. The delivery crews will place the kitchen container and the promotion information into the organics collection cart and deliver it to the household.  Promotional information will include a user guide, two sample organic waste bags (donated to the City) and a coupon to purchase additional bags. Since organics collection will not start until January of 2010, a sticker will be placed on the lid of each cart, informing residents not to place organics in their cart until a week or two prior to the collection commencement date.  Residents will be referred to their collection calendar to find out when their collection will occur. In addition, outreach officers will be assigned to each of the delivery crews to provide personal, one-on-one support for residents as the carts are delivered. The Officers will be knowledgeable and able to answer resident’s questions about the program. They will also have information packages to leave with residents should they require further information. Other municipal experience has shown that this step is critical in minimizing confusion and phone calls / inquiries during the roll-out.

 

Manufacturing of the organics collection carts started in April of this year. The carts will be placed in indoor storage locally in Ottawa prior to delivery, starting in mid-September 2009.  Four storage locations strategically located in the west, centre, east and south of the City have been secured. These storage locations will be used as staging areas to load the smaller delivery vehicles.

 

Staff are working closely with Norseman on the development of an address database for route design to assist with delivery. The database will give a reference for Norseman to register the unique barcode on each cart against the address it was delivered to, providing staff with tracking information for maintenance and warranty purposes.

 

Over the twelve week schedule, carts will be delivered by collection zones, concentrating on one zone at a time. Norseman will provide staff with a daily list of delivered addresses and an area delivery schedule will be made available to Call Centre staff and Members of Council in advance. Staff will provide updates on the progress of the roll-out. 

 

It is important to note that Norseman has experience delivering over 930,000 containers to municipalities such as Toronto, Peel Region and Durham Region.

 

The City’s In House Collection Group, as well as our collection contractors have been officially advised by Supply Branch that collection is scheduled to commence on January 4, 2010. As per the collection contract, the In-House Collection Group and contractors are required to have adequate collection vehicles and labour for the start of collection.

 

A high level timeline of the project, including the roll-out, is included as Document 2.

 

Collection Program – Implementation Phasing

 

It is estimated that about 220,000 of approximately 250,000 curbside collected households will receive green bins in the initial phase of the roll-out. 

 

The remaining curbside households will require changes to set out method or container type in order to participate, and this will require that staff visit these specific sites to discuss with owners and landlords how best to implement an organics solution at their location. This process will start in the fall of 2009 and continue until complete, estimated for 2010. Some of the barriers to implementation include common pad set out, lack of storage space and no suitable access from storage space (backyard) to collection location (curbside). Due to the potential variance in approaches that may be required to implement organics service for these households, they will be implemented on a case-by-case basis.

 

The remaining two phases include high-rise, multi-unit, residential buildings and rural households that did not receive leaf and yard waste / organic collection in the last collection contract. Planning for pilot programs for high-rise, multi-unit, residential buildings will start this year with eventual pilot implementation in 2010. Factors to consider include collection bins, in-unit containers and collection vehicles, etc. Staff will report to Committee and Council on an implementation plan once the preferred option is determined. Finally, for the about 7,000 rural households that did not receive leaf and yard waste or organics collection as per the level of service in the last collection contract, staff are intending to include these households in the level of service for the new collection contract (2012) for Council’s consideration. 

 


Table 1 below summarizes the implementation phases.

 

Table 1

Green Bin Program Implementation Phases

 

Phase

# Households

Housing Type

Set Out

Challenges

Opportunities

Service Delivery Date

1a

220,000

Primarily Single Units

At Curb

None

 

January 2010

1b

30,000

Low-rise multi-units

Common Pad, Private Property, Front end loading container collection

Space for storage & set out, access to set out, site visits required

Front end loading bins, different sized carts, changes to collection set out

January 2010 and ongoing

2

100,000

High-rise, multi-units

High-rise

Space for storage & set out, access to set out, Front end loading container collection

High-rise Green Bin Pilot underway

 

Pilots/research 2009/2010 – recommended system 2011 or sooner

3

7,000

Rural

At Curb

Not in current collection contract

Include in 2012 contract

2012 new contract service level

 

Procedure – Compliance and Monitoring

 

The approximately two and one half months between late September 2009 when the green bins start to be delivered and January 4, 2010 when collection starts will be critical. Staff have developed a procedure in the likely event that some carts will be placed at the curb before collection starts.

 

Should carts be placed out in advance of collection, staff will empty the carts and place a notice on the cart reminding residents that collection doesn’t start until January. The notice will be a sticker that is placed such that it will have to be broken to open the lid.

 

Monitoring of the program will begin immediately after collection begins in January 2010.  There will be two processes; Solid Waste Inspectors providing education on the new program as part of regular by-law enforcement procedures and measuring customer satisfaction through set out studies, phone polls and web based surveys. 

 

As with the City’s other diversion programs, the Blue and Black Box Programs, participation is mandatory. Public education will play the primary role in encouraging the public’s participation in the early stages of the program. When the green bin is contaminated or is not being placed out, an advisory notice will be issued. The experience of Waste Inspectors has been that issuing a notice normally corrects the problem.

 

Client surveys will assist in targeting the Branch’s overall education program. For instance, ongoing promotion may include tips on effective storage of organics.

 

2.                  Organics Processing

 

Orgaworld Canada was awarded the contract to build and operate an organics processing facility for the City’s program. The facility is located at Rideau Road and Hawthorne Road in an industrial area. Construction on the site began in April of this year.

 

A conditional building permit has allowed construction on the exterior shell of the facility to commence and that work is well underway. The permit covers the foundations, walls, roof and structure. The permit covering the interior of the building has been submitted to the City.  Processes to finalize the Subdivision Agreement and Site Plan Agreement are underway as well as Certificate of Approval permits from the Ministry.

 

Orgaworld Canada has advised that the current timelines for the construction of the processing facility are on schedule. Staff have been and will continue to closely monitor the construction progress.

 

The contract with Orgaworld Canada was executed in the spring of 2008 and was based upon the Request for Qualifications (January 2006) and the Request for Proposals (March 2007).  Orgaworld Canada has committed to building a facility capable of processing 100,000 tonnes of organics per year and the City has committed to supply 80,000 tonnes of organics on a put or pay basis.

 

As with all programs involving significant social change and public education, the phase in approach of this Organics Program does represent some risk that the City may not meet its put or pay commitment solely on the residential organics program in the first stage of implementation.

 

To manage this risk, City staff are looking to the recently approved Diversion 2015 Plan to help minimize this shortfall possibility while taking best advantage of available organics processing capacity. As part of the work plan, staff have started proactively meeting with generators and haulers to have IC&I organic collection programs available for January 2010 early implementation. Also, Phase 2 of the implementation schedule as set out in this report (Table 1) has high-rise multi-unit buildings starting in 2011 or sooner. This process may be accelerated pending pilot findings. Finally staff have contacted neighbouring Municipalities to determine potential Organic Program start dates and advise on Ottawa’s processing capabilities. These measures are encouraging and will work towards minimizing the risk to the City’s commitment.

 

Staff will advise Committee and Council on both construction progress and organics processing commitment as required.

 


3.                  Communications Plan

 

Effective communication, education and promotion are integral to the success of the Green Bin Program. Engaging residents in a meaningful way will encourage participation in organics diversion allowing Members of Council and the City to divert significant amounts of organic waste from the landfill.

 

Research

 

Solid Waste Operations conducted a survey of City of Ottawa residents regarding their current attitudes, interests and opinions on recycling and garbage issues. The goal of the survey was to assess depth of knowledge and identify perceptions of recycling and garbage services.

 

The survey questions were developed to gain a baseline understanding of residents’ attitudes towards the City’s waste management programs, identify areas of concern and assess the awareness and understanding of initiatives including the Green Bin Program, the Household Hazardous Waste Program and other recycling and garbage services. A combination of open-ended and closed-ended questions were used to allow for quantification of respondents’ opinions and to probe for additional information. The survey provided geographic representation through our existing waste collection zones as well as a mix of urban and rural participants. 

 

Findings included strong support for solid waste collection services in general and for diversion programs, particularly the Green Bin Program. The complete report is included as Document 4.

 

The Green Bin Program communications motion passed by Council on September 10, 2008, speaks to the need to consult with residents, raise public awareness and address why the City is implementing this program. The research findings have been a valuable resource in the development of the Green Bin communications plan. 

 

Staff will continue to take a consultative approach that includes ongoing public dialogue to help develop and refine our overall communications plan. 

 

Communications Plan Stages

 

The City of Ottawa has developed a multi-phased communications plan that will increase resident awareness and knowledge, and promote participation in the Green Bin Program.  The plan integrates existing City resources and will continue beyond the launch period.  Details of the plan include:

 

Stage 1: Preparation (April – July 2009)

 

This stage is largely devoted to program planning and preparation of foundational elements.  Following the development of the strategic communications plan (see Document 5) and a detailed work plan, efforts will focus on developing the creative concept and brand, program website, and core campaign materials including the User Guide and the Collection Calendar. Efforts will be undertaken to ensure Councillors and community leaders have the resources and information they require to support their constituency and communities through the launch. In addition, the communications team will focus on developing messaging tools and questions and answers to support public-facing staff, including 3-1-1 operators, Council staff and Green Bin liaison officers. 

 

The City of Ottawa Green Bin Champions Pilot Project will give approximately 95 households first-hand experience with organics collection in advance of the Green Bin Program launch. Champions will be using the City of Ottawa’s official green bin and specially designed kitchen container. The feedback provided and the experience gained during this initiative will allow us to better serve the residents of Ottawa as we implement the City-wide program in 2010.

 

Stage 2: Education (August – December 2009)

 

This stage covers the time period immediately before and throughout bin delivery. Activities during this stage will be highly visible and focused on educating Ottawa residents about the Green Bin Program; what it is, how it works, when to expect bins and pick-up, and who will be involved. A multi-faceted approach will be used to ensure information is reaching all Ottawa residents in a range of ways.

 

Community Outreach will play an important role in ensuring all Ottawa residents are informed about this new program and how they can be involved. Current Community Outreach programs will be expanded to include the green bin and some specific outreach efforts will be undertaken specifically for the Green Bin launch, including:

·         Community workshops;

·         Developing or expanding school programs; and,

·         Presence at community events with information for adults and fun activities for kids.

 

Highly-visible and wide-reaching awareness activities will include:

·         Radio, print and television advertising;

·         Outdoor advertising;

·         Interactive web content including social networking; and,

·         Bin delivery launch announcement and media outreach.

Stage 3: Participation (January – March, 2010)

 

This stage marks the start of organics pick-up and the communications focus will shift from education to building participation.  Highly-visible launch events including Members of Council will be held during the early part of January. A second round of advertising will reinforce the details of program participation. Online presence and social networking will continue.

 

During this time, a City-wide community competition will be launched, challenging each of the five collection zones to have the highest organic diversion rates over a three or six month period.

 

 

 

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


ENVIRONMENTAL IMPLICATIONS

 

Implementation of the Green Bin Program will yield several environmental benefits including:

 

 

RURAL IMPLICATIONS

 

Organics collections will be provided to rural residents within a village or country estate subdivision as part of the initial implementation, but not to rural residents outside of a village or country estate. This level of service is consistent with that of leaf and yard waste pickup in rural areas, which is set out in the current collection contract. Further, Council debated this issue at its November 26, 2008 meeting.

 

A report on the level of service will be considered by Committee and Council as part of the development of the 2012 collection contract and it is envisioned that the rural collection of both organics and leaf and yard waste will be included in that report.

 

CONSULTATION

 

Public consultation on the issue of a Source Separated Organics Program has been ongoing since 1997 through various methods and venues, including:

·         Nanos Research (2008) - Survey of residents regarding solid waste services.

·         Genevar Consulting, formerly MacViro (2002) - In preparation of the City of Ottawa’s Integrated Waste Management Master Plan.

·         Decima telephone surveys in 2003 and 2006.

·         The Environmental Advisory Committee was consulted in July 2005 and again in December 2006. 

·         Analysis and reports by David Redmond and Associates of 10 public surveys between 1997 and 2004.

·         Communications report (2003) by Howard Williamson Consulting with a variety of public input (surveys, telephone polls, workshops, etc.).

·         Staff conducted open houses for the various pilot neighborhoods for Compost Plus, as well as monitored and responded to feedback through a dedicated e-mail box for Compost Plus participants.

 

FINANCIAL IMPLICATIONS

 

This report has no financial implications as all costs associated with the Green Bin Program have been identified in previous reports and approved by Council.

 

LEGAL/RISK MANAGEMENT IMPLICATIONS

 

There are no legal/risk management impediments to receiving the information in this report and directing staff to report back in early 2011.

 

SUPPORTING DOCUMENTATION

 

Document 1 - Green Bin Program Containers

Document 2 - Timeline for Roll-out of Green Bin Program

Document 3 - List of Acceptable Green Bin Items

Document 4 - City of Ottawa Solid Waste Survey Report (Executive Summary)Issued Separately

Document 5 - Communications Plan - Issued Separately

Document 6 - Memo to Mayor and Members of Council Green Bin Selection

 

DISPOSITION

 

Solid Waste Operations will implement the plan for roll-out of the Green Bin Program and report back to Council with updates as required throughout 2010.


Document 1

 

Green Bin Containers

 

Kitchen container (Ottawa Mould - Craft Sure Close 6.6)

 

 

 


 

Document 1

 

Green Bin Program Containers

 

Curbside Cart (Norseman - NPL-285)


Document 2

Green Bin Program Project Timeline

 

 

 

 

 

 


Document 3

 

List of Acceptable Green Bin Items

 

Food Waste

 

Non-Food Items


Document 6

M E M O   /   N O T E   D E   S E R V I C E

 

To / Destinataire

Mayor and Members of Council

File/N° de fichier:

From / Expéditeur

General Manager, Environmental Services

 

Subject / Objet

Impartial Tests Required for New Organic Carts

Date:  29 April 2009

 

 

This memo is intended to respond to the concerns expressed regarding the bidding and selection process for the new organic carts. 

 

In accordance with the City of Ottawa Purchasing By-law, an evaluation team was assembled, comprised of three managers of the City's Solid Waste Operations Branch and a consultant with expertise in the subject matter from the engineering firm of Jacques-Whitford.  The City's Supply Management Division facilitated the evaluation process and all proposals were evaluated and scored using a consensus approach, in accordance with the point rated requirement in the RFP document. 

The evaluation process was extensive and each bidder provided a sample container as part of the evaluation process.  The bids were provided using a 2 envelope system, one technical submission and one financial.  The financial envelopes were not opened until the technical evaluation was complete.  We were fortunate that the bin that scored the highest in the technical evaluation process in all areas was also the one that provided the best value to the City.


The Manager of Supply oversaw the procurement process, and confirms that it has been conducted in a fair and unbiased fashion, and the containers selected represent the best value to the City.   The contract has been awarded and the carts are being manufactured. 

 

Comments have been made about potential operational problems associated with the compatibility of the lifters that will be used on the trucks and the containers.  City staff physically tested the containers using both types of lifters that could be used on waste collection vehicles as part of the evaluation process, to make sure the containers would perform properly.  None of the potential operational problems were experienced. 

 

The City requested in the RFP that results of specific independent testing certified by a professional engineer be submitted with the bids.  No concerns about this requirement were expressed by any prospective bidders during the bid preparation process.  Unfortunately, not all bidders complied with the City's RFP process as they did not submit any testing results to illustrate the quality of their container or their ability to meet the requirements as outlined in the RFP, which specified a higher weight tolerance and greater temperature range tolerance than the regular ANSI standards.  Those bidders that did not comply with this requirement were eliminated from further consideration.

 

Norseman Plastics, the successful bidder was the only one to submit the required testing results and their bin satisfied the testing requirement.  The tests were conducted by an independent laboratory, Bodycote Ortech, which is a worldwide company specializing in material testing, research, consultation and analysis.  Bodycote Ortech provided accurate and complete information for our analysis and performance evaluation results, certified by a professional engineer licensed to practice in Ontario.  We have no reason to doubt the validity or the quality of the testing, nor is there a need for additional testing, we have no issue with the testing provided or with the quality of the container selected.

 

Norseman Plastics, is a well-respected company with a proven track record in design and manufacturing of environmental and recycling containers.  Their bin comes with a 10 year warranty against defects and staff firmly believe that it will work effectively and efficiently with the City's (and waste contractor's) current equipment, and will provide exceptional service as we move forward.   
 

In summary, the Norseman green bins represent the best value to the City as these bins achieved the highest technical score; were judged to be the most durable, the best overall container and the lowest price.

 

Should you require further information, please feel free to contact Kevin Wylie, A/Manager, Solid Waste Operations at extension 19013.

 

 

Original Signed By

 

Dixon Weir, P.Eng.

General Manager

Environmental Services

 

 

cc:     Executive Management Committee

         Kevin Wylie, Manager, Solid Waste Services